Guildford Borough Council
Executive, Thursday 4 December 2025 at 6.00pm

Procurement Pipeline Report - over £200k (2025-2026)

Approved Executive 2 papers

AI summaryGuildford Borough Council's Executive approved starting procurement for projects over £200,000 listed in Appendix 1 and delegated award authority to the Joint Strategic Director for Finance and Resources, after consulting the Lead Councillor for Finance.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProcurement process to begin for Appendix 1 projects
MoneyOver £200,000 thresholdEach project exceeds £200,000 or affects two or more wards
What happens nextProcurement team to proceed to marketThen move to award process and obtain approvals
Who it affectsProcurement team and service areasWill run tendering for projects in Appendix 1

What was decided

The Executive approved the start of the procurement process for the projects listed in Appendix 1. Report P5

Authority to award the contracts was delegated to the Joint Strategic Director for Finance and Resources, after consulting the Lead Councillor for Finance. Report P5, 1.3

The report does not commit the Council to running the procurements, the stated sourcing route, or collaboration with Waverley Borough Council. Report 6.6

Why

The Council's Contract Procedure Rules require Executive approval before starting any procurement that may lead to a key decision, as a matter of good governance. Report 1.1, 3.1

Planning procurement in advance supports stakeholder management, compliance with procurement law, ethical sourcing, contract price management, and best value. Report 3.2, P9, P10, P11, P12, P13, P14

A consolidated pipeline avoids the need for multiple individual approval reports, saving time and making the process more agile. Report 3.3, P40

What happens next

The Procurement team and the relevant service area will go to market for the projects in Appendix 1. Report 4.1

On conclusion of each procurement, the team will move to the award process and obtain the relevant approvals, with the delegated officer able to award. Report 4.1, P5

Future pipeline updates will be brought to the Executive at periodic intervals to continue the strategic forward planning approach. Report P39, 6.3

The money

  • £200k Threshold above which Executive approval is needed before starting procurement Report 1.1
  • £2m (inc VAT) Estimated value threshold for individual pipeline notices under the Procurement Act 2023 Report 6.5
  • £100m (inc VAT) Annual third party supplier spend that triggers the pipeline notice duty Report 6.5

Options considered

  • Chosen: Bring a consolidated procurement pipeline to the Executive at periodic intervals. Saves officer and Executive time, reduces procurement lead times, supports a more strategic approach Report P39
  • Rejected: Bring each individual item to the Executive as a separate report. Incurs more time and cost writing individual reports Report P40

Implications

  • Staffing: More resource is needed from the Procurement team to draft papers and from service areas as subject matter experts. Report 10.1
  • Risk: Without planned pipelines there is a heightened risk of non-compliant spend as contracts may expire before re-procurement. Report 10.2
  • Financial: No direct financial implications; financial approval will be sought before any procurement commences. Report P42
  • Legal: No direct legal implications; the Council's Procurement and Legal teams will provide project-specific advice. Report P43, P44
  • Equalities: No direct equality and diversity implications from this report; Public Sector Equality Duty considered at project level. Report P49
  • Climate: No direct climate change or sustainability implications from this report; to be considered at project level. Report 12.5

Who and where

  • The Council's Procurement team and relevant service areas Report 4.1, 6.3
  • Suppliers and potential bidders, including small and medium enterprises and the voluntary, community and social enterprise sector Report 7.2
  • Waverley Borough Council, as a possible collaboration partner Report 6.3, 6.4, 8.1
  • The Lead Councillor for Finance, who must be consulted before contract award Report P5, 1.3

Timeline

  • 6 November 2025: Previous procurement pipeline presented to the Executive Report 1.2
  • 2025-12-04: Executive considers updated pipeline and delegates award authority Report P5
  • Every 18 months (if annual third party spend exceeds £100m inc VAT): Council must publish individual pipeline notices for procurements over £2m inc VAT under the Procurement Act 2023 Report 6.5
  • Periodic intervals after approval: Future pipeline updates will return to the Executive Report P39

Plain English for the jargon

  • CPRs: The Council's Contract Procedure Rules, introduced in updated form in June 2024, which govern how procurements are run and approved.
  • Key Decision: A procurement where the estimated contract value is over £200,000 or which significantly affects two or more wards in the Borough.
  • VCSE sector: Voluntary, community and social enterprise organisations, which the Council wants to consider as potential suppliers.
  • SME: Small and medium sized enterprises, which the Council wants to avoid putting at a disadvantage in its procurements.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX92

Resolved

Approve commencement of the procurement process for the projects listed in Appendix 1 to this report. 2. Delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award the contracts listed in Appendix 1: Reason(s): 1. The Executive is required to approve, prior to their commencement, all procurement activity which may require a key decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a key decision prior to procurement procedures formally commencing. 2. Planning procurement activity ensures: · effective stakeholder management ? · effective procurement and sourcing ? · compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules ?? · there is consideration on how contract price is to be managed in contract and what contract price model will be used ? · our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk. ?? · how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract. 3. This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity. 4. When a procurement activity is concluded Executive approval for any consequent contract award which would be a key decision will be sought by a separate report, unless authority is specifically delegated to an officer. Other options considered and rejected by the Executive: Bring each individual item to the Executive, which will incur more time and cost writing individual reports, so is not recommended. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive summary

1.1The Council’s Contract Procedure Rules (CPRs) provide that the Executive must give permission to commence any procurement activity which could result in the award being a key decision as the estimated value is greater than £200k or it significantly impacts two or more wards within the Borough.

1.2This report provides an update of the procurement pipeline which was presented to Executive on 6 November 2025. The pipeline set out in Appendix 1 to this report includes additional projects which are likely to result in Key Decisions and seeks Executive agreement for procurements to commence.

1.3In addition, delegated authority is sought for the Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor following an appropriate tendering process, to enter contracts for the award of the projects set out in Appendix 1.

Recommendations

2.1That the Executive resolves to:

(1) Approve commencement of the procurement process for the projects listed in Appendix 1 to this report. (2) Delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award the following contracts listed in Appendix 1:

3 Reason(s) for recommendation:

3.1The Executive is required to approve, prior to their commencement, all procurement activity which may require a key decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a key decision prior to procurement procedures formally commencing.

3.2Planning procurement activity ensures: Procurement Pipeline Report – over £200k (2025-2026)

• effective stakeholder management

• effective procurement and sourcing

• compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules

• there is consideration on how contract price is to be managed in contract and what contract price model will be used

• our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk.

• how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract.

3.3This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity.

3.4When a procurement activity is concluded Executive approval for any consequent contract award which would be a key decision will be sought by a separate report, unless authority is specifically delegated to an officer.

4 Next steps

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GBC Procurement Pipeline 041225_v2Appendix 1 133 KB Download
PDF
Procurement Pipeline Report: over £200k (2025-2026)Report 127 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
JM
Councillor Julia McShaneChairperson, present
TH
Councillor Tom HuntVice-Chair, present
AG
Councillor Angela GoodwinCommittee Member, present
CH
Councillor Catherine HoustonCommittee Member, present
RL
Councillor Richard LucasCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, apologies
SK
Sharon KeenlysideCouncil Staff, expected

On this subject at Guildford

Search all
  1. Procurement Pipeline Report - over £200k (2025-2026)This decision
  2. Procurement Pipeline Report - over £200k (2025-2026)Approved
  3. Procurement Pipeline Report - over £200k (2025-2026)Approved
  4. Procurement Pipeline Report - over £200k (2025-2026)Approved
  5. Procurement Pipeline Report - over £200k (2025-2026)Approved
  6. Procurement Pipeline Report - over £200k (2025-2026)Approved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open