That the priority list of highway and transport schemes likely to be critical to Local Plan delivery as described in the report submitted to the Executive, be approved. Reason: The approval of the five priority schemes would enable officers to set up regular discussions with Surrey County Council (SCC) and Highways England (HE) on transport infrastructure priorities so that progress can be made in terms of the delivery of the schemes as well as modelling the impact of the schemes in any future transport review likely to be undertaken by SCC. If SCC and HE agree to these priorities it will also assist in terms of lobbying central Government for funding towards these schemes as well as assuring that S106 contributions are made, when appropriate, as planning applications come forward, or that the Council can justify imposing a Grampian condition restricting the amount of development that can come forward in the absence of a particular scheme. Other options considered and rejected by the Executive: 1) Not to support the five priorities; 2) Wait until further transport modelling has been undertaken to demonstrate with a higher degree of evidence and therefore confidence what the key priorities are. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Executive Report Ward(s) affected: All Wards Report of Strategic Services Director Author: Martin Knowles Email: [email protected] Lead Councillor responsible: John Rigg Tel: [phone removed] Email: [email protected] Date: 24 August 2021
Priority List of Highway and Transport Schemes Critical to Local Plan Delivery Executive Summary
Infrastructure interventions require a holistic approach to highways and transport. This requires a plan to address the existing problems and to accommodate any future growth. It will need to recognise changes in society, travel patterns, congestion, pollution and health and in most respects should put health first.
In looking at the borough of Guildford, the plan needs to have regard to growth in traffic, worsening pollution, accident rates, the need for modal shift – buses/trains, the need for better active travel – cycling/walking, and should take into account the existing issues on the A3 and the emerging work and evidence from the Guildford Economic Regeneration (GER) Programme evolving town centre masterplan.
Addressing the above issues needs to be our overall priority for highway and transport schemes going forward. Further work will be carried out through the review of the Local Plan, the GER Programme.
Currently, available funding is likely to be directed towards housing delivery and growth in employment. It is therefore important that the Council aligns its priorities with those of other strategic bodies such as Surrey County Council, Highways England and Network Rail in order to develop deliverable business cases and bid for any available infrastructure funding to aid delivery of these schemes.
Corporate Programmes has highlighted five highway and transport schemes that are likely to be critical priorities to the delivery of the Local Plan maintaining its housing trajectory and continuing to be up to date. These five priorities are dependent on other agencies wholly or partly funding the projects and are where the Council will need to work with them to secure delivery. They have been named ‘priority schemes’ and are in no particular order in this report.
On 11 March 2020 the government published the Road Investment Strategy 2 (RIS2). These are prepared every five years and the latest strategy deals with funding for the period 2020- 2025 but also mandates Highways England to investigate schemes that could be funded in the period 2025-2030 (RIS3).
The RIS2 does not now include an A3 Guildford scheme but does include a requirement to develop a scheme for the RIS3 pipeline known as A3/A247 Ripley south. The details of this improvement have not been formulated by Highways England and officers assume that this scheme relates in part to potential new north facing slips at the A3/A247 junction at Burnt Common.
As the A3 through Guildford scheme no longer forms part of the Government’s Road Strategy Local Plan Policy ID2(2) requires the Council to review its transport evidence base to investigate the consequent cumulative impacts of approved developments and Local Plan growth including site allocations on the safe operation and the performance of the Local Road Networks and the Strategic Road Network. The final sentence of the Policy is important in that it states that “The outcome of this review will determine whether development can continue to be completed in accordance with the Local Plan trajectory or will determine whether there needs to be a review of the Local Plan.”
The highway and transport Schemes that are likely to be critical to the Local Plan (in no particular order) are as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.