Executive, Thursday 6 November 2025 at 6.00pm

Procurement Pipeline Report - over £200k (2025-2026)

Approved Executive 2 papers

AI summaryGuildford Borough Council Executive approves procurement pipeline over £200k and delegates award authority for two named contracts to an officer.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPipeline go-ahead plus delegated awards
MoneyOver £200k thresholdTriggers key decision requirement
What happens nextProcurement team proceeds to marketThen award or further Executive approval
Who it affectsSuppliers, service areas, residentsIncluding council tax bill recipients

What was decided

The Executive approved the commencement of procurement for the projects listed in Appendix 1 to the report. Report P5

Authority to award the Memorial Safety Testing and Remedial Works Contract and the Printing of Annual Council Tax Bills Contract is delegated to the Joint Strategic Director for Finance and Resources, after consulting the Lead Councillor for Finance. Report P5, P6, P7

Other contract awards arising from the pipeline that are key decisions will be brought back to the Executive in a separate report unless separately delegated. Report 3.4

Why

The Council's Contract Procedure Rules require Executive approval before starting any procurement that could result in a key decision, either because its value exceeds £200k or it significantly affects two or more wards. Report 1.1, 6.2

A planned pipeline is considered good practice, helps the Council meet the Procurement Act 2023 duty to publish pipeline notices for procurements over £2m if annual third party spend exceeds £100m, and avoids multiple individual approval papers. Report 3.3, 6.5

Forward planning also aims to attract suppliers, reduce barriers for small and medium enterprises and the voluntary, community and social enterprise sector, and explore collaboration with Waverley Borough Council. Report 7.2, 8.1

What happens next

The Procurement team and the relevant service area will proceed to market for the procurements listed in Appendix 1 and then run the award process, obtaining any further approvals needed. Report 4.1, P20

Financial approval will be sought before any procurement actually commences, and project-specific advice will be provided by the Procurement and Legal teams. Report P45, P47

The money

  • £200k Threshold above which procurement must go to Executive as a key decision Report 1.1
  • £100m (inc VAT) Annual third party spend level that triggers pipeline notice duties under the Procurement Act 2023 Report 6.5
  • £2m (inc VAT) Estimated value above which individual pipeline notices must be published every 18 months Report 6.5

Options considered

  • Chosen: Bring a consolidated procurement pipeline to the Executive at intervals, saving officer and member time. More strategic, agile and reduces time taken to procure Report P42, 3.3
  • Rejected: Bring each individual procurement item to the Executive as a separate report. Would incur more time and cost writing individual reports Report P43

Implications

  • Financial: No direct financial implications; financial approval will be sought before any procurement actually commences. Report P45
  • Legal: No direct legal implications; the Procurement and Legal teams will provide project-specific advice throughout. Report P46, P47
  • Equalities: No equality and diversity implications for this report; project teams will consider the Public Sector Equality Duty for each procurement. Report P49, P52
  • Climate: No climate change or sustainability implications for this report; will be considered per project. Report 12.4, 12.5
  • Risk: Risk that new Contract Procedure Rules demand more officer and service area resource to draft Executive papers. Report 10.1
  • Risk: Risk of non-compliant spend if pipelines are not planned, with contracts potentially expiring before re-procurement. Report 10.2
  • Staffing: Procurement team is prioritising resource to support both Waverley Borough Council and Guildford Borough Council. Report 6.3

Who and where

  • Suppliers, including small and medium enterprises and the voluntary, community and social enterprise sector Report 7.2
  • Waverley Borough Council, as a potential collaboration partner Report 6.3, 8.1
  • Guildford Borough Council service areas that will run the procurements Report 10.1
  • Residents receiving annual council tax bills Report P7

Timeline

  • June 2024: New Contract Procedure Rules introduced, changing who approves procurements and awards Report 6.1
  • 9 October 2025: Previous procurement pipeline presented to the Executive Report 1.2
  • 2025-11-06: Executive decision to approve updated pipeline and delegate two contract awards Report P5

Plain English for the jargon

  • CPRs: Contract Procedure Rules, the Council's internal rules governing how procurements and contracts are run.
  • Key decision: An Executive decision that is significant in budget or impact, including procurements over £200k or those affecting two or more wards.
  • SME: Small and medium sized enterprise.
  • VCSE: Voluntary, community and social enterprise sector.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX81

Resolved

To approve commencement of the procurement process for the projects listed in Appendix 1 to this report. 2. To delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award the following contracts listed in Appendix 1: · Memorial Safety Testing and remedial works Contract; and · Printing of Annual Council Tax Bills Contract. Reason(s): The Executive is required to approve, prior to their commencement, all procurement activity which may require a key decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a key decision prior to procurement procedures formally commencing. Planning procurement activity ensures: · effective stakeholder management? · effective procurement and sourcing? · compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules?? · there is consideration on how contract price is to be managed in contract and what contract price model will be used? · our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk.?? · how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract. This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity. When a procurement activity is concluded Executive approval for any consequent contract award which would be a key decision will be sought by a separate report, unless authority is specifically delegated to an officer. Other options considered and rejected by the Executive: Bring each individual item to the Executive, which will incur more time and cost writing individual reports, so is not recommended. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive summary

1.1The Council’s Contract Procedure Rules (CPRs) provide that the Executive must give permission to commence any procurement activity which could result in the award being a key decision as the estimated value is greater than £200k or it significantly impacts two or more wards within the Borough.

1.2This report provides an update of the procurement pipeline which was presented to Executive on 9 October 2025. The pipeline set out in Appendix 1 to this report includes additional projects which are likely to result in Key Decisions and seeks Executive agreement for procurements to commence.

1.3In addition, delegated authority is sought for the Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor following an appropriate tendering process, to enter contracts for the award of the projects set out in Appendix 1.

Recommendations

2.1That the Executive resolves to:

(1) Approve commencement of the procurement process for the projects listed in Appendix 1 to this report. (2) Delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award the following contracts listed in Appendix 1:

a) Memorial Safety Testing and remedial works Contract; and

b) Printing of Annual Council Tax Bills Contract.

3 Reason(s) for recommendation:

3.1The Executive is required to approve, prior to their commencement, all procurement activity which may require a key decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may Procurement Pipeline Report – over £200k (2025-2026)

result in a key decision prior to procurement procedures formally commencing.

3.2Planning procurement activity ensures:

• effective stakeholder management

• effective procurement and sourcing

• compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules

• there is consideration on how contract price is to be managed in contract and what contract price model will be used

• our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk.

• how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract.

3.3This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity.

3.4When a procurement activity is concluded Executive approval for any consequent contract award which would be a key decision will be sought by a separate report, unless authority is specifically delegated to an officer.

4 Next steps

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
_Procurement Pipeline Nov.25 version 2Appendix 1 215 KB Download
PDF
Procurement Pipeline Report: over £200k (2025-2026)Report 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
SK
Sharon KeenlysideCouncil Staff, expected
JM
Councillor Julia McShaneChairperson, present
TH
Councillor Tom HuntVice-Chair, present
AG
Councillor Angela GoodwinCommittee Member, present
CH
Councillor Catherine HoustonCommittee Member, present
RL
Councillor Richard LucasCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, apologies

On this subject at Guildford

Search all
  1. Procurement Pipeline Report - over £200k (2025-2026)This decision
  2. Procurement Pipeline Report - over £200k (2025-2026)Approved
  3. Procurement Pipeline Report - over £200k (2025-2026)Approved
  4. Procurement Pipeline Report - over £200k (2025-2026)Approved
  5. Procurement Pipeline Report - over £200k (2025-2026)Approved
  6. Procurement Pipeline Report - over £200k (2025-2026)Approved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open