Guildford Borough Council
Executive, Thursday 20 August 2026 at 6.00pm

Procurement Pipeline Report - over £200k (2025-2026)

Approved Executive 2 papers

AI summaryGuildford Borough Council Executive approves procurement pipeline for nine contracts, including £33.37m Weyside main works, and refers them to West Surrey Shadow Executive for consent.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNine contracts over £200k cleared to start
MoneyUp to £33.37m main worksLargest single contract in pipeline
What happens nextRefer to West Surrey Shadow ExecutiveThen delegate award to officer
Who it affectsFinance, IT, housing, fleet, WeysiteContracts span multiple council services

What was decided

The Executive approved the start of procurement for the nine projects listed in Appendix 1.

The pipeline will be recommended to the West Surrey Shadow Executive for consent under the Section 24 Direction and General Consent.

Authority to award each contract, after all consents, is delegated to the Joint Strategic Director for Finance and Resources, in consultation with the Lead Councillor for Finance.

Why

Procurements that may lead to a Key Decision on award need prior Executive sign-off, and a single pipeline report is more efficient than separate papers.

The Council says this approach supports good governance, compliance with procurement law and its own Contract Procedure Rules, and the consideration of social value, climate and modern slavery risks.

What happens next

Each project is to be put to market using the route shown in Appendix 1, with portfolio holder consultation where required. Report P1

A separate Executive paper will be brought for award where it is a Key Decision, unless authority has been delegated to an officer.

The money

  • £300k Weyside Urban Village Project Manager, 3 years Report P2
  • £200k Integration and automation platform, 1+1 year Report P3
  • £500k Replacement Asset Management Solution, 3+1+1 years Report P4
  • £1.5m Fire Safety Equipment installation, servicing and maintenance, 3+2 years Report P5
  • £2.5m Variation to Gas and Electricity contract, 1 year Report P5
  • £10m Fleet of vehicles purchase, 3 years Report P6
  • £250K Variation of Gleeds contract for Weyside PM, QS and EA role, 2+1 years Report P7
  • £5.67m Phase 4 enabling works infrastructure at Weyside, 1 year Report P8
  • £33.37m Phase 4 main works infrastructure at Weyside, 1 year Report P9

Options considered

  • Chosen: Approve the consolidated procurement pipeline and delegate award to an officer. Avoids multiple individual reports and is more agile; the Council cites governance, compliance and value for money
  • Rejected: Bring each procurement to the Executive separately. Would take more time and cost in writing individual reports

Implications

  • Financial: Pipeline covers contracts with values ranging from £200k to £33.37m; a £9.7m original Gas and Electricity contract is to be varied by £2.5m to match other D&B arrangements. Report P5, P9
  • Legal: Award is subject to the Section 24 Direction and the General Consent, so projects must also obtain West Surrey Shadow Executive consent.
  • Other: The Council says it will consider environmental and climate impact, social value and modern slavery risk in each procurement.
  • Staffing: Some procurements are joint long-term contracts with Waverley Borough Council, including the Weyside enabling and main works. Report P8, P9

Who and where

  • Finance and Resources service, including IT, Revenues and Customer Communications, Housing, Assets and Property, and Environmental Services Report P1
  • Regeneration and Economic Development service, leading on Weyside Urban Village Report P2, P7, P8, P9
  • Waverley Borough Council as joint contracting partner on Weyside works and Gleeds variation Report P7, P8, P9
  • West Surrey Shadow Executive, which must consent to the projects

Timeline

  • 20 August 2026: Executive approves the procurement pipeline
  • Beyond vesting day: All contracts require Strategic Director for Stability sign-off as part of local government reorganisation transition Report P2, P3, P4, P5, P6, P7, P8, P9
  • 3 Years: Term for the Weyside Project Manager contract Report P2
  • 1+1 Year: Term for the integration and automation platform contract Report P3
  • 3+1+1 Years: Term for the replacement Asset Management Solution Report P4
  • 3+2 Years: Term for the Fire Safety Equipment contract Report P5
  • 1 Year: Proposed variation term for Gas and Electricity contract Report P5
  • 3 Years: Term for the vehicle fleet purchase Report P6
  • 2+1 years: Term for the Gleeds PM, QS and EA variation Report P7
  • 1 year: Term for Phase 4 enabling and main works at Weyside Report P8, P9

Plain English for the jargon

  • Section 24 Direction: A statutory direction covering how the council must operate pending local government reorganisation in Surrey.
  • General Consent: Consent mechanism under which the West Surrey Shadow Executive must agree to certain council decisions.
  • Key Decision: An executive decision that is significant in budget, policy or impact, requiring prior approval.
  • Weyside Urban Village: Major regeneration scheme in Guildford, delivered jointly with Waverley Borough Council.
  • LGR: Local government reorganisation, the restructuring of Surrey's councils.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX46

Resolved

To approve commencement of the procurement process for the projects listed in Appendix 1 to this report; 2. To recommend the projects listed in Appendix 1 to the West Surrey Shadow Executive for consent in accordance with the requirements of the Section 24 Direction and the General Consent; and 3. To delegate authority to the Joint Strategic Director for Finance and Resources, after consultation with the Lead Councillor for Finance and upon selection of a successful contractor, to award the contracts listed in Appendix 1, once all necessary approvals and consents have been obtained. Reason(s): 1. The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a Key Decision prior to procurement procedures formally commencing. 2. Planning procurement activity ensures: · effective stakeholder management ? · effective procurement and sourcing ? · compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules ?? · there is consideration on how contract price is to be managed in contract and what contract price model will be used ? · our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk. ?? · how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract. 3. This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity. 4. When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer. Other options considered and rejected by the Executive: Bring each individual item to the Executive, which will incur more time and cost writing individual reports, so is not recommended. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Procurement Pipeline GBC – 20 August 2026 – Appendix 1 Potential route Anticipated Estimated to market Joint Requested LGR PP No. URN Contract Title Brief Description Service Service Lead Contract Term Value (subject to procurement authority for award implications (Including Exts.) (£’000) options ? sign off. appraisal)

Strategic Director for Stability required Project Appointment of project Finance & Regeneration & beyond vesting Manager manager to support Resources in 159 CRPN-00613 Economic Abi Lewis 3 Years £300k TBC No day. No Weyside delivery of Weyside Urban Consultation with Development requirement for Urban Village Village Portfolio Holder for WBC Finance

Provision of an integration and automation platform Strategic Director for from 2027 that enables Stability required Integration Finance & GBC to move into a unified Communications beyond vesting and Resources in 161 CRPN-00598 architecture where legacy & Customer James Beach 1+1 Year £200k Framework No day. No Automation Consultation with systems, modern APIs, Service requirement for Platform Portfolio Holder for and autonomous agents WBC Finance interact securely on a single foundation.

Updated Asset Management solution Strategic Director for designed to help GBC Stability required Replacement Finance & manage their housing and beyond vesting Asset Housing Resources in 162 CRPN-00615 property assets more Nicola Philp 3+1+1 Years £500k TBC No day. No Management Services Consultation with strategically, providing requirement for Solution Portfolio Holder for tools for effective data WBC Finance management, compliance, and decision-making.

Fire Safety Strategic Director for Equipment – Finance & Installation, servicing and Yogesh Stability required installation, Housing Resources in 164 CRPN-00TBC maintenance contract for Vadgama/Pa 3+2 Years £1.5m Open Procedure Yes beyond vesting maintenance, Services Consultation with all fire equipment assets ul Cleaver day. and servicing Portfolio Holder for contract Finance Strategic Director for Brings GBC in- Variation to Extending Provision of Estimated: Finance & Variation line with supply Gas and Gas and Electricity to GBC Assets & Original: 3 Years £9.7m Resources in 165 CRPN-00593 Jude Cozens Compliant with No terms of other Electricity to match terms of other Property Variation: 1 Year Proposed: Consultation with Regs D&B forming Contract D&B arrangements £2.5m Portfolio Holder for West Surrey Finance

Strategic Director for Stability required Finance & beyond vesting Vehicles To procure fleet of vehicles Environmental Resources in 166 CRP-00084 Steve Skinner 3 Years £10m Framework No day. No Purchase in Environmental Services Services Consultation with requirement for Portfolio Holder for WBC Finance

Variation of existing Strategic Director for Stability required Phase 1 & 3 contract with Gleeds to Finance & Regeneration & beyond vesting Infrastructure appoint them to perform Resources in 168 CRPN-00590 Economic Abi Lewis 2 + 1 years £250K N/A No day. This is a joint Weyside PM, QS and EA role for Consultation with Development long term contract Urban Village Phase 1 and 3 Portfolio Holder for with GBC Infrastructure Finance

Phase 4 Procurement of contractor Strategic Director for Onsite to deliver enabling works Stability required Finance & infrastructure package for Weyside Regeneration & beyond vesting Competitive Flex Resources in 170 CRPN-00661 enabling Phase 4 onsite Economic Abi Lewis 1 year £5.67m No day. This is a joint Procedure Consultation with works infrastructure (i.e. Development long term contract Portfolio Holder for Weyside demolition of existing with GBC Finance Urban Village sewage treatment works)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement Pipeline App1: 200826Report 69 KB DownloadRead as text
PDF
Procurement Pipeline Report: over £200k (2025-2026)Report 132 KB Download

At this meeting

Whole meeting

Who was there

5 of 8 attended
JM
Councillor Julia McShaneChairperson, apologies
VK
Councillor Vanessa KingVice-Chairperson, present
PB
Councillor Phil BellamyCommittee Member, present
AG
Councillor Angela GoodwinCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, apologies
FW
Councillor Fiona WhiteCommittee Member, present
SK
Sharon KeenlysideCouncil Staff, expected

On this subject at Guildford

Search all
  1. Procurement Pipeline Report - over £200k (2025-2026)This decision
  2. Procurement Pipeline Report - over £200k (2025-2026)Approved
  3. Procurement Pipeline Report - over £200k (2025-2026)Approved
  4. Procurement Pipeline Report - over £200k (2025-2026)Approved
  5. Procurement Pipeline Report - over £200k (2025-2026)Approved
  6. Procurement Pipeline Report - over £200k (2025-2026)Approved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies