Executive, Tuesday 19 July 2016 at 7.00pm

Proposed Pop-Up Village

Approved Executive 2 papers

Executive approved this item on Tuesday 19 July 2016. Below is the council's own wording, with the papers it was decided on.

ItemEX28

Resolved

That full approval for the construction and opening of a Pop-Up Village at the former cinema site in Woodbridge Road, Guildford, in accordance with the proposals agreed provisionally by the Executive at its meeting on 28 June 2016, be confirmed. Reasons for The financial models have been reviewed and they show that the original report Scenario (A) continues to deliver a surplus, but the new Scenarios B and C, predict a loss although these assume a ‘worst case position’. Officers believe that the project remains a highly attractive one for the town centre that will deliver a range of benefits. Officers also believe that all risks have been satisfactorily identified and understood and are being properly managed and mitigated. Alternative options considered and rejected by the Executive: None Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None The financial models have been reviewed and they show that the original report Scenario (A) continues to deliver a surplus, but the new Scenarios B and C, predict a loss although these assume a ‘worst case position’. Officers believe that the project remains a highly attractive one for the town centre that will deliver a range of benefits. Officers also believe that all risks have been satisfactorily identified and understood and are being properly managed and mitigated.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Purpose of report

1.1The report has been produced in response to the provisional approval for the Guildford Pop Up Village. Officers have undertaken further detailed work on the financial modelling in light of further information on the site, further conversations with the proposed managing agent Appear Here, the construction project manager, meetings with planners, the licensing team and our electrical engineer. The report also seeks to provide a clearer presentation of the risks in the project, how they are being planned for and mitigated. 2. Financial Implications

2.1The new financial model is provided below. This includes a number of identified additional costs the most significant being:

 Electrical infrastructure costs to comply with legislation, in particular the need to meter all units (around £45,000)  To provide a prudent estimate for more secure hoarding around the substation (£18,000)

The three income and expenditure scenarios are explained as follows:-

 Scenario A – this is based on an October 2016 opening with unchanged rentals (but including updated costs)  Scenario B – Follows discussion with Appear Here who suggest a much lower year one rental of £25 per day, increasing to £40 per day in year two  Scenario C – Assumes Scenario B but a delayed opening of January 2017 – this is deemed to be the ‘worst case scenario’

Costs and revenues breakdown: see Appendix 1 for details (£-Sterling)

Capital Cost 415,760 Revenue Cost 180,000 Total Costs 595,760

Income projections Scenario A Scenario B Scenario C Year One (units) (273,641) (162,882) (118,047) Year Two (units) (385,331) (335,070) (335,070) Total Income(units) (658,972) (497,952) (453,117)

Year One (performance area) (13,000) (13,000) (10,833) Year Two (performance area) (23,400) (23,400) (23,400) Total income (perf. area) (36,400) (36,400) (34,233)

Sponsorship (nominal) (10,000) (10,000) (10,000)

Total income (705,372) (544,352) (497,350) Less expenditure 595,760 595,760 595,760 (Profit)/Loss (99,612) 51,408 98,410

Notes: 1. No figures have been entered for resale values, which will mitigate de- commissioning costs. 2.2 Economic conditions and consequent delayed development may favour an extended operation. A third year could be expected to yield net additional income of £268,000 using either scenario B or C for example if M&G would be prepared to offer an extended lease, which might be possible in the currently less favourable commercial property market.

Risk management

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 09 (1): Pop Up Village: App 1: Income Expenditure projections (4)Appendix 299 KB Download
PDF
Proposed Pop-Up VillageReport 378 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 14 attended
PS
Councillor Paul SpoonerChairperson, present
MF
Councillor Matt FurnissVice-Chairperson, present
RB
Councillor Richard BillingtonCommittee Member, present
DB
Councillor David BilbéCommittee Member, present
GD
Councillor Geoff DavisCommittee Member, present
TR
Councillor Tony RoothCommittee Member, present
GE
Councillor Graham EllwoodCommittee Member, present
MI
Councillor Michael IllmanCommittee Member, present
NN
Councillor Nikki Nelson-SmithCommittee Member, apologies
IR
Councillor Iseult RocheCommittee Member, present
AC
Councillor Adrian ChandlerGuest, in attendance
DG
Councillor David GoodwinGuest, in attendance

All 14 on the meeting page

On this subject at Guildford

Search all
  1. Proposed Pop-Up VillageThis decision
  2. North Street, Guildford - Proposed Pop-Up VillageApproved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies