That the removal of the following schemes from the General Fund Capital Programme be approved: (1) Guildford Gyratory and Approaches (2) Stoke Park office accommodation (3) Stoke Park – Home Farm redevelopment Recommendation to Council (5 October 2021): (1) That the Treasury Management Annual Report for 2020-21 be noted. (2) That the actual prudential indicators reported for 2020-21, as detailed in Appendix 1 to the report submitted to the Executive, be approved. Reason: To comply with the Council’s treasury management policy statement, the Chartered Institute of Public Finance and Accountancy (CIPFA) Code of Practice on treasury management and the CIPFA Prudential Code for Capital Finance in Local Authorities. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Executive Report Ward(s) affected: n/a Report of the Director of Resources Author: Vicky Worsfold Tel: 01483 444834 Email: [email protected] Lead Councillor responsible: Tim Anderson Tel: [phone removed] Email: [email protected] Date: 24 August 2021
Capital and Investment outturn report 2020-21 Executive Summary
This annual outturn report includes capital expenditure, non-treasury investments and treasury management performance for 2020-21.
Capital programme In total, expenditure on the General Fund capital programme was £29.4 million against the original budget of £171.5 million, and revised budget of £28.8 million. Details of the revised estimate and actual expenditure in the year for each scheme are given in Appendix 3.
The budget for Minimum Revenue Provision (MRP) was £1.64 million and the outturn was £1.29 million. This was due to slippage in the capital programme in 2019-20.
Councillors will be aware that one of the strands of the Council’s savings strategy is to review the projects in the capital programme. There are three schemes that officers are recommending are removed due to the length of time they have been in the programme, and as such the original proposal is no longer relevant and a new business case will need to be prepared if any of the schemes are to come forward in the future. These are: • Guildford Gyratory and Approaches - £10.967 million on the provisional capital programme in 2024-25 • Stoke Park Office Accommodation - £665,000 on the provisional programme in 2024-25 • Stoke Park – Home Farm redevelopment - £4 million on the provisional programme in 2024-25
Non-treasury investments The Council’s investment property portfolio stood at £155 million at the end of the year. Our rental income was £8.1 million, and our income return 5.8% against the benchmark of 4.6%. Treasury management The Council’s cash balances have built up over several years, and reflect our strong balance sheet, with considerable revenue and capital reserves. Officers carry out the treasury function within the parameters set by the Council each year in the Capital and Investment Strategy. As at 31 March 2021, the Council held £159.1 million in investments, £310.5 million in long-term borrowing of which £118.5 million is short- term borrowing, and £192 million is long term borrowing (related to HRA) so net debt of £151.4 million.
We borrowed short-term from other local authorities for cash flow purposes and aim to minimise any cost of carry on this. We did not take out any additional long-term borrowing during the year.
This report (section 8) confirms that the Council complied with its prudential indicators, treasury management policy statement and treasury management practices (TMPs) for 2020-21. The policy statement is included and approved annually as part of the Capital and Investment Strategy, and the TMPs are approved under delegated authority.
The treasury management performance over the last year, compared to estimate, is summarised in the table below. The report highlights the factors affecting this performance throughout the report, and in Appendix 1.
Estimate Actual Estimate Actual % % (£000) (£000) General fund Capital Financing 207,109 116,524 Requirement (CFR) Housing Revenue Account CFR 217,024 199,204 Total CFR 424,133 315,728
Return on investments 2.18 1.05 1,685 2,435 Interest paid on external debt 5,650 5,274 Total net interest paid 3,965 2,839
There was slippage in the capital programme which resulted in a lower CFR than estimated (more information in Appendix 1, section 3).
Interest paid on debt was lower than budget, due to less long-term borrowing taken out on the general fund because of slippage in the capital programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies