Guildford Borough Council
Executive, Thursday 9 October 2025 at 6.00pm

Transfer of funds from Capital Contingency Fund to Midleton Industrial Estate Budget

Approved Executive 1 paper

AI summaryGuildford Borough Council Executive approved transferring £180,625 from the Capital Contingency Fund to close the Midleton Industrial Estate Redevelopment budget after its final phase overspent the approved allocation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedTransfer £180,625 to close project budget
Money£180,625From Capital Contingency Fund to Midleton budget
What happens nextVirement to be madeFinance Team to update records this financial year
Who it affectsMidleton Industrial Estate projectCapital Contingency Fund reserve

What was decided

The Executive approved viring £180,625 from the Capital Contingency Fund to the Midleton Industrial Estate Redevelopment budget so the project can be closed. Report 2.1, P2

No other decisions by members or committees are required to carry out the transfer. Report 4.3

Why

The project is overspent after settlement of the final account, and the business case budget did not contain enough remaining contingency to absorb the extra cost. Report 3.1, 3.2, 6.5

Industry-wide increases in materials and labour costs between the 2017 budget approval and delivery of the final phase were not fully anticipated. Report 6.4

What happens next

Following approval, the £180,625 will be vired from the Capital Contingency Fund to the Midleton project budget. Report 4.1

The Finance Team will update the project budget and financial records so the project can be closed within the current financial year. Report 4.2

A lessons learned session will be held with Guildford and Waverley councils' Regeneration and Economic Development service. Report 8.1

The money

  • £180,625 Virement from Capital Contingency Fund to Midleton Redevelopment budget Report P2, P31
  • £14,907,000 Original single budget for the whole Midleton redevelopment programme approved in 2017 Report 6.3
  • £15,007,000 Total programme budget after an additional £100,000 approved in 2023 Report P34
  • £15,167,230 Current expenditure on the programme at time of reporting Report P34
  • £20,625 Remaining outstanding expenditure included in the recommended additional funding Report P34
  • £2.5m Size of the Capital Contingency Fund Report P32
  • £2m Brought forward balance within the Capital Contingency Fund Report P32

Options considered

  • Rejected: Do not vire funds from the Capital Contingency Fund. Would leave the project with an overspend and an unchanged, short budget Report 11.1
  • Chosen: Vire £180,625 from the Capital Contingency Fund to the project budget. Funds were earmarked in the 2025/26 budget-setting process and are available and consistent with the fund's purpose Report 11.2, P32

Implications

  • Financial: The £180,625 virement will reduce the Capital Contingency Fund, which had been earmarked to cover overspends on Midleton and Walnut Bridge. Report P32
  • Risk: Not approving the virement would leave an unresolved budget shortfall, affect year-end reporting and may breach financial regulations. Report 10.1, P27
  • Legal: No direct legal concerns, provided the transfer is approved through proper governance. The Executive can approve capital virements up to £500,000 under Financial Procedure Rules paragraph 5.3. Report P35, P37
  • Equalities: No equality and diversity implications arising from this report. Report P43
  • Climate: No climate change or sustainability implications arising directly from this report. Report P46

Who and where

  • The Council's capital budget and year-end financial reporting Report 10.1, P27
  • Tenants and small businesses using the new industrial units at Midleton Industrial Estate Report 6.2, P20
  • The Capital Contingency Fund, also earmarked for the Walnut Bridge project Report P32

Timeline

  • 24 January 2017: Executive approved the business case for phased redevelopment of Midleton Industrial Estate Report 6.1
  • December 2023: Phase 4 works completed Report 6.2
  • December 2024: Final certificate issued for Phase 4 Report 6.2
  • Late 2024: Overspend first reported to the Capital Monitoring Board through budget forecasting Report P33
  • 2025/26: Funding from the Capital Contingency Fund earmarked during budget-setting to cover the Midleton and Walnut Bridge overspends Report P32
  • 2025-10-09: Executive approved the £180,625 virement

Plain English for the jargon

  • Virement: Transfer of budget from one heading to another without changing the overall total
  • Capital Contingency Fund: A £2.5m reserve, with a £2m brought forward balance, set aside for unforeseen or unavoidable capital project costs
  • Practical completion: The point at which construction works are sufficiently complete for the building to be taken over for its intended use
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX65

Resolved

Vire the sum of £180,625 from the Capital Contingency Fund to the Midleton Industrial Estate Redevelopment budget in order that the project can be closed. Reason(s): 1. The reason for the recommendation is to balance and close the project budget at the completion of the scheme. The additional funding is required to close the budget due to existing overspend now that final account has been settled. 2. As this project was the fourth and final phase of a wider redevelopment of the Midleton Industrial Estate, there was insufficient contingency remaining within the approved budget to absorb the additional cost. Other options considered and rejected by the Executive: Option 1, not to vire the funds. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Recommendation

2.1That the Executive resolve to:

2.1.1 Vire the sum of £180,625 from the Capital Contingency Fund to the Midleton Industrial Estate Redevelopment budget in order that the project can be closed.

Reasons for recommendation

3.1The reason for the recommendation is to balance and close the project budget at the completion of the scheme. The additional funding is required to close the budget due to existing overspend now that final account has been settled.

3.2As this project was the fourth and final phase of a wider redevelopment of the Midleton Industrial Estate, there was insufficient contingency remaining within the approved budget to absorb the additional cost.

4 Next steps

4.1Following Executive approval of this report, the virement of £180,625 from the Capital Contingency Fund to the Midleton Industrial Estate Redevelopment budget will be undertaken.

4.2The Finance Team will update the project budget and financial record accordingly to enable the project to be closed within the current financial year. Transfer of funds from Capital Contingency Fund to Midleton Industrial Estate Budget

4.3No further decisions by members or committees are required to implement this transfer.

5 Exemption from publication

5.1This report contains no exempt content.

6 Background and Proposal

6.1The Midleton Industrial Estate comprises approx. 5.7 acres within the Council’s freehold ownership and the Executive approved a business case for its phased redevelopment on 24 January 2017.

6.2Phase 4 - the final phase of the development – has delivered 20 individual units ranging in size from approximately 50sqm to 75 sqm on a section of the original estate. Works to phase 4 completed in December 2023 with the final certificate issued in December 2024. Since practical completion 19 units have been successfully let with rental income proving higher than originally anticipated.

6.3The business case for the programme of works was approved in 2017, with all phases operating under a single budget of £14,907,000. As budgets were not separated by each individual phase, the overall contingency allowance was shared across the programme. A portion of this contingency was absorbed during earlier phases, leaving limited financial flexibility for later stages of the programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transfer of funds from Capital Contingency Fund to Midleton Industrial Estate BudgetReport 126 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
JM
Councillor Julia McShaneChairperson, present
TH
Councillor Tom HuntVice-Chair, present
AG
Councillor Angela GoodwinCommittee Member, present
CH
Councillor Catherine HoustonCommittee Member, present
RL
Councillor Richard LucasCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, present

On this subject at Guildford

Search all
  1. Transfer of funds from Capital Contingency Fund to Midleton Industrial Estate BudgetThis decision
  2. Strategic Property Acquisition Procedure and Request for Transfer of FundsApproved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open