Greater Manchester Combined Authority, Friday 25 September 2026

Capital Programme Outturn 2025/26

Noted Committee 1 paper

AI summaryGMCA noted 2025/26 capital outturn of £497.6m, against a £585.9m February 2026 forecast, with most underspend rephased to 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted2025/26 spend was £497.6m against a £585.9m forecast
Money£497.6m actual, £585.9m forecastVariance of 88,245 in £000s, mostly timing
What happens nextContinued monitoring in 2026/27Pending audit of the Statement of Accounts
Who it affectsGMCA capital programmeTransport, fire, regeneration, waste schemes

What was decided

GMCA noted the 2025/26 actual outturn capital expenditure of £497.6m, compared to the forecast of £585.9m presented to GMCA on 13 February 2026. Report P7, 1.3

Why

Most of the variance reflects timing differences rather than permanent savings, with budgets rephased into 2026/27 to match revised delivery schedules. Report 4.7, 1.4

What happens next

The figures are a draft ahead of the audit of the Statement of Accounts, though no material changes are anticipated. Report 1.4

Officers will continue monitoring rolled-forward budgets in 2026/27 against updated project plans and milestones. Report 4.7

The money

  • £497.6m Actual outturn capital expenditure 2025/26 Report P7, 1.3, P182
  • £585.9m Forecast capital expenditure presented to GMCA on 13 February 2026 Report P7, 1.3, P182
  • 88,245 (£'000) Total (Increase)/Decrease between Q3 forecast and 2025/26 outturn Report P182
  • 279,695 (£'000) Transport outturn 2025/26 Report P158, P169
  • 176,656 (£'000) Economic Development and Regeneration outturn 2025/26 Report P158, P177
  • 21,850 (£'000) Fire and Rescue outturn 2025/26 Report P158, P179
  • 19,406 (£'000) Waste and Resources outturn 2025/26 Report P158, P181

Options considered

  • Chosen: Note the actual outturn position. Members were asked to note the position against the February 2026 forecast Report P6, P7

Implications

  • Financial: Most underspend relates to rephasing of grant-funded schemes into 2026/27; budgets are not removed but rolled forward. Report 4.7, 1.4
  • Risk: A significant proportion of the capital budget is funded through grant; claw back risk is mitigated by careful monitoring against grant conditions. Report P14
  • Equalities: No specific equalities, carbon or sustainability issues are identified in this report. Report P13
  • Legal: No specific legal implications are contained in the report. Report P15

Who and where

  • Greater Manchester residents and businesses using transport infrastructure including Metrolink, bus, rail and active travel Report 2.1, 2.2, 2.7
  • Greater Manchester Fire and Rescue Service across estates, transport, ICT, equipment and sustainability Report 4.1, 4.2, 4.3, 4.4, 4.5
  • Registered social housing providers and low income households eligible for Warm Homes funding Report 3.10, 3.11
  • Looked After Children in Greater Manchester who may be placed in Project Skyline homes Report 3.14
  • GM Local Authorities delivering highway and active travel schemes Report 2.10, 2.7

Timeline

  • 7 February 2025: GMCA approved the 2025/26 capital programme Report P20
  • 26 September 2025: Capital Update Q1 2025/26 presented to GMCA Report P21
  • 12 December 2025: Capital Update Q2 2025/26 presented to GMCA Report P22
  • 13 February 2026: GMCA Capital Programme 2025/26 to 2028/29 and forecast outturn presented Report P23
  • 25 September 2026: Capital outturn 2025/26 reported to GMCA Report P2, P7

Plain English for the jargon

  • GMCA: Greater Manchester Combined Authority
  • TfGM: Transport for Greater Manchester
  • GMFRS: Greater Manchester Fire and Rescue Service
  • Bee Network: Greater Manchester's plan for an integrated public transport and active travel system
  • CRSTS: City Region Sustainable Transport Settlement
  • MREP: Metrolink Renewals and Enhancements Programme
  • MCIP: Metrolink Capacity Improvement Package
  • ZEB: Zero Emission Buses
  • HILF: Housing Investment Loans Fund
  • LAC: Looked After Children
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9A

Resolved

That the 2025/26 actual outturn capital expenditure of £497.6m, compared to the forecast position of £585.9m presented to GMCA on 13 February 2026, be noted.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Greater Manchester Combined Authority

Greater Manchester Combined Authority

Date: 25 September 2026

Subject: Capital Outturn 2025/26

Report of: Councillor Nazia Rehman, Portfolio Lead for Resources and Investments and Steve Wilson, GMCA Group Chief Finance Officer

Purpose of Report This report is to inform members of the Greater Manchester Combined Authority of the capital outturn for 2025/2026.

Recommendations: The GMCA is requested to:

1. Note the 2025/26 actual outturn capital expenditure of £497.6m compared to the forecast position presented to GMCA on 13 February 2026 of £585.9m.

