That the Council approves the transfer of £69.548 million from the provisional capital programme to the approved capital programme for payments which the Council is obliged to make to Thames Water Utilities Limited under the Thames Water Agreement for 2024-25, for costs necessary to meet the milestones set within the Homes England HIF agreement and construction costs of ... view the full minutes text for item CO15
Word for word from the decision Guildford published for this meeting.Source: democracy.guildford.gov.uk
Guildford Borough Council Report to: Council Date: 13 May 2024 Ward(s) affected: Bellfields and Slyfield Report of Director: Place Author: Abi Lewis, Assistant Director Regeneration & Planning Policy Tel: 01483 444908 Email: [email protected] Lead Councillor responsible: Tom Hunt Tel: [phone removed] Email: [email protected] Report Status: Part Exempt
Weyside Urban Village Development 1. Executive Summary 1.1 Weyside Urban Village ("WUV") is a major 41-hectare brownfield regeneration scheme that Guildford Borough Council (the "Council") anticipates could deliver approximately 1,500 homes across a range of tenures, as well as 2,000 square metres of community space and 6,500 square metres of employment space.
1.2In February 2020 the Council committed £334.9 million to de-risk the infrastructure and site assembly process needed across the Weyside Urban Village site. Over 44 percent of the site is currently in Council ownership, and 100 per cent will be achieved on completion of land transfers with Thames Water Utilities Ltd (“TWUL”). The conditional contract with TWUL was signed on 25 April 2019 (the "TW Agreement"). 1.3 The Council signed a Grant Determination Agreement (GDA) with Homes England in July 2020 for Housing Infrastructure Funding (HIF) for £52.3m, to draw down the grant expenditure associated with the implementation of the infrastructure works. In October 2021, the Planning Committee issued a Resolution to Grant for the hybrid planning application for Weyside, with the decision notice to approve the application issued in March 2022.
1.4The broader economic landscape and its impact on the construction industry over the last 12–18 months has been profound. At the end of 2021, the Building Cost Information Service (BCIS) - which provides cost and price data for the UK construction industry - reported that the annual growth in its material cost index reached a forty-year high. Since then, pressures on supply chains have persisted and labour shortages have become more acute. Although the lifting of Covid restrictions led to a return of high activity levels, the war in Ukraine and high rates of inflation have put the construction industry in further turmoil. The impact of these issues is being felt at a local level, with forecast construction and financing costs also increasing significantly.
1.5It was agreed with Executive in January 2020 that the project team would report the financial position to the Executive on an annual basis. This report sets out the current financial forecast to the end of the programme ahead of a further paper being presented to Executive and Council outlining the proposed mitigation plan to address the potential financial deficit that has arisen as a result of macro-level factors.
1.6This report will be considered by the Executive at its special meeting on 9 May at which it will be asked:
(1) to note the current financial position of WUV at the Spring 2024 Financial Review, as set out in this report, and (2) to note the current forecasted eventual deficit - outlined in Exempt Appendix 1 - in 2033 (year 10 of the project delivery programme). (3) Delegate to the Strategic Director of Place, in consultation with the Lead Councillor for Regeneration and Lead Councillor for Finance and Property, authority to enter into such other contracts and legal agreements connected with the Weyside Urban Village programme as may be necessary in compliance with Procurement Procedure Rules and within the approved budget.
1.7The Executive will also be asked to endorse the recommendation to Council in paragraph 2 below.
1.8Details of the outcome of the Executive’s consideration of this matter will be reported to the Council on the Supplementary Agenda Pack (formerly known as the Order Paper).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Overview and Scrutiny Annual Report(1) To approve the attached at Appendix 1 to the report submitted to the Council. (2) To not amend the current O&S wo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.