Guildford Borough Council
Executive, Thursday 23 April 2026 at 7.00pm

Procurement Pipeline Report - over £200k (2025-2026)

Approved Executive 2 papers

AI summaryGuildford Borough Council Executive approved the start of procurement for projects in its over £200k pipeline and delegated contract award authority to the Joint Strategic Director for Finance and Resources.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProcurement may start for listed projects
MoneyNot stated
What happens nextProcurement to commenceListed projects in Appendix 1 to go to market
Who it affectsCouncil procurement, suppliersProjects over £200k that may be Key Decisions

What was decided

The Executive approved the start of procurement for the projects listed in Appendix 1 to the report. Report P5

Authority to award the listed contracts was delegated to the Joint Strategic Director for Finance and Resources, after consulting the Lead Councillor for Finance and selecting a successful contractor. Report P6, 1.3

Why

The Council's Contract Procedure Rules require Executive approval before starting any procurement that could lead to a Key Decision award, where the estimated value is over £200k or it significantly affects two or more wards. Report 1.1, 3.1

Bringing a consolidated pipeline avoids multiple separate approval requests and supports planning for stakeholder management, legal compliance, contract price modelling, ethical and social value considerations, and best value. Report 3.2, 3.3, P10, P11, P12, P13, P14, P15

Forward planning procurement activity also helps the Council prepare for any duty to publish pipeline notices under the Procurement Act 2023 if annual third party supplier spend exceeds £100m inc VAT. Report 6.5

What happens next

The Procurement team and relevant service areas will go to market for the procurements in Appendix 1 and then proceed to the award process, obtaining any further approvals needed. Report 4.1, P18

If a resulting contract award is itself a Key Decision and is not delegated, a separate Executive report will be brought for approval. Report 3.4

Article 24 directions under the 2007 Act are expected and may restrict entering certain contracts of certain values without West Surrey Council consent, so further advice will follow. Report P49

The money

  • greater than £200k Threshold above which procurement must be approved by Executive Report 1.1
  • greater than £100m (inc VAT) Third party supplier spend level that would trigger Procurement Act 2023 pipeline notice duties Report 6.5
  • over £2m (inc VAT) Estimated value above which individual pipeline notices may need publishing Report 6.5

Options considered

  • Chosen: Bring a consolidated pipeline of procurement activity at intervals, saving time and reflecting a strategic planned approach. Preferred option: reduces officer and Executive time and shortens procurement timelines Report P43, 11.1
  • Rejected: Bring each individual procurement item separately to the Executive. Would incur more time and cost writing individual reports Report P44

Implications

  • Legal: Any contract entered into under this approval must be necessary and proportionate to ensure continued service delivery up to and beyond the transfer of functions to West Surrey Council. Report 8.3, 8.4, P37
  • Legal: No direct legal implications arise from the report itself; project specific advice will be given by Procurement and Legal teams, and any Article 24 directions will be tracked. Report P47, P48, P49
  • Financial: No financial implications from this report; financial approval will be sought before any procurement commences. Report P46
  • Equalities: The Public Sector Equality Duty has been considered; no equality and diversity implications arise from this report. Report 12.3, P51, P52, P53, P54
  • Climate: No climate change or sustainability implications from this report; implications will be considered per project. Report 12.4, 12.5
  • Risk: Resource pressure on Procurement and service areas from preparing more Executive papers, and a heightened risk of non-compliant spend if pipelines and approvals are not planned. Report 10.1, 10.2
  • Other: Pipeline planning supports local suppliers, SMEs and the VCSE sector and may enable collaboration with Waverley Borough Council. Report 7.2, 8.1, 8.2

Who and where

  • Guildford Borough Council procurement team and service areas Report 4.1, 6.3, 10.1
  • Suppliers, including SMEs and the voluntary, community and social enterprise sector Report 7.2
  • Waverley Borough Council (potential collaboration partner) Report 6.3, 6.4, 8.1
  • West Surrey Council (successor body under the Surrey Structural Changes Order 2026) Report 8.3, 8.4, P37
  • Residents and stakeholders of affected wards where procurements may have an impact Report 1.1, 9.1

Timeline

  • June 2024: New Contract Procedure Rules were introduced Report 6.1
  • 10 March 2026: Surrey (Structural Changes) Order 2026 came into effect, placing duties on the Council up to Vesting Day Report 8.3
  • 19 March 2026: Previous procurement pipeline was presented to the Executive Report 1.2
  • 23 April 2026: Executive approved commencement of procurement and delegated award authority for the Appendix 1 pipeline Report 1.2
  • 1 April 2027: Vesting Day when Council functions transfer to West Surrey Council Report 8.3

Plain English for the jargon

  • Key Decision: An Executive decision of significant cost or impact, as defined in the Council's rules.
  • Contract Procedure Rules (CPRs): The Council's internal rules governing how contracts must be procured and awarded.
  • Procurement Act 2023: UK legislation setting new rules for public procurement, including pipeline notice duties for larger spending bodies.
  • Article 24 direction: A direction under the Local Government and Public Involvement in Health Act 2007 that can restrict councils from entering certain contracts without consent during reorganisation.
  • VCSE sector: Voluntary, community and social enterprise organisations.
  • Vesting Day: The date on which the new West Surrey Council takes on the transferred functions.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemEX158

