That the Executive approves 1) the transfer of £1,150,000 from Woodbridge Road scheme PL29(p) on the provisional capital programme to the approved capital programme 2) a provisional capital virement of £550,000 from the capital contingency fund (scheme FS1) for the refurbishment of the Woodbridge Road Sportsground Pavilion, and delegate authority to the Lead Councillor and Head of Financial Services to provide final approval of the virement subject to the outcome of the value engineering exercise and examination of possible further external funding streams 3) the use of relevant section 106 contributions, as outlined in paragraph 7.2 of the report submitted to the Executive, to part finance the scheme 4) the disposal of the groundsman’s cottage (subject to Charity Commission approval) Reason for To enable the project for the refurbishment of the Woodbridge Road Sportsground Pavilion to proceed to tender and award of the building works contract. Alternative options considered and rejected by the Executive: · To withdraw support for this project: · To await the garnering of all anticipated contributions before proceeding: Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None To enable the project for the refurbishment of the Woodbridge Road ... view the full minutes text for item EX26
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Executive Report Ward(s) affected: Friary & St Nicolas Report of Director of Environment Author: Paul Stacey Tel: 01483 444720 Email: [email protected] Lead Councillor responsible: Richard Billington Tel: 01483 203206 Email: [email protected] Date: 19 July 2016
Woodbridge Road Sportsground Pavilion Refurbishment Approval of Capital Funding
Executive Summary The refurbishment of the Woodbridge Road Sportsground Pavilion is listed in the Council’s Corporate Plan, in order to upgrade the current out-of-date facility through working with partners. The project is included in the Council’s draft capital programme, with a budget of £1,150,000. £200,000 is in the approved capital programme towards professional fees giving a total budget of £1,350,000. The current estimated total cost is now £1,640,000. This report requests approval to transfer £1,150,000 from the provisional capital programme to the approved capital programme, and a capital virement of £290,000 from the capital contingency fund in order to enable the project to proceed to tendering the building works contract. It is estimated that this total cost of £1,640,000 will be offset by £496,000 in Section 106 contributions, £300,000 in grants (from Surrey County Cricket Club and Guildford Cricket Club) and £575,000 future capital receipts generated through a capital disposal. This will make the Council’s net capital contribution £269,000.
Recommendation to Executive That the Executive approves 1) the transfer of £1,150,000 from Woodbridge Road scheme PL29(p) on the provisional capital programme to the approved capital programme 2) a capital virement of £290,000 from the capital contingency fund (scheme FS1) for the refurbishment of the Woodbridge Road Sportsground Pavilion. 3) the use of relevant section 106 contributions, as outlined in paragraph 7.2 of this report, to part finance the scheme 4) the disposal of the groundsman’s cottage (subject to Charity Commission approval) Reason for Recommendation: To enable the project for the refurbishment of the Woodbridge Road Sportsground Pavilion to proceed to tender and award of the building works contract. 1. Purpose of Report
1.1The purpose of this report is to set out the background to the proposed refurbishment of the facilities at Woodbridge Road Sportsground Pavilion, which are required as the facilities are dated, life expired, do not meet modern standards and disadvantage the objectives of the Woodbridge Road Sportsground Charity. We have an opportunity to work in partnership with Surrey County Cricket Club (SCCC) and Guildford Cricket Club (GCC) to develop the facilities for the benefit of the Woodbridge Road Sportsground Charity.
1.2The refurbishment of the Woodbridge Road Sportsground Pavilion is listed in the Councils Corporate Plan, and is included in the Council’s provisional capital programme, with a budget of £1,150,000 and £200,000 in the approved capital programme to cover professional fees. Following detailed work, the current estimated total cost is now £1,640,000.
1.3This report requests approval to transfer £1,150,000 from the provisional capital programme to the approved capital programme, and a capital virement of £290,000 to enable the project to proceed to tendering the building works contract. It is estimated that this total cost of £1,640,000 will be offset by £300,000 in grants, £496,000 in Section 106 contributions and by £575,000 through a future capital receipt from disposal.
1.4It is important that the funding is approved to enable the works to take place this winter in the cricket off season. This will ensure that the project remains on schedule in accordance with the project plan, that external funding is not lost, project costs do not escalate further and revenue savings are derived by the Council.
2. Strategic Priorities
2.1The redevelopment of Woodbridge Road Sportsground Pavilion delivers on two key strategic priorities:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.