Capital and Investment outturn report 2020-21

Approved Executive 6 papers

Executive approved this item on Tuesday 24 August 2021. Below is the council's own wording, with the papers it was decided on.

ItemEX14

Resolved

That the removal of the following schemes from the General Fund Capital Programme be approved: (1) Guildford Gyratory and Approaches (2) Stoke Park office accommodation (3) Stoke Park – Home Farm redevelopment Recommendation to Council (5 October 2021): (1) That the Treasury Management Annual Report for 2020-21 be noted. (2) That the actual prudential indicators reported for 2020-21, as detailed in Appendix 1 to the report submitted to the Executive, be approved. Reason: To comply with the Council’s treasury management policy statement, the Chartered Institute of Public Finance and Accountancy (CIPFA) Code of Practice on treasury management and the CIPFA Prudential Code for Capital Finance in Local Authorities. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive Report Ward(s) affected: n/a Report of the Director of Resources Author: Vicky Worsfold Tel: 01483 444834 Email: [email protected] Lead Councillor responsible: Tim Anderson Tel: [phone removed] Email: [email protected] Date: 24 August 2021

Capital and Investment outturn report 2020-21 Executive Summary

This annual outturn report includes capital expenditure, non-treasury investments and treasury management performance for 2020-21.

Capital programme In total, expenditure on the General Fund capital programme was £29.4 million against the original budget of £171.5 million, and revised budget of £28.8 million. Details of the revised estimate and actual expenditure in the year for each scheme are given in Appendix 3.

The budget for Minimum Revenue Provision (MRP) was £1.64 million and the outturn was £1.29 million. This was due to slippage in the capital programme in 2019-20.

Councillors will be aware that one of the strands of the Council’s savings strategy is to review the projects in the capital programme. There are three schemes that officers are recommending are removed due to the length of time they have been in the programme, and as such the original proposal is no longer relevant and a new business case will need to be prepared if any of the schemes are to come forward in the future. These are: • Guildford Gyratory and Approaches - £10.967 million on the provisional capital programme in 2024-25 • Stoke Park Office Accommodation - £665,000 on the provisional programme in 2024-25 • Stoke Park – Home Farm redevelopment - £4 million on the provisional programme in 2024-25

Non-treasury investments The Council’s investment property portfolio stood at £155 million at the end of the year. Our rental income was £8.1 million, and our income return 5.8% against the benchmark of 4.6%. Treasury management The Council’s cash balances have built up over several years, and reflect our strong balance sheet, with considerable revenue and capital reserves. Officers carry out the treasury function within the parameters set by the Council each year in the Capital and Investment Strategy. As at 31 March 2021, the Council held £159.1 million in investments, £310.5 million in long-term borrowing of which £118.5 million is short- term borrowing, and £192 million is long term borrowing (related to HRA) so net debt of £151.4 million.

We borrowed short-term from other local authorities for cash flow purposes and aim to minimise any cost of carry on this. We did not take out any additional long-term borrowing during the year.

This report (section 8) confirms that the Council complied with its prudential indicators, treasury management policy statement and treasury management practices (TMPs) for 2020-21. The policy statement is included and approved annually as part of the Capital and Investment Strategy, and the TMPs are approved under delegated authority.

The treasury management performance over the last year, compared to estimate, is summarised in the table below. The report highlights the factors affecting this performance throughout the report, and in Appendix 1.

Estimate Actual Estimate Actual % % (£000) (£000) General fund Capital Financing 207,109 116,524 Requirement (CFR) Housing Revenue Account CFR 217,024 199,204 Total CFR 424,133 315,728

Return on investments 2.18 1.05 1,685 2,435 Interest paid on external debt 5,650 5,274 Total net interest paid 3,965 2,839

There was slippage in the capital programme which resulted in a lower CFR than estimated (more information in Appendix 1, section 3).

Interest paid on debt was lower than budget, due to less long-term borrowing taken out on the general fund because of slippage in the capital programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital and Investment outturn report 2020-21Report 311 KB DownloadRead as text
PDF
Item 07 (1): Capital and Investment Outturn Report 2020-21: App 1: Treasury Management activity and treasury and prudential indicators 202021Appendix 331 KB Download
PDF
Item 07 (2): Capital and Investment Outturn Report 2020-21: App 2: Fund Report 20-21 v4Appendix 969 KB Download
PDF
Item 07 (3): Capital and Investment Outturn Report 2020-21: App 3: Capital ProgrammeAppendix 109 KB Download
PDF
Item 07 (4): Capital and Investment Outturn Report 2020-21: App 4: Schedule of investments at 31 March 2021Appendix 242 KB Download
PDF
Item 07 (5): Capital and Investment Outturn Report 2020-21: App 5: Economic background (2)Appendix 345 KB Download

At this meeting

Whole meeting

Who was there

6 of 12 attended
JB
Councillor Joss BigmoreChairperson, present
JH
Councillor Jan HarwoodVice-Chair, present
TA
Councillor Tim AndersonCommittee Member, apologies
TH
Councillor Tom HuntCommittee Member, present
JM
Councillor Julia McShaneCommittee Member, present
JR
Councillor John RedpathCommittee Member, apologies
JR
Councillor John RiggCommittee Member, present
JS
Councillor James SteelCommittee Member, present
CB
Councillor Chris BlowGuest, in attendance
RN
Councillor Ramsey NagatyGuest, in attendance
WS
Councillor Will SalmonGuest, in attendance
PS
Councillor Paul SpoonerGuest, in attendance

On this subject at Guildford

Search all
  1. Capital and Investment outturn report 2020-21This decision
  2. Capital and Investment Strategy 2024/25 - 2028/29Approved
  3. Capital and Investment Outturn Report 2022-23Noted
  4. Capital and Investment Strategy (2023-24 to 2027-28)Approved
  5. Capital and Investment outturn report 2021-22Approved
  6. Capital and Investment Strategy (2022-23 to 2026-27)Approved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open