Resolved

(1) To approve commencement of the procurement process for the projects listed in Appendix 1 to the report. (2) To delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award the contracts as listed in Appendix 1. Reasons: 1. The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a Key Decision prior to procurement procedures formally commencing. 2. Planning procurement activity ensures: · effective stakeholder management ? · effective procurement and sourcing ? · compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules ?? · there is consideration on how contract price is to be managed in contract and what contract price model will be used ? · our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk. ?? · how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract. 3. This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity. 4. When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer. Other options considered and rejected by the Executive: None. Details of any conflict of interest declared by the Leader or lead councillors and any dispensation granted: None.
Word for word from the decision Guildford published for this meeting. Source: democracy.guildford.gov.uk

Follow this further

Built from Guildford's papers

What the report saysPro

Report to Executive

Executive summary

1.1The Council’s Contract Procedure Rules (CPRs) provide that the Executive must give permission to commence any procurement activity which could result in the award being a Key Decision as the estimated value is greater than £200k or it significantly impacts two or more wards within the Borough.

1.2This report provides an update of the procurement pipeline which was presented to Executive on 19 March 2026. The pipeline set out in Appendix 1 to this report includes additional projects which are likely to result in Key Decisions and seeks Executive agreement for procurements to commence.

1.3In addition, delegated authority is sought for the Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor following an appropriate tendering process, to enter contracts for the award of the projects set out in Appendix 1.

Recommendations

2.1That the Executive resolves to:

(1) Approve commencement of the procurement process for the project(s) listed in Appendix 1 to this report.

(2) Delegate authority to the Joint Strategic Director for Finance and Resources, having consulted with the Lead Councillor for Finance and upon selection of a successful contractor, to award the contract(s) as listed in Appendix 1.

3 Reason(s) for recommendation:

3.1The Executive is required to approve, prior to their commencement, all procurement activity which may require a Key Decision for the contract award. It is good governance to seek approval by providing Executive with a summary of all proposed procurements that may result in a Key Decision prior to procurement procedures formally commencing. Procurement Pipeline Report – over £200k (2025-2026)

3.2Planning procurement activity ensures:

• effective stakeholder management

• effective procurement and sourcing

• compliance with relevant Procurement Legislation and the Council’s own Contract Procedure Rules

• there is consideration on how contract price is to be managed in contract and what contract price model will be used

• our procurement is ethical by considering factors such as environmental and climate change impact, social value and modern-day slavery risk.

• how best value is to be achieved is clearly defined including how contract management will ensure that the Council attains best value during the life of the contract.

3.3This report will avoid the need to submit multiple individual requests for approval to procure and award contracts, therefore being more agile in the approval process in relation to procurement activity.

3.4When a procurement activity is concluded Executive approval for any consequent contract award which would be a Key Decision will be sought by a separate report, unless authority is specifically delegated to an officer.

4 Next steps

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
_GBC Procurement Pipeline 240426Appendix 1 64 KB Download
PDF
Procurement Pipeline Report: over £200k (2025-2026)Report 131 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 8 attended
JM
Councillor Julia McShaneChairperson, present
VK
Councillor Vanessa KingVice-Chairperson, present
PB
Councillor Phil BellamyCommittee Member, present
AG
Councillor Angela GoodwinCommittee Member, present
CM
Councillor Carla MorsonCommittee Member, present
MR
Councillor Merel Rehorst-SmithCommittee Member, present
FW
Councillor Fiona WhiteCommittee Member, in attendance, virtual
SK
Sharon KeenlysideCouncil Staff, expected

On this subject at Guildford

Search all
  1. Procurement Pipeline Report - over £200k (2025-2026)This decision
  2. Procurement Pipeline Report - over £200k (2025-2026)Approved
  3. Procurement Pipeline Report - over £200k (2025-2026)Approved
  4. Procurement Pipeline Report - over £200k (2025-2026)Approved
  5. Procurement Pipeline Report - over £200k (2025-2026)Approved
  6. Procurement Pipeline Report - over £200k (2025-2026)Approved

More from Guildford Executive

All decisions
MeetingDecisionOutcome
17 Sep 2026 MinutesThe minutes of the meeting held on 20 August 2026 were confirmed. The Leader signed the minutes. : The minutes of the... Decided Open
17 Sep 2026 Delivery Plan Progress Report 2025/26 - 2026/27To note the summary of the actions delivered from the 2025/26 Delivery Plan and the progress made in Q1 and Q2 toward... Noted Open
17 Sep 2026 Scrutiny Review of the Council’s Heritage Service and Tourist Information CentreTo develop the strategic direction within the report at Appendix 1 into a fuller strategy for the Heritage Service, i... Approved Open
17 Sep 2026 Homelessness Review DecisionsApprove the contracting out of the Council’s statutory homelessness review function under section 202 of the Housing ... Approved Open
17 Sep 2026 GBC New Build Housing Development - Hurdle RatesTo adopt the proposed hurdle rate framework for affordable housing development schemes across the Borough as an indic... Approved Open