That the current position, recent progress and key milestones on the transport infrastructure pipeline be noted. 2. That the drawdown of CRSTS funding and associated scheme progression be approved as follows: • Bus Pinch Points and Maintenance Programme: £6.457m • Improving Journeys: Early Interventions: £0.6m and Full Business Case; and • Bee Network Rail Integration: £15.5m 3. That it be noted that the following CRSTS drawdown was approved by the Group Chief Executive TfGM and GMCA under delegated authority of £0.496m for the Rapid Transit Extensions Package 4. That the return of £0.9m to the Mayor’s Challenge Fund (MCF) from the Oldham Town Centre: Rock Street/Lord Street and allocation to the Oldham Town Centre: Market Place scheme be noted. 5. That approval be given to the associated drawdown of funding and scheme progression: • Wigan: Leigh Neighbours: £0.92m Active Travel Funding and Full Business Case; and • Oldham: Town Centre Market Place: £4.58m Active Travel Funding, £0.9m of MCF funding, and Full Business Case.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Bee Network Committee Date: Thursday 27th March 2025
Subject: Transport Infrastructure Pipeline
Report of: Chris Barnes, Network Director Infrastructure, TfGM
Purpose of Report This report provides an update on progress delivering a pipeline of transport infrastructure improvements to support the Bee Network: a high-quality, affordable and fully integrated public transport and active travel system which can support sustainable economic growth. The report makes a number of recommendations for members to support the continued development and delivery of the pipeline programme.
Recommendations: The Committee is requested to:
1. Note the current position, recent progress and key milestones on the transport infrastructure pipeline; 2. Approve the drawdown of CRSTS funding and associated scheme progression as follows: • Bus Pinch Points and Maintenance Programme: £6.457m; • Improving Journeys: Early Interventions: £0.6m and Full Business Case; and • Bee Network Rail Integration: £15.5m; 3. Note the following CRSTS drawdown as approved by the Group Chief Executive TfGM and GMCA under delegated authority of £0.496m for the Rapid Transit Extensions Package; 4. Note the return of £0.9m to the Mayor’s Challenge Fund (MCF) from the Oldham Town Centre: Rock Street/Lord Street and allocation to the Oldham Town Centre: Market Place scheme; 5. Approve the associated drawdown of funding and scheme progression: • Wigan: Leigh Neighbours: £0.92m Active Travel Funding and Full Business Case; and • Oldham: Town Centre Market Place: £4.58m Active Travel Funding, £0.9m of MCF funding, and Full Business Case.
Contact Officers Chris Barnes Network Director, Infrastructure, TfGM [email removed]
Richard Nickson Network Director, Active Travel, TfGM [email removed] Equalities Impact, Carbon and Sustainability Assessment: Recommendation - Key points for decision-makers Insert text
Impacts Questionnaire Impact Indicator Result Justification/Mitigation Equality and Inclusion G Health G Resilience and G Adaptation Housing Economy Mobility and G Connectivity Carbon, Nature and G Environment Consumption and Production
Contribution to achieving the GM Carbon Neutral 2038 target
Further Assessment(s): Equalities Impact Assessment and Carbon Assessment Positive impacts overall, Mix of positive and Mostly negative, with at G whether long or short A negative impacts. Trade- R least one positive aspect. RR Negative impacts overall. term. offs to consider. Trade-offs to consider.
Carbon Assessment Overall Score 0.93
Buildings Result Justification/Mitigation New Build residential N/A
New build non- residential (including N/A public) buildings Transport Active travel and public 1.14 transport Roads, Parking and N/A Vehicle Access Access to amenities 1 Vehicle procurement N/A Land Use Land use 0.5
High standard in Mostly best practice Partially meets best Not best practice No associated terms of practice with a good level of practice/ awareness, and/ or insufficient carbon impacts and awareness on awareness on significant room to awareness of carbon expected. carbon. carbon. improve. impacts.
Risk Management The recommendations of this report will enable the continued development and delivery of the Bee Network infrastructure pipeline and prioritised infrastructure expenditure. This will mitigate the programme risk of not fully expending the funding awarded by Government. A programme risk register is maintained and updated regularly by TfGM.
Legal Considerations There is a significant contract workstream supporting the delivery of the Capital Programme which is being supported and delivered by both internal and external legal teams. The Legal Delivery/Funding Agreements in respect of the allocation of MCF, Active Travel and CRSTS funding will be produced and implemented for full scheme and development costs approvals as appropriate using the template agreements agreed with GMCA. Financial Consequences – Revenue
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Bee Network Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.