Guildford Borough Council
Executive, Thursday 9 October 2025 at 6.00pm

Procurement Pipeline Report - over £200k (2025-2026)

Approved Executive 2 papers

AI summaryGuildford Executive approves procurement start for pipeline projects over £200k and delegates award of three named contracts.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedThree named contracts delegated for award
MoneyNo direct financial implicationsFinancial approval needed before each procurement starts
What happens nextProceed to market for listed procurementsProcurement and service areas will run tender processes
Who it affectsSuppliers and service areasProcurements over £200k during 2025-2026

What was decided

The Executive approved the start of procurement for the projects listed in Appendix 1, covering procurement activity over £200k for 2025-2026. Report P2, 2.1

Authority to award three named contracts was delegated to the Joint Strategic Director for Finance and Resources, after consulting the Lead Councillor for Finance: Advanced Electricity Metering and Data Services, Minor Works for Rodboro walkway paving, and the Electric Taxi Project. Report P3, P4, P5

Future contract awards that are key decisions will come back to the Executive in a separate report unless delegation has been given to an officer. Report 3.4, P29

Why

The Council's Contract Procedure Rules require Executive approval before starting any procurement that may result in a key decision for the contract award. Report 3.1, 6.2

Planning procurement activity supports stakeholder management, compliance with procurement law, ethical and social value considerations, and best value over the life of each contract. Report 3.2, P9, P10, P11, P12, P13, P14

A consolidated pipeline avoids repeated individual reports and lets the procurement team plan resources with Waverley Borough Council, while meeting potential duties under the Procurement Act 2023. Report 3.3, 6.3, 6.5

What happens next

The Procurement team and the relevant service area will go to market for the procurements listed in Appendix 1, then run the award process and seek relevant approvals. Report 4.1, P17

Collaboration opportunities with Waverley Borough Council and others will be considered as part of the business case for each procurement, with any current collaboration noted in Appendix 1. Report 8.1, 8.2

Any public consultation needed for an individual procurement will be carried out at the appropriate time before tender. Report 9.1, P36

Options considered

  • Chosen: Bring a consolidated procurement pipeline to the Executive at intervals, saving time and supporting strategic planning.. Reflects a more strategic planned approach and reduces time taken to procure. Report P40, 11.1
  • Rejected: Bring each individual item to the Executive in a separate report.. Would incur more time and cost writing individual reports. Report P41

Implications

  • Financial: No direct financial implications from this report; financial approval will be sought before any procurement starts and considered in each business case. Report P43
  • Legal: No direct legal implications; the Council's Procurement and Legal teams will provide project-specific advice during the process and at award. Report P44, P45
  • Equalities: No equality and diversity implications from this report; the Public Sector Equality Duty will be considered within each project's business case. Report 12.3, P47, P50
  • Climate: No climate change or sustainability implications from this report; these will be considered within each project's business case, and ethical factors including climate impact are part of procurement planning. Report 12.5, P13
  • Risk: Key risks are extra resource needed from the Procurement team and service areas under the new Contract Procedure Rules, and the risk of non-compliant spend or expired contracts if a planned pipeline is not in place. Report 10.1, 10.2
  • Other: The pipeline supports the Council's strategic priorities, including reducing barriers for small and medium enterprises, the voluntary and community sector, and local suppliers, as required under public sector procurement law. Report 7.2, P32

Who and where

  • The Procurement team and service areas at Guildford Borough Council, who will run the procurements. Report 4.1, P17
  • Waverley Borough Council, as a potential collaboration partner across procurements. Report 6.3, 6.4, 8.1
  • Suppliers, including small and medium enterprises, the voluntary, community and social enterprise sector, and local suppliers, who may be able to bid for listed contracts. Report 7.2

Timeline

  • 2025-2026: Procurement pipeline covers contracts over £200k for this period. Report P6, 6.1

Plain English for the jargon

  • CPRs: Contract Procedure Rules, the Council's rules governing how procurements and contracts are run.
  • Key decision: An Executive decision of significant scale or impact, as defined in the Council's governance rules.
  • Procurement Act 2023: New UK legislation governing public sector procurement, including pipeline notice duties for larger spenders.
  • Social value: Consideration of wider benefits, such as environmental, social and economic outcomes, when buying goods, works or services.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX67

Resolved

Approve commencement of the procurement process for the projects listed in Appendix 1 to this report. 2. Delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award the following contracts listed in Appendix 1: a) Advanced Electricity Metering & Data Services Contract; b) Minor Works – Rodboro walkway paving Contract; and c) Electric Taxi Project. Reason(s): 1. The Executive is required to approve, prior to their commencement, all procurement activity which may require a key decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a key decision prior to procurement procedures formally commencing. 2. Planning procurement activity ensures: • effective stakeholder management? • effective procurement and sourcing? • compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules?? • there is consideration on how contract price is to be managed in contract and what contract price model will be used? • our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk.?? • how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract. 3. This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity. 4. When a procurement activity is concluded Executive approval for any consequent contract award which would be a key decision will be sought by a separate report, unless authority is specifically delegated to an officer. Other options considered and rejected by the Executive: Bringing each individual item to the Executive, which would incur more time and cost writing individual reports. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Recommendations

2.1That the Executive resolves to:

(1) Approve commencement of the procurement process for the projects listed in Appendix 1 to this report.

(2) Delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award the following contracts listed in Appendix 1: a) Advanced Electricity Metering & Data Services Contract;

b) Minor Works – Rodboro walkway paving Contract; and

c) Electric Taxi Project.

3 Reason(s) for recommendation: Procurement Pipeline Report – over £200k (2025-2026)

3.1The Executive is required to approve, prior to their commencement, all procurement activity which may require a key decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a key decision prior to procurement procedures formally commencing.

3.2Planning procurement activity ensures:

• effective stakeholder management

• effective procurement and sourcing

• compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules

• there is consideration on how contract price is to be managed in contract and what contract price model will be used

• our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk.

• how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract.

3.3This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GBC ProcurementPipeline 091025Appendix 1 134 KB Download
PDF
Procurement Pipeline Report: over £200k (2025-2026)Report 138 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 8 attended
JM
Councillor Julia McShaneChairperson, present
TH
Councillor Tom HuntVice-Chair, present
AG
Councillor Angela GoodwinCommittee Member, present
CH
Councillor Catherine HoustonCommittee Member, present
RL
Councillor Richard LucasCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, present

On this subject at Guildford

Search all
  1. Procurement Pipeline Report - over £200k (2025-2026)This decision
  2. Procurement Pipeline Report - over £200k (2025-2026)Approved
  3. Procurement Pipeline Report - over £200k (2025-2026)Approved
  4. Procurement Pipeline Report - over £200k (2025-2026)Approved
  5. Procurement Pipeline Report - over £200k (2025-2026)Approved
  6. Procurement Pipeline Report - over £200k (2025-2026)Approved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open