Guildford Borough Council
Executive, Thursday 25 June 2026 at 7.00pm

Procurement Pipeline Report - over £200k (2025-2026)

Approved Executive 2 papers

AI summaryGuildford Borough Council Executive approved a consolidated procurement pipeline of projects over £200,000 and delegated contract award authority to the Joint Strategic Director for Finance and Resources.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedStart procurement for Appendix 1 projects, award to officer
MoneyOver £200,000 thresholdPer Contract Procedure Rules for Key Decisions
What happens nextProcurement team to proceed to marketService areas to run tender exercises
Who it affectsSuppliers and Shadow West Surrey CouncilConsent may be needed for larger contracts

What was decided

The Executive approved the start of procurement for the projects listed in Appendix 1 of the report. Report P5

Authority to award those contracts was delegated to the Joint Strategic Director for Finance and Resources, after consulting the Lead Councillor for Finance, once a successful contractor is chosen. Report P6, 1.3

Using one consolidated pipeline report was preferred to submitting multiple individual reports for each procurement. Report 3.3, P50

Why

The Council's Contract Procedure Rules require Executive permission before any procurement that may lead to a Key Decision, where the value is over £200,000 or it significantly affects two or more wards. Report 1.1, 3.1

Planning procurements in advance supports stakeholder management, legal compliance, ethical buying, social value, and best value over the life of contracts. Report 3.2, P9, P10, P11, P12, P13, P14

A consolidated approach is more agile and saves officer and Executive time compared with bringing each item to Executive separately. Report 11.1, P50, P51

What happens next

The Procurement team and the relevant service areas will go to market for the projects in Appendix 1 and then run an award process. Report 4.1, P17

If a procurement produces a Key Decision award and no delegation exists, a separate Executive paper will be needed for award approval. Report 3.4

A direction under section 24 of the Local Government and Public Involvement in Health Act 2007 is expected by 30 June 2026 and may require Shadow West Surrey Council consent for property, capital, and longer-term non-capital contracts. Report 8.5, 8.6, P38, P39, P40, P41

The money

  • £200,000 Threshold above which Executive must approve procurement commencement Report 1.1
  • £100,000 Threshold above which property transactions may need Shadow Authority consent Report P38
  • £1,000,000 Threshold above which capital contracts may need Shadow Authority consent Report P39
  • £100m (inc VAT) Annual third party spend level that triggers Procurement Act 2023 pipeline notices Report 6.5
  • £2m (inc VAT) Estimated value above which individual pipeline notices would be required Report 6.5

Options considered

  • Chosen: Bring a consolidated procurement pipeline to Executive at periodic intervals. Saves officer and Executive time, reflects strategic planned approach Report P50, 11.1
  • Rejected: Bring each individual procurement item to the Executive separately. Would take more time and cost writing individual reports Report P51

Implications

  • Legal: The Surrey (Structural Changes) Order 2026 came into effect on 10 March 2026; a section 24 direction, expected by 30 June 2026, may require Shadow West Surrey Council consent before the Council enters certain contracts. Report 8.3, 8.5, 8.6, 8.7, 8.8, P56, P57
  • Legal: Any contract entered into in contravention of a section 24 direction would be void and could not be enforced by or against West Surrey Council or Guildford Borough Council. Report 8.8
  • Risk: Without planned pipelines and approvals there is a heightened risk of non-compliant spend as contracts may expire before re-procurement, and reduced ability to engage the market early. Report 10.2
  • Staffing: More resource is expected from the Procurement team to draft Executive papers and from service areas acting as subject experts. Report 10.1
  • Equalities: The Public Sector Equality Duty applies; the report itself has no direct equality and diversity implications, with detailed work to follow on each project. Report P61, P62, P63, P64
  • Climate: No direct climate change or sustainability implications for this report; project-level assessments will follow. Report P66
  • Financial: No direct financial implications from this report; financial approval will be sought before any procurement starts. Report P53

Who and where

  • Suppliers, including small and medium enterprises and the voluntary, community and social enterprise sector Report 7.2, P32
  • Waverley Borough Council, as a potential collaboration partner Report 6.3, 8.1, 8.2
  • Shadow West Surrey Council, which may need to consent to certain contracts Report 8.5, 8.6
  • Guildford Borough Council service areas and Procurement team Report 10.1, 4.1

Timeline

  • 10 March 2026: Surrey (Structural Changes) Order 2026 came into effect Report 8.3
  • 28 May 2026: Previous procurement pipeline presented to Executive Report 1.2
  • 2026-06-25: Executive decision to approve updated pipeline and delegate award authority
  • By 30 June 2026 (expected): Possible issue of a section 24 direction requiring Shadow Authority consent for certain contracts Report 8.5
  • 1 April 2027: Vesting Day for West Surrey Council Report 8.3

Plain English for the jargon

  • CPRs: The Council's Contract Procedure Rules, introduced in updated form in June 2024
  • Key Decision: An Executive decision of significant financial or cross-ward impact that needs formal approval
  • Procurement Act 2023: UK legislation governing how public sector bodies must run procurements
  • Section 24 direction: A direction under the Local Government and Public Involvement in Health Act 2007 that can require a shadow authority to consent to certain council actions
  • Shadow Authority: The shadow West Surrey Council being set up ahead of the transfer of functions
  • Vesting Day: The date on which the new West Surrey Council takes on its functions, set as 1 April 2027
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX23

Resolved

Approve commencement of the procurement process for the projects listed in Appendix 1 to this report; and 2. delegate authority to the Joint Strategic Director for Finance and Resources, after consultation with the Lead Councillor for Finance and upon selection of a successful contractor, to award the contracts listed in Appendix 1. Reason(s): 1. The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a Key Decision prior to procurement procedures formally commencing. 2. Planning procurement activity ensures: • effective stakeholder management • effective procurement and sourcing • compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules • there is consideration on how contract price is to be managed in contract and what contract price model will be used • our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk. • how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract. 3. This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity. 4. When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer. Other options considered and rejected by the Executive: Bring each individual item to the Executive, which will incur more time and cost writing individual reports, so is not recommended. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive summary

1.1The Council’s Contract Procedure Rules (CPRs) provide that the Executive must give permission to commence any procurement activity which could result in the award being a Key Decision if the estimated value is greater than £200k or it significantly impacts two or more wards within the Borough.

1.2This report provides an update of the procurement pipeline which was presented to Executive on 28 May 2026. The pipeline set out in Appendix 1 to this report includes additional projects which are likely to result in Key Decisions and seeks Executive agreement for procurements to commence.

1.3In addition, delegated authority is sought for the Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor following an appropriate tendering process, to enter contracts for the award of the projects set out in Appendix 1.

Recommendations

2.1That the Executive resolves to:

(1) Approve commencement of the procurement process for the projects listed in Appendix 1 to this report.

(2) Delegate authority to the Joint Strategic Director for Finance and Resources, after consultation with the Lead Councillor for Finance and upon selection of a successful contractor, to award the contracts listed in Appendix 1.

Reasons for recommendation

3.1The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a Key Decision prior to procurement procedures formally commencing. Procurement Pipeline Report – over £200k (2026-27)

3.2Planning procurement activity ensures:

• effective stakeholder management

• effective procurement and sourcing

• compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules

• there is consideration on how contract price is to be managed in contract and what contract price model will be used

• our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk.

• how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract.

3.3This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity.

3.4When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer.

4 Next steps

4.1If approved, the Procurement team and the relevant Service Area will proceed to market for the procurements listed in Appendix 1 and on conclusion of the procurement exercise, will proceed to award process and obtain relevant approvals.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
_GBC Procurement Pipeline 250626v2Appendix 1 98 KB Download
PDF
Procurement Pipeline Report: over £200k (2025-2026)Report 134 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
JM
Councillor Julia McShaneChairperson, present
VK
Councillor Vanessa KingVice-Chairperson, present
PB
Councillor Phil BellamyCommittee Member, present
AG
Councillor Angela GoodwinCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, present
SK
Sharon KeenlysideCouncil Staff, expected

On this subject at Guildford

Search all
  1. Procurement Pipeline Report - over £200k (2025-2026)This decision
  2. Procurement Pipeline Report - over £200k (2025-2026)Approved
  3. Procurement Pipeline Report - over £200k (2025-2026)Approved
  4. Procurement Pipeline Report - over £200k (2025-2026)Approved
  5. Procurement Pipeline Report - over £200k (2025-2026)Approved
  6. Procurement Pipeline Report - over £200k (2025-2026)Approved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open