That the current position, recent progress and key milestones on the transport infrastructure pipeline be noted. 2. That DfT approval of the following Monitoring and Evaluation Reports be noted: • Cross City Bus and Busway; and • Rochdale Interchange; 3. That approval be given to the drawdown of Integrated Settlement (CRSTS) funding and associated scheme progression as follows: • Bury Interchange Phase 1: Metrolink Access and Platform Improvement Works: £1.318m; • Stop Improvements and New Stops Package: £2.539m, including local contribution; • Improving Journeys: Wigan – Leigh Orbital Corridor (Advanced Utility Diversions): £0.144m • Bolton: Farnworth Streets for All Town Centre (and Full Business Case): £4.87m; • Stockport: Town Centre West (and Full Business Case): £2.53m, including local contribution; and • Trafford Electric Vehicle Charging Infrastructure (and Full Business Case): £0.501m. 4. That approval be given to the amendments to previously approved Active Travel scheme budgets as set out in section 4. 5. That a future discussion take place to consider how to improve the speed of governance around funding approvals following the onset of devolution.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Bee Network Committee Date: Thursday 29th May 2025
Subject: Transport Infrastructure Pipeline
Report of: Chris Barnes, Network Director Infrastructure, TfGM
Purpose of Report This report provides an update on progress delivering a pipeline of transport infrastructure improvements to support the Bee Network: a high-quality, affordable and fully integrated public transport and active travel system which can support sustainable economic growth and the wider GM Integrated Pipeline. The report makes a number of recommendations for members to support the continued development and delivery of the transport pipeline programme.
Recommendations: The Committee are requested to:
1. Note the current position, recent progress and key milestones on the transport infrastructure pipeline; 2. Note DfT approval of the following Monitoring and Evaluation Reports: • Cross City Bus and Busway; and • Rochdale Interchange; 3. Approve the drawdown of Integrated Settlement (CRSTS) funding and associated scheme progression as follows: • Bury Interchange Phase 1: Metrolink Access and Platform Improvement Works: £1.318m; • Stop Improvements and New Stops Package: £2.539m, including local contribution; • Improving Journeys: Wigan – Leigh Orbital Corridor (Advanced Utility Diversions): £0.144m • Bolton: Farnworth Streets for All Town Centre (and Full Business Case): £4.87m; • Stockport: Town Centre West (and Full Business Case): £2.53m, including local contribution; and • Trafford Electric Vehicle Charging Infrastructure (and Full Business Case): £0.501m. 4. Approve the amendments to previously approved Active Travel scheme budgets as set out in section 4.
Contact Officers Chris Barnes Network Director, Infrastructure, TfGM [email removed]
Richard Nickson Network Director, Active Travel, TfGM [email removed] Equalities Impact, Carbon and Sustainability Assessment: Recommendation - Key points for decision-makers Insert text
Impacts Questionnaire Impact Indicator Result Justification/Mitigation Equality and Inclusion G Health G Resilience and G Adaptation Housing Economy Mobility and G Connectivity Carbon, Nature and G Environment Consumption and Production
Contribution to achieving the GM Carbon Neutral 2038 target
Further Assessment(s): Equalities Impact Assessment and Carbon Assessment Positive impacts overall, Mix of positive and Mostly negative, with at G whether long or short A negative impacts. Trade- R least one positive aspect. RR Negative impacts overall. term. offs to consider. Trade-offs to consider.
Carbon Assessment Overall Score 0.846154
Buildings Result Justification/Mitigation New Build residential N/A Residential building(s) N/A renovation/maintenance New build non- residential (including N/A public) buildings Transport Active travel and public 1 transport Roads, Parking and N/A Vehicle Access Access to amenities 1 Vehicle procurement N/A Land Use Land use 0.5
High standard in Mostly best practice Partially meets best Not best practice No associated terms of practice with a good level of practice/ awareness, and/ or insufficient carbon impacts and awareness on awareness on significant room to awareness of carbon expected. carbon. carbon. improve. impacts.
Risk Management The recommendations of this report will enable the continued development and delivery of the Bee Network infrastructure pipeline and prioritised infrastructure expenditure. This will mitigate the programme risk of not fully expending the funding awarded by Government. A programme risk register is maintained and updated regularly by TfGM.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Bee Network Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.