Executive, Thursday 9 October 2025 at 6.00pm

Risk Management and Corporate Risk Registers (Q1 2025/26)

Noted Executive 3 papers

AI summaryGuildford Borough Council Executive noted the Q1 2025/26 corporate risk registers and comments from the Audit and Risk Committee, making no further recommendations.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedExecutive noted updated corporate risk registers
MoneyNoneNo direct financial implications from this report
What happens nextNo further stepsReport states no further steps are required
Who it affectsCouncil-wide risk managementCovers strategic and operational risk registers

What was decided

The Executive noted the comments arising from the Audit and Risk Committee as set out in the Supplementary Agenda. Report 2.1

The Executive noted the updated corporate risk registers and made no recommendations. Report 2.2

This was the first time red rated operational risks were reported to the Audit and Risk Committee, and there were no changes to that register. Report 6.7

Why

To ensure that risks threatening corporate objectives are adequately addressed and managed in line with the Council's risk appetite, as set out in the Risk Management Strategy. Report 3.1

Without a fit for purpose and consistent risk management process the Council would be exposed to unnecessary and unacceptable risks, and best value authorities must demonstrate good governance. Report 10.1

What happens next

There are no further steps for this report. Report 4.1

Substantive updates have been made to strategic risks SR1 (Financial Sustainability), SR2 (Local Government Reorganisation), SR3 (Scale and Pace of Change), and SR10 (Fraud). Report P22, P24, P25, P26

Two new strategic risks have been added since the Committee's June meeting: SR12 (Safeguarding) and SR13 (Contract Management). Report P27, P28

Options considered

  • Chosen: Note the report and consider any comments or observations made by the Audit and Risk Committee Report P40, 11.1

Implications

  • Legal: Under the Accounts and Audit Regulations 2015, the Council must undertake effective internal audit, considering Public Sector Internal Audit Standards, and meet the statutory Best Value duty to manage risk effectively. Report P44, P45, P46
  • Risk: The residual likelihood score for strategic risk SR1 (Financial Sustainability) was increased from Unlikely (2) to Possible (3) to reflect Weyside Urban Village implications and financial uncertainties of Local Government Reorganisation. Report P22, P23
  • Staffing: Completion and oversight of the risk registers will require resource from the Joint Leadership Team, Service Leads, the Strategy and Performance team, and specialists within the organisation. Report P53
  • Equalities: The Equalities Comprehensive Impact Assessment indicates the proposals will not have a disproportionately adverse impact on people with a protected characteristic. Report P52
  • Climate: There are no direct climate change or sustainability implications, though the Council must manage risk effectively to achieve its goal of being net zero carbon by 2030. Report P56

Who and where

  • Guildford Borough Council staff involved in risk management, including the Joint Leadership Team, Service Leads, and the Strategy and Performance team Report P53
  • Waverley Borough Council, through joint quarterly review meetings under the shared Risk Management Framework Report 8.1
  • Council members receiving independent assurance on the risk management framework and internal control environment Report 6.1

Timeline

  • Q1 2025/26: Q1 corporate risk registers presented to the Executive Report 15.1, 15.2
  • June 2025: Previous Strategic Risk Register update received by the Audit and Risk Committee Report 6.8
  • End of 2024: Government intentions for Local Government Reorganisation announced; risks held within SR2 Report 8.2

Plain English for the jargon

  • LGR: Local Government Reorganisation
  • MTFP: Medium Term Financial Plan
  • CLB: Corporate Leadership Board
  • PSIAS: Public Sector Internal Audit Standards
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX69

Resolved

Noted the comments arising from the Audit and Risk Committee as set out in the Supplementary Agenda. 2. Noted the updated corporate risk registers and made no recommendations. Reason(s): To enable the Executive to ensure that risks threatening corporate objectives are adequately addressed and managed in accordance with the Council’s risk appetite, as set out in the Council’s Risk Management Strategy. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Recommendation

2.1That the Executive note the comments arising from the Audit and Risk Committee as set out in the Supplementary Agenda; and

2.2That the Executive note the updated corporate risk registers and make any observations on their contents.

3 Reason(s) for recommendation

3.1To enable the Executive to ensure that risks threatening corporate objectives are adequately addressed and managed in accordance with the Council’s risk appetite, as set out in the Council’s Risk Management Strategy.

4 Next steps

4.1There are no further steps for this report.

5 Exemption from publication

5.1No part of this report is exempt from publication.

6 Background and Proposal

Role of the Audit & Risk Committee

6.1The purpose of the Committee is to provide independent assurance to councillors of the adequacy of the risk management framework and the internal control environment. It provides independent review of the authority’s governance, risk management and control frameworks.

Strategic and operational risks 6.2 The Council’s risk management strategy defines corporate risks as risks ‘that reside outside the usual course of management and require a wider corporate response or awareness …’.

6.3Corporate risks are split into two categories: strategic and operational risks.

6.4Strategic risks (shown at Appendix 1) are risks that could impact the Council’s medium to long term priorities and objectives as set out in the Corporate Strategy or other corporate level policies and strategies, including the Medium- Term Financial Plan (MTFP).

6.5Operational risks are risks that are encountered in the delivery of services and which affect service objectives, as defined in service plans. Operational risks are usually managed as part of the usual course of management by services. However, where an operational risk cannot be managed within the service or if it is outside of the Council’s risk appetite, then it should be considered for inclusion on the operational risk register.

6.6Red rated operational risks shown at Appendix 2 are reported to the Audit and Risk Committee and the Executive.

Changes to the risk registers since the last report

6.7This is the first time that red rated operational risks had come before the Audit and Risk Committee, and, as such, there were no changes to report.

6.8Since the Committee last received an update on Strategic Risk Register in June, the following substantive changes have been made to the risk register:

Strategic Risk Register:

Substantive change to note (see the risk Ref. Risk register for full information)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Guildford Operational risk register Q1 (Appendix 2)Appendix 157 KB Download
PDF
Guildford Strategic Risk Q1 register (Appendix 1)Appendix 313 KB Download
PDF
Risk Management and Corporate Risk Registers (Q1 2025/26)Report 125 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
JM
Councillor Julia McShaneChairperson, present
TH
Councillor Tom HuntVice-Chair, present
AG
Councillor Angela GoodwinCommittee Member, present
CH
Councillor Catherine HoustonCommittee Member, present
RL
Councillor Richard LucasCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, present

On this subject at Guildford

Search all
  1. Risk Management and Corporate Risk Registers (Q1 2025/26)This decision
  2. Risk Management and Corporate Risk Registers (Q1 2026/27)Noted
  3. Risk Management and Corporate Risk Registers (Q4 2025/26)Noted
  4. Risk Management and Corporate Risk Registers (Q2 and Q3 2025/26)Noted
  5. Risk Management and Corporate Risk Registers (Q2 2025/26)Noted
  6. Risk Management and Corporate Risk Registers (Q1 2025/26)Noted

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies