Resolved
Resolved that a mechanism be put in place for notifying Members of emergency works by utility companies.
Gravesham Joint Transportation Board decided this item on Wednesday 9 December 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that a mechanism be put in place for notifying Members of emergency works by utility companies.
To: Gravesham Joint Transportation Board
By: KCC Highways, Transportation & Waste
Date: 9th December 2015
Subject: Highway Works Programme 2015/16
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction in 2015/16
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2015/16
Footway and Carriageway Improvement Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D Casualty Reduction Measures – Appendix D1 Local Growth Fund – Appendix D2
Developer Funded Works – see Appendix E
Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Member Fund – see Appendix H
Conclusion
1. This report is for Members information. Contact Officers:
The following contact officers can be contacted on 03000 418181
Carol Valentine Highway Manager (West) Lisa Gillham Gravesham District Manager Alan Casson Resurfacing Manager Katie Moreton (Lewis) Drainage Manager Sue Kinsella Street Lighting Manager Toby Butler Intelligent Transport Systems Manager Melvyn Twycross PROW Tony Ambrose Structures Manager Jamie Hare Developer Funded Work Jamie Watson Transportation and Safety Schemes Kirstie Williams Combined Member Fund Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer [name removed] Name Parish Extent of Works Current Status
From Zion Street to A227 Wrotham Road Gravesend Wingfield Road Completed (Full Reconstruction) A227 Wrotham Road Across junction Johns Road Meopham Completed and both North and South
Footway Improvement - Contact Officer [name removed] its junction with Waterlow Road (West footway) and various sections Completed Churchside (East) Vigo of internal footways serving properties. (Footway Reconstruction) From the junction with Medhurst Crescent for its Works commenced Medhurst Gardens Gravesend Entire Length on site and on-going. (Footway Reconstruction)
Farmcroft Gravesend Entire Length. Completed (Footway Reconstruction)
Appendix B – Drainage
Drainage Works – Contact Officer Katie Moreton (Lewis)
Road Name Parish Description of Works Current Status
No Drainage works planned over £5000 Appendix C – Street Lighting
Structural testing of KCC owned street lights has identified the following as requiring replacement this financial year. A status of complete identifies that the column replacement has been carried out. Programme dates are identified for those still requiring replacement.
Street Lighting Column Replacement – Contact Officer Sue Kinsella
Road Name Parish Description of Works Status
Replacement of 2 no street light complete Works Programmed for Earl Road Gravesend with LED Lanterns Completion by December 2015
Homemead Replacement of 1 no street lights complete Works Programmed for Gravesend Close with LED Lanterns Completion by December 2015
Replacement of 2 no street light complete Works Programmed for New Road Gravesend with LED Lantern Completion by December 2015
Old Road Replacement of 1 no street lights complete Works Programmed for Gravesend West with LED Lanterns Completion by December 2015
Replacement of 2 no street lights complete Works Programmed for Barr Road Gravesend with LED Lanterns Completion by December 2015
Replacement of 6 no street lights complete Works Programmed for Burch Road Gravesend with LED Lanterns Completion by December 2015
Replacement of 5 no street lights complete Works Programmed for Chalk Road Gravesend with LED Lanterns Completion by December 2015
Clifton Marine Replacement of 5 no street lights complete Works Programmed for Gravesend Parade with LED Lanterns Completion by December 2015
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Works Programme 2015/16Report | 143 KB | DownloadRead as text |
Follow Gravesham Joint Transportation Board at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2021 | Bath Street - Fastrack Infrastructure SchemeResolved that the report be noted. | Noted | Open |
| 10 Mar 2021 | Highway Forward Works Programme - 2019/20 onwardsResolved the report be noted. | Noted | Open |
| 10 Mar 2021 | Issues raised by Councillors with the approval of the ChairIt was agreed that the results of the ATC be shared with Cllr Rana. It was noted that the officer had previously disc... | Agreed | Open |
| 14 Mar 2018 | Gravesham Highway Works Programme 2017/18Resolved that the Board noted the information contained within the report and agreed the following: · The Gravesham D... | Noted | Open |
| 14 Mar 2018 | Petitions from residents at the JTB (KCC Petition Scheme)Resolved that the Board look at the original JTB Legal Agreement between KCC and GBC with the view to amending it to ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.