Corporate Network Strategy

Decided Executive 1 paper

Cabinet decided this item on Monday 9 November 2009. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED : That the Council commissions H&F Bridge Partnership (HFBP) to de-commission the affected components and install new equipment and services to both modernise the infrastructure and make it fit for purpose for at least a further five years, in accordance with the proposals set out in the separate report on the exempt part of the agenda.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Cabinet London Borough of Hammersmith & Fulham

9 NOVEMBER 2009

LEADER CORPORATE NETWORK STRATEGY Wards Councillor Stephen All Greenhalgh Significant parts of the existing corporate data network have been in service for over nine years and critical components have reached the end of their life. From May 2010 the products become unserviceable and will need to be replaced. There is also a need to remove the network hub from Stowe Road Depot prior to its sale.

Information about costings and sensitive technical aspects of the proposals are in a separate report on the exempt part of the Cabinet agenda.

CONTRIBUTORS Recommendation:

DFCS That the Council commissions H&F Bridge ADLDS Partnership (HFBP) to de-commission the David Green affected components and install new H&F Bridge equipment and services to both modernise Partnership the infrastructure and make it fit for purpose for at least a further five years, in accordance with the proposals set out in the separate HAS A PEIA BEEN report on the exempt part of the agenda. COMPLETED? YES 1. BACKGROUND

1.1HFBP operates a voice and data network on behalf of H&F which provides the core infrastructure on top of which the Council operates the rest of its IT systems. This network extends from the East London Data Centre and HTH and radiates out to over 60 sites around the borough and is illustrated in the attached diagram (see Appendix 1).

1.2The last round of significant investment in the corporate network took place in 2000 with the installation of the ATM based data, voice and video network.

1.3Additional investment has taken place since to build a fast data network (Gigabit Ethernet fibre ring) around the King Street area but the bulk of the network shown in dark shade on the diagram still relies on the old infrastructure.

1.4HFBP has recently been advised that as of June 2009 support for critical components in the current network (ATM) is being withdrawn by our system maintainers. This equipment has reached the end of its life and whilst they have offered to provide a hardware replacement service for a further year the affected components must be replaced by June 2010 if HFBP is going to be able to offer network support to H&F in the future.

1.5This has a significant business impact, should a network incident occur after June 2010 and the cause be an old network (ATM) component, HFBP may not be able to restore services to a significant number of users.

1.6The area affected encompasses many of the major strategic sites (nodes) on the current network including Hammersmith Town Hall (HTH), Fulham Town Hall (FTH), Bagleys Lane and the Stowe Road depot and their network connected satellite locations.

1.7In a major network incident, whilst major applications will still be available in the data centres they will not be accessible by staff across the borough affecting the delivery of front line services and consequently impacting residents.

1.8In a worst case scenario restoration of the service could take several months during which time new data links and equipment would need to be purchased, deployed, configured and tested before users would be back on line.

1.9Should this paper not be agreed in November then from May 2010 the Council may suffer more and longer outages of the type experienced in August 2009.

2. CURRENT ARRANGEMENTS

2.1The existing network is built from a series of point to point connections using a collection of private fibres, BT circuits, microwave dishes and laser links. This is centrally managed and operated by HFBP, it deploys a number of different networking technologies and has a number of single points of failure, in particular HTH which is the core hub from which most of the other network sites radiate.

2.2A major loss of service at HTH is of serious concern and a new design is needed to meet the Business Continuity requirements of the council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Network StrategyReport 140 KB DownloadRead as text

At this meeting

Whole meeting
1Minutes of the Cabinet Meeting held on 12 October 2009Noted 4The General Fund Capital Programme, Housing Revenue Capital Programme and Revenue Budget 2009/10 - Month 3 AmendmentsApproved 5Hammersmith & Fulham Council's Corporate Plan 2009/2012Approved 6Maximising European Social Fund (ESF) Funding in Hammersmith and FulhamApproved 7Funding Drawdown for the Smartworking Programme and Removal Expenses Related to the Decant of Riverview HouseNoted 8Serious Case Review into the Death of Baby JNoted 9Establishment of 'Generations Together' Programme in W12, North Fulham and Hammersmith BroadwayApproved
10Corporate Network StrategyThis decision
11Memorandum of Understanding with the PoliceApproved 12North End Road - Parallel InitiativesDecided 13Coningham Road/Goldhawk Road/Brackenbury Road CrossingApproved 14Fulham Road, Footway WorksApproved 15Bishops Park and Fulham Palace Grounds - Stage 2 Big/Heritage Lottery Fund, Parks for People ApplicationApproved 16Home Care and Housing Related Support Consultation - Results and Update on Procurement ProcessNoted 1716-19 Funding TransitionNoted 18Forward Plan of Key DecisionsOn the agenda 19Summary of Open Decisions taken by the Leader and Cabinet Members, and Reported to Cabinet for InformationOn the agenda 20Exclusion of Press and PublicDecided 21Exempt Minutes of the Cabinet Meeting Held on 12 October 2009 (E)Private 22Bishops Park and Fulham Palace Grounds - Stage 2 Big/Heritage Lottery Fund, Parks for People Application : Exempt Aspects (E)Private 23Memorandum of Understanding with the Police: Exempt Aspects (E)Private 24Corporate Network Strategy: Exempt Aspects (E)Private

Who was there

6 of 8 attended
SG
Councillor Stephen GreenhalghChairman, present
NB
Councillor Nicholas BotterillVice-Chair, present
PB
Councillor Paul BristowCommittee Member, present
LI
Councillor Lucy IvimyCommittee Member, present
ML
Councillor Mark LovedayCommittee Member, present
GS
Councillor Greg SmithCommittee Member, apologies
FS
Councillor Frances StaintonCommittee Member, apologies
SG
Councillor Sarah GoreCommittee Member, present

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies