That the review of the programme to date is noted. 2. That the HR and IT policy related to SmartWorking is noted. 3. That the sum of £673,332 is drawn down from the total sum of £3.944m set aside for SmartWorking, from the Efficiency Projects Reserve. 4. That a further sum of £290,000 be approved regarding the office move from Riverview House (and consequential moves of Corporate Finance to the Town Hall and the IT Training suite to the Macbeth Centre) funded from the central contingency for office moves/dilapidations. 5. That a sum of £60,000 be approved to fund a replacement IT training suite in Macbeth St for use in staff training and by Adult Education funded from the central contingency for office moves/dilapidations. 6. That the sum of £159,000 is approved to fund the SmartWorking of H&F Homes staff currently in Riverview House, and the associated removal and infrastructure costs relating to their move to the Town Hall Extension. 7. That settlement of the dilapidations claim relating to the termination of the Riverview House lease is delegated to the Director of Environment and Director of Finance & Corporate Services. 8. That a report is presented to Cabinet in March 2010 summarising the outcomes achieved and with a further business case and plan for the remaining roll out to the rest of the council (Stage C).
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
LEADER FUNDING DRAWDOWN FOR THE Wards Councillor Stephen SMARTWORKING PROGRAMME & All Greenhalgh REMOVAL EXPENSES RELATED TO THE DECANT OF RIVERVIEW HOUSE
This report is an update on the SmartWorking programme (funding for Stage 1 agreed by Cabinet on 14th July 2008), a request to draw down budget for the next stage of the programme as detailed in the report, as well as a request for additional funds required to meet the removal costs related to the decant of Riverview House.
CONTRIBUTORS Recommendations:
DENV That the review of the programme to date is DFCS noted. Programme Manager AD H&F Direct That the HR and IT policy related to AD HR SmartWorking is noted.
That the sum of £673,332 is drawn down from the total sum of £3.944m set aside for SmartWorking, from the Efficiency Projects Reserve. HAS A PEIA BEEN COMPLETED? That a further sum of £290,000 be approved YES regarding the office move from Riverview House (and consequential moves of Corporate Finance to the Town Hall and the IT Training suite to the Macbeth Centre) funded from the central contingency for office moves/dilapidations.
That a sum of £60,000 be approved to fund a replacement IT training suite in Macbeth St for use in staff training and by Adult Education funded from the central contingency for office moves/dilapidations That the sum of £159,000 is approved to fund the SmartWorking of H&F Homes staff currