Executive, Thursday 4 December 2025 at 6.00pm

GBC Kitchen and Bathroom 3+1+1-Year Contract

Agreed Executive 1 paper

AI summaryGuildford Executive backs joint 3+1+1 year kitchen and bathroom contract with Waverley, with £12.5m HRA funding to go to full Council on 9 December 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSubject to Council approving the £12.5m budget
Money£12.5m HRA capital£2.5m per year for five years from 2026/27
What happens nextFull Council 9 December 2025To approve £12.5m HRA capital funding
Who it affectsGBC council housing tenantsAround 260 kitchens and 130 bathrooms a year

What was decided

The Executive agreed the business case and, subject to Council budget approval, delegated authority to the Joint Strategic Director of Finance and Resources, in consultation with the Joint Assistant Director of Housing and the Lead Councillor for Finance, to run a joint procurement with Waverley Borough Council and award a 3-year contract with the option to extend by 1+1 years. Report 2.1, 2.2, P9

The Executive resolved to recommend that full Council on 9 December 2025 approves £12.5m of Housing Revenue Account capital funding for replacement kitchens and bathrooms between 2026/27 and 2031/32. Report 2.3, P10

Why

Social housing landlords must meet and maintain the Government Decent Homes Standard, and GBC data indicates around 260 kitchens and 130 bathrooms will fall below the standard each year over the next five years. Report 3.1, 3.2, 6.7

A long-term joint contract with Waverley is expected to deliver economies of scale, value for money, and consistent services, and the 3+1+1 term allows reassessment at break points as West Surrey moves towards Local Government Reorganisation. Report 3.3, 3.4, 8.2, 8.3, 8.4

An earlier joint procurement was abandoned in August 2025 under section 31(1)(a) of the Procurement Act 2023, and GBC currently relies on a one-year interim contract. Report 6.1, 6.2

What happens next

A working group of GBC and Waverley housing and procurement officers will agree scope, specification, and tender details for the joint procurement and award. Report 4.1, 4.3

A new joint 3+1+1 year contract is anticipated to be in place by November 2026, with resident engagement co-created through the Tenants Engagement Group. Report 4.2, 4.4

Full Council on 9 December 2025 is asked to approve £12.5m of HRA capital funding; spend will be monitored through the Capital Programme Board and a funds checker within requisitions. Report P10, P77

The money

  • £12.5m HRA capital funding for kitchens and bathrooms 2026/27 to 2031/32, at £2.5m per year Report 2.3, P10, 6.11
  • £2.5m Estimated annual cost of the procurement
  • £5.5m Existing 2025/26 budget within the HRA Major Repairs and Improvements Capital Programme

Options considered

  • Rejected: Option 1: Defer the longer-term procurement and extend the interim arrangement, subject to performance and procurement rules. Likely non-compliant with procurement regulations and does not address longer-term needs or the corporate priority to procure collaboratively Report 11.1, P68, P69, P70
  • Chosen: Option 2: Run a compliant procurement for a 5-year contract in collaboration with Waverley Borough Council. Delivers economies of scale, value for money, and consistent services, and fits Local Government Reorganisation planning Report 11.2, 3.4, 8.2, 8.3

Implications

  • Financial: The £12.5m is the gross maximum value of the contract and will not be exceeded, with controls via the funds checker and Capital Programme Board oversight. Report 6.8, P77
  • Legal: Procurement must comply with the Procurement Act 2023, the Public Contracts Regulations 2015, and the Council's Contract Procedure Rules; any contract in place at reorganisation will transfer to the new authority. Report 6.1, 10.9
  • Equalities: The Public Sector Equality Duty has been considered and no immediate equality implications arise; the programme design will consider communication needs, household characteristics, and disabled adaptations. Report 12.3, P82, P87, P88
  • Climate: Bidders will be asked to show how their carbon reduction targets align with GBC's net zero by 2030 goal and how they support the Climate Change Strategy, including material sourcing, transport, waste, and recycling. Report 12.4, 12.5, 12.6, 12.7
  • Risk: Key risks are service delays and failure to meet the Decent Homes Standard without a long-term contract, insufficient HRA funds, market reticence after the abandoned procurement, and LGR uncertainty, each with mitigations set out. Report 10.2, 10.3, 10.4, 10.5, 10.6, 10.7, 10.8, 10.9
  • Other: The proposal supports several strategic objectives, including decent and affordable homes, a more sustainable borough, a more prosperous borough, and a resilient and well managed council. Report 7.2, 7.3, 7.4, 7.5

Who and where

  • GBC council housing tenants needing kitchen and bathroom replacements Report 3.2, 6.6, 6.7
  • GBC and Waverley housing and procurement officers delivering the joint programme Report 4.1, 6.3
  • Waverley Borough Council as joint procurement partner Report 1.3, 2.2, 3.4, 3.5
  • Future West Surrey unitary authority inheriting the contract at reorganisation Report 8.3, 8.4, 10.9
  • Supply chain bidders for the kitchen and bathroom contract Report 6.12, 10.6, 10.7, 12.4

Timeline

  • 1 April 2025: Waverley Borough Council agreed to commence its own procurement with a £12.6m budget Report 3.5
  • August 2025: Earlier joint procurement abandoned under section 31(1)(a) of the Procurement Act 2023 and a one-year interim contract put in place Report 6.1, 6.2
  • 4 December 2025: GBC Executive agreed the business case and recommended £12.5m HRA funding to full Council Report 2.3
  • 9 December 2025: Full Council asked to approve £12.5m of HRA capital funding for 2026/27 to 2031/32 Report 2.3, P10
  • 2026/27 to 2031/32: Delivery of around 260 kitchens and 130 bathroom replacements per year within £2.5m annual budget Report 1.5, 3.2, 6.7, 6.11
  • November 2026: New joint 3+1+1 year contract anticipated to be in place Report 1.4, 4.2

Plain English for the jargon

  • Decent Homes Standard: Government standard that social housing landlords must meet and maintain for the condition of their homes, including components like kitchens and bathrooms.
  • HRA (Housing Revenue Account): A ring-fenced account that local authorities use to manage income and spending on their own council housing.
  • LGR (Local Government Reorganisation): The restructuring of councils in West Surrey that will create a new unitary authority, with existing contracts expected to transfer to it.
  • Procurement Act 2023, section 31(1)(a): The legal provision under which the earlier joint procurement was abandoned as a modification of a section 19 procurement.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX90

Resolved

Note and agree the business case set out in this report; 2. Subject to Council approving the budget to delegate authority to the Joint Strategic Director of Finance & Resources, in consultation with the Joint Assistant Director of Housing and the Lead Councillor for Finance, to commence a joint procurement with Waverley Borough Council and to subsequently award a contract for 3 Years with the option to extend for a further 1+1 year, kitchen and bathroom contract in compliance with the Contract Procedure Rules and within the approved budgets; and 3. Recommend to full Council, meeting 9 December 2025, to approve Housing Revenue Account (HRA) Capital Funding of £12.5m for replacement kitchens and bathrooms between 2026/27 and 2031/32 Reason(s): 1. Social Housing Landlords have an ongoing requirement to meet and maintain the Governments’ Decent Homes Standard. Replacing and improving components, such as kitchens and bathrooms, that are old and in poor condition, help us meet that requirement. 2. GBC’s current decent homes data indicates that c260 kitchens and c130 bathrooms will become non-decent annually over the 5-year horizon. 3. Procuring and having in place a long-term kitchen and bathroom contract will allow GBC to efficiently and economically delivery kitchen and bathroom improvements to resident’s homes. 4. The Procurement Strategy for GBC and WBC is to wherever possible procure services and works jointly to utilise economies of scale, procure services efficiently and economically, and deliver effective and consistent services to residents. 5. Waverley Borough Council agreed to commence the procurement for a Kitchen and Bathrooms contract on the 1 April 2025, for a budget of £12.6m, which is sufficient to cover a five-year contract. Other options considered and rejected by the Executive: Option 1 - Defer procurement of a longer-term contract and extend the term of the interim arrangement, subject to satisfactory performance and compliance with procurement regulations Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive summary

1.1Social Housing Landlords have an on-going duty to meet and maintain the Government’s Decent Homes Standard. Planned capital works programmes for the improvement and replacement of components such as kitchens and bathrooms are key to ensuring that duty is met.

1.2Long-term strategic procurement of capital works programmes provide certainty of cost, quality, and timely delivery supporting Guildford Borough Council’s (GBC) duty to provide compliant and well governed value for money services.

1.3GBC and Waverley Borough Council (WBC) both require new kitchen and bathroom contracts. Procuring these jointly maximises the opportunities from economies of scale and supports the corporate objective to work and procure services collaboratively.

1.4This report recommends commencing a joint GBC and WBC procurement for the supply and installation of kitchens and bathrooms via 3-year contract with the option to extend by up to a further 2-years (a 3+1+1 Year Contract) commencing November 2026.

1.5This report and proposal recommend the approval of £12.5m of GBC Housing Revenue Account (HRA) Capital Funding (£2.5m per annum) to improve c260 kitchens and c130 bathrooms per annum between the period 2026/27 to 2031/32.

Recommendations

That the Executive resolves to:

2.1Note and agree the business case set out in this report;

2.2Subject to Council approving the budget to delegate authority to the Joint Strategic Director of Finance & Resources, in consultation with the Joint Assistant Director of Housing and the Lead Councillor for Finance, to commence a joint procurement with Waverley Borough 2 GBC Kitchen and Bathroom 5-Year Contract

Council and to subsequently award a contract for 3 Years with the option to extend for a further 1+1 year, kitchen and bathroom contract in compliance with the Contract Procedure Rules and within the approved budgets; and

To recommend that full Council, meeting 9 December 2025, agrees to:

2.3Approve Housing Revenue Account (HRA) Capital Funding of £12.5m for replacement kitchens and bathrooms between 2026/27 and 2031/32.

3 Reason(s) for recommendation:

3.1Social Housing Landlords have an ongoing requirement to meet and maintain the Governments’ Decent Homes Standard. Replacing and improving components, such as kitchens and bathrooms, that are old and in poor condition, help us meet that requirement.

3.2GBC’s current decent homes data indicates that c260 kitchens and c130 bathrooms will become non-decent annually over the 5-year horizon.

3.3Procuring and having in place a long-term kitchen and bathroom contract will allow GBC to efficiently and economically delivery kitchen and bathroom improvements to resident’s homes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GBC Kitchen and Bathroom 3+1+1-Year ContractReport 136 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
JM
Councillor Julia McShaneChairperson, present
TH
Councillor Tom HuntVice-Chair, present
AG
Councillor Angela GoodwinCommittee Member, present
CH
Councillor Catherine HoustonCommittee Member, present
RL
Councillor Richard LucasCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, apologies
SK
Sharon KeenlysideCouncil Staff, expected

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies