Resolved
Resolved/- That the report be noted.
Greater Manchester Waste & Recycling Committee noted this item on Wednesday 17 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved/- That the report be noted.
The Committee is recommended to: 1. Note and comment on matters set out within the report.
Contact Officers
Michael Kelly Head of Engineering and Asset Management, Waste and Resources [email protected] Equalities Impact, Carbon, and Sustainability Assessment:
There are no equalities impacts arising from the matters set out in this report. A fundamental principle of the WRMS and HWRCMS contracts is the sustainable management of waste to reduce carbon emissions from landfill disposal. The carbon impacts of the contracts are monitored and provided annually by the contractor.
Performance of the contracts and associated risks are captured in the GMCA corporate risk register.
Legal Considerations
Activities set out in this report are in accordance with the terms of the WRMS and HWRCMS contracts.
Financial Consequences – Revenue
Activities set out in this report are in accordance with the Waste revenue budget.
Financial Consequences – Capital
Activities set out in this report are in accordance with the Waste capital budget.
Number of attachments to the report:
None
Comments/recommendations from Overview & Scrutiny Committee
N/A
Background Papers N/A Tracking/ Process
Does this report relate to a major strategic decision, as set out in the GMCA Constitution
No
Exemption from call in Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
No
GM Transport Committee N/A
Overview and Scrutiny Committee N/A 1. Introduction This report provides members with updates relating to the Waste and Resources team asset portfolio. Updates are provided for key projects undertaken in quarter 1 of 2024-25. The waste estate is managed by the Engineering Team and comprises of the following three assets categories:
1.1Category A - Operational Waste Facilities
• WRMS Contract Facilities – Lot 1 (28) waste processing and reception facilities across 11 locations. • WRMS Contract – Lot 2 (11) Household Waste Recycling Centres HWRC’s
1.2Category B - Buildings and Land
• Land and building premises separate to operational locations.
1.3Category C - Closed Landfill Sites
• 4 former dilute and disperse landfill sites now closed and requiring ongoing management.
2. Category (A) Updates – Operational Waste Facilities
2.1Reliance Street HWRC
Background - A modified HWRC is required at Reliance Street in Newton Heath, Manchester due to the existing facility being beyond its economic life span and the restricted layout which does not encourage high-levels of recycling. A new improved HWRC will provide a larger facility giving more capacity to receive, manage and recycle commodities by providing 16 individual containers to segregate materials like many of our other HWRC’s across the region.
Current Position – Additional ground investigations were undertaken in May to provide clarity on existing conditions as initial investigations undertaken last year did not provide sufficient reassurances that ground conditions were suited to the proposed design. This additional review provided 17 cone penetration tests (CPT’s) alongside 3 borehole cores. Boreholes were cored to depths of more than 30 metres to locate underlying bedrock. Data obtained from the latest investigations will be reviewed to define the site soil properties and inform the final ground structure design.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2024-25 Capital Programme and Asset Management UpdateReport | 203 KB | DownloadRead as text |
Follow Greater Manchester Waste & Recycling Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 11 Mar 2026 | ApologiesTo note the apologies for absence received from Councillor Sue Maitland (Trafford) Subs: Gina Reynolds (Salford) Apol... | Noted | Open |
| 11 Mar 2026 | Chairs Announcements and Urgent BusinessThat the Committee notes the sad loss of Councillor David Lancaster MBE and acknowledges the significant contribution... | Decided | Open |
| 11 Mar 2026 | Declarations of InterestThere were no declarations of interest reported. | Decided | Open |
| 11 Mar 2026 | Greater Manchester Waste & Recycling Committee Minutes 21 January 2026That the minutes of the meeting held on 21 January 2026 be approved as a correct record. | Approved | Open |
| 11 Mar 2026 | Contracts UpdateThat the performance of the Waste and Resource Management contracts be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.