Bee Network Committee, Tuesday 19 August 2025 at 10.00am

Transport Infrastructure Pipeline

Noted Committee 1 paper

Bee Network Committee noted this item on Tuesday 19 August 2025. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That the current position, recent progress and key milestones on the transport infrastructure pipeline be noted. 2. That the drawdown of Integrated Settlement funding and associated scheme progression be approved as follows: · Rapid Transit Extensions Package: £6.190m; and · Salford Rise: £3.4m and Full Business Case. 3. That the proposed allocations of capital funding from Active Travel Fund 4, Active Travel Fund 5 and the Consolidated Active Travel Fund, to be considered for approval by GMCA on 22 nd August 2025 be noted. 4. That the drawdown of active travel capital fund, subject to GMCA approval of the overall allocations on 22 nd August 2025, be approved as follows: · Active Travel Remedial Works: £1.1m; · Cycle Hire: £0.5m; · Secure Cycle Parking: £0.5m; and · Wayfinding: £0.5m. 5. That the proposed allocations of revenue funding from Active Travel Fund 4, Active Travel Fund 5 and the Consolidated Active Travel Fund, to be considered for approval by GMCA on 22nd August 2025 be noted.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Bee Network Committee

Bee Network Committee Date: Tuesday 19th August 2025

Subject: Transport Infrastructure Pipeline

Report of: Chris Barnes, Network Director Infrastructure, TfGM

Purpose of Report This report provides an update on progress delivering a pipeline of transport infrastructure improvements to support the Bee Network: a high -quality, affordable and fully integrated public transport and active travel system which can support sustainable economic growth and the wider GM Integrated Pipeline. The report makes a number of recommendations for members to support the continued development and delivery of the pipeline programme.

Recommendations: The Committee are requested to:

1. Note the current position, recent progress and key milestones on the transport infrastructure pipeline. 2. Approve the drawdown of Integrated Settlement funding and associated scheme progression as follows: • Rapid Transit Extensions Package: £6.190m; and • Salford Rise: £3.4m and Full Business Case. 3. Note the proposed allocations of capital funding from Active Travel Fund 4, Active Travel Fund 5 and the Consolidated Active Travel Fund, to be considered for approval by GMCA on 22nd August 2025; 4. Approve the drawdown of active travel capital fund, subject to GMCA approval of the overall allocations on 22nd August 2025, as follows: • Active Travel Remedial Works: £1.1m; • Cycle Hire: £0.5m; • Secure Cycle Parking: £0.5m; and • Wayfinding: £0.5m. 5. Note the proposed allocations of revenue funding from Active Travel Fund 4, Active Travel Fund 5 and the Consolidated Active Travel Fund, to be considered for approval by GMCA on 22nd August 2025.

Contact Officers Chris Barnes Network Director, Infrastructure, TfGM [email removed]

Richard Nickson Network Director, Active Travel, TfGM [email removed] Equalities Impact, Carbon and Sustainability Assessment: Recommendation - Key points for decision-makers Insert text

Impacts Questionnaire Impact Indicator Result Justification/Mitigation Equality and Inclusion G Health G Resilience and G Adaptation Housing Economy Mobility and G Connectivity Carbon, Nature and G Environment Consumption and Production

Contribution to achieving the GM Carbon Neutral 2038 target

Further Assessment(s): Equalities Impact Assessment and Carbon Assessment Positive impacts overall, Mix of positive and Mostly negative, with at G whether long or short A negative impacts. Trade- R least one positive aspect. RR Negative impacts overall. term. offs to consider. Trade-offs to consider.

Carbon Assessment Overall Score 0.857143

Buildings Result Justification/Mitigation New Build residential N/A Residential building(s) N/A renovation/maintenance New build non- residential (including N/A public) buildings Transport Active travel and public 1 transport Roads, Parking and N/A Vehicle Access Access to amenities 1 Vehicle procurement N/A Land Use Land use 0.5

High standard in Mostly best practice Partially meets best Not best practice No associated terms of practice with a good level of practice/ awareness, and/ or insufficient carbon impacts and awareness on awareness on significant room to awareness of carbon expected. carbon. carbon. improve. impacts.

Risk Management The recommendations of this report will enable the continued development and delivery of the Bee Network infrastructure pipeline and prioritised infrastructure expenditure. This will mitigate the programme risk of not fully expending the funding awarded by Government. A programme risk register is maintained and updated regularly by TfGM.

Legal Considerations There is a significant contract workstream supporting the delivery of the Capital Programme which is being supported and delivered by both internal and external legal teams. The Legal Delivery/Funding Agreements in respect of the allocation of MCF, Active Travel and CRSTS funding will be produced and implemented for full scheme and development costs approvals as appropriate using the template agreements agreed with GMCA.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transport Infrastructure PipelineReport 791 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 18 attended
GM
GM Mayor Andy BurnhamChair, expected
EO
Councillor Eamonn O'BrienVice-Chair, expected
HK
Councillor Hamid KhurramCommittee Member, expected
AQ
Councillor Alan QuinnCommittee Member, expected
TR
Councillor Tracey RawlinsCommittee Member, expected
JC
Councillor Josh ChartersCommittee Member, expected
PB
Councillor Phil BurkeCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
GB
Councillor Grace BaynhamCommittee Member, expected
SH
Councillor Stephen HomerCommittee Member, expected
AW
Councillor Aidan WilliamsCommittee Member, expected
PP
Councillor Paul PrescottCommittee Member, expected

All 18 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. Transport Infrastructure PipelineThis decision
  2. Transport Infrastructure PipelineNoted
  3. Transport Infrastructure PipelineNoted
  4. Transport Infrastructure PipelineNoted
  5. Transport Infrastructure PipelineApproved
  6. Transport Infrastructure PipelineNoted

More from Greater Manchester Combined Authority Bee Network Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 ApologiesApologies were received and noted from Cllr Nazia Rehman (Wigan), City Mayor Paul Dennett (Salford), Cllr Stephen Hom... Noted Open
24 Sep 2026 Appointment UpdatesThat the update on the appointments made at the June meeting of the GMCA be noted. 2. That the appointments of the Ma... Noted Open
24 Sep 2026 Appointments to Outside BodiesThat the appointment of Cllr Barry Winstanley, Cllr Grace Baynham & Cllr Michael Welton to the Greater Manchester Acc... Noted Open
24 Sep 2026 Terms of Reference & Rules of ProcedureThat the terms of reference and rules of procedure be noted. Noted Open
24 Sep 2026 Declarations of InterestThere were none. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies