That the Executive: (1) notes progress with the scheme and reaffirms its decision that the Council carries out the development, including the market sale element of the project, subject to the proposal receiving planning permission (2) authorises the transfer of £6 million from the general fund provisional capital programme to the approved capital programme to fund the cost of the necessary enabling works described in the report together with costs associated with procuring construction partners including design costs (3) authorises the Director of Community Services, in consultation with the relevant lead councillors, to let relevant contracts to allow the necessary enabling work to be carried out (4) agrees to the appropriation of land as necessary between the General Fund and the Housing Revenue Account. Reason for To enable the redevelopment of the Guildford Park car park site. Alternative options considered and rejected by the Executive: · retain the status quo · dispose of the site to a private developer · develop the site with an external partner through a joint venture arrangement. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None To enable the redevelopment of the Guildford Park car park site.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
The Council owns a significant brownfield site on the edge of the town at Guildford Park. The site is currently used as a surface car park largely serving commuters using the nearby station.
We are committed to redeveloping the site to not only provide much needed additional housing but an enhanced parking facility. The proposal involves the construction of 160 new homes, of which 40% will be affordable rented homes. The development will also include a multi-storey car park with 493 public spaces.
The affordable housing will be funded by the Housing Revenue Account. The remaining housing will be built for market sale and along with the car park funded through the General Fund. Financial projections at this point suggest proceeds from the sale of the market housing will largely offset the cost of the new car park.
To minimise the impact on the amount of public parking provision in the town during the construction period, the development will be phased. The new car park will be built ahead of the residential development.
There are both construction and market risks associated with the project; however, these are outweighed by the opportunity to regenerate the site with a quality development that helps to meet local housing needs.
A specific measure to reduce project risk in the early stages will be to carry out various enabling works before letting the contract for the construction of the car park. The report seeks the necessary funding for this along with the final design and procurement stages of the project.
The commencement of the enabling works will be subject to the proposal receiving planning permission during the Autumn. Recommendation to Executive
That the Executive:
(1) notes progress with the scheme and reaffirms its decision that the Council carries out the development, including the market sale element of the project, subject to the proposal receiving planning permission (2) authorises the transfer of £6 million from the general fund provisional capital programme to the approved capital programme to fund the cost of the necessary enabling works described in the report together with costs associated with procuring construction partners including design costs (3) authorises the Director of Community Services to let relevant contracts to allow the necessary enabling work to be carried out (4) agrees to the appropriation of land as necessary between the General Fund and the Housing Revenue Account.
Reason(s) for Recommendation: To enable the redevelopment of the Guildford Park car park site.
Purpose of report
1.1The Council is committed to redevelop the existing surface public car park at Guildford Park to provide much needed additional housing. This report outlines the progress made to date and seeks the funding required to move the project to the next phase.
2. Strategic Priorities
2.1This development contributes to all the themes of our Corporate Plan.
Our Borough – The provision of quality developments providing homes across a range of tenures for members of our communities is a central strand to this theme. A development on a town centre brownfield site is particularly welcome.
Our Economy – We are taking the opportunity to include an element of commercial space within the development. This will increase the range of opportunities open to business whilst offering additional employment.
The scheme will provide homes for residents who will support the local economy with a number likely to be employed by local business.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.