Contact Officers Name: Steve Wilson, Group Chief Finance Officer, GMCA

Telephone: 0161 778 7004

E-Mail: [email protected]

Name: Matt Bull, Director of Finance, Commercial and Corporate Services, Transport for Greater Manchester

Telephone: [phone removed]

E-mail: [email removed] Equalities Impact, Carbon and Sustainability Assessment: There are no specific equalities impact, carbon and sustainability issues contained within this report.

Risk Management An assessment of major budget risks faced by the authority are carried out quarterly as part of the reporting process – at the present time a significant proportion of the capital budget is funded through grant. In order to mitigate the risk of monetary claw back the full programme is carefully monitored against the grant conditions and further action would be taken as necessary.

Legal Considerations There are no specific legal implications contained within the report.

Financial Consequences – Revenue There are no specific revenue considerations contained within the report.

Financial Consequences – Capital The report details the actual capital expenditure for 2025/26

Number of attachments to the report: None

Comments/recommendations from Overview & Scrutiny Committee N/A

Background Papers GMCA Capital Programme 2024/25 - 2027/28, GMCA 7 February 2025

Capital Update Q1 2025/26, GMCA 26 September 2025

Capital Update Q2 2025/26, GMCA 12 December 2025

GMCA Capital Programme 2025/26 - 2028/29, GMCA 13 February 2026

Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution

No Exemption from call in

Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?

None

Bee Network Committee

N/A

Overview and Scrutiny Committee N/A 1. Introduction/Background 1.1. The Greater Manchester Combined Authority approved the 2025/26 capital programme at its meeting on 7 February 2025. Updated forecast outturns were provided on a quarterly basis during 2025/26 with the latest forecast being presented on 13 February 2026.

1.2The Authority’s capital programme, funded from a number of sources and grants, includes Greater Manchester Fire and Rescue Services (GMFRS), Economic Development & Regeneration programmes, Waste & Resources Service and the continuation of the programme of activity currently being delivered by the Authority, Transport for Greater Manchester (TfGM) and GM Local Authorities (LA) including the following elements:

a) Metrolink schemes;

b) Future Rapid Transit programme;

c) Rail schemes;

d) Interchange schemes;

e) Clean Air schemes;

f) Active Travel schemes;

g) Bus Infrastructure schemes;

h) Bus Franchising schemes;

i) Local Authority highways schemes;

j) Other capital projects and programmes; and

k) Capital Highways Maintenance, Traffic Signals and Full Fibre.

1.3The actual expenditure for 2025/26 was £497.6m, compared to a forecast for 2025/26 presented to GMCA 13 February 2026 of £585.9m. This is summarised in Appendix A and the major variances are described in this report. The financing of capital expenditure in 2025/26 is provided in section 6.

1.4It should be noted that this report is a draft of the expected outcome of the 2025/26 capital outturn position, ahead of the audit of the Statement of Accounts, however it is not anticipated that there will be any material changes to the position presented in this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Outturn 2025/26Report 317 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 12 attended
GM
GM Mayor Bev CraigChair, expected
RR
Rachael RobinsonCouncil Staff, expected
SK
Shelley KiplingCouncil Staff, expected
EW
Councillor Eleanor WillsCommittee Member, expected
TR
Councillor Tom RossCommittee Member, expected
NE
Councillor Neil EmmottCommittee Member, expected
EO
Councillor Eamonn O'BrienCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
NR
Councillor Nazia RehmanCommittee Member, expected
MR
Councillor Mark RobertsCommittee Member, expected
AZ
Councillor Akhtar ZamanCommittee Member, expected
AS
Councillor Arooj ShahCommittee Member, expected

On this subject at Greater Manchester Combined Authority

Search all
  1. Capital Programme Outturn 2025/26This decision
  2. Capital Programme and Asset Management UpdateNoted
  3. GMCA Capital Programme 2025/26 - 2028/29Noted
  4. GMCA Capital Programme -2024/25 - 2027/28Noted
  5. 2024-25 Capital Programme and Asset Management UpdateNoted
  6. Transport Capital ProgrammeNoted

More from Greater Manchester Combined Authority Greater Manchester Combined Authority

All decisions
MeetingDecisionOutcome
25 Sep 2026 ApologiesThat apologies be received from Councillor Eleanor Wills (Tameside), with Councillor Andrew Mclaren attending as subs... Decided Open
25 Sep 2026 Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities... Decided Open
25 Sep 2026 Declarations of InterestThat it be noted that no declarations of interest were received. Noted Open
25 Sep 2026 GMCA Minutes - 10 July 2026That the minutes of the GMCA meeting held on 10 July 2026 be approved. Approved Open
25 Sep 2026 Bee Network Committee - 25 June 2026That the proceedings of the Bee Network Committee held on 25 June 2026 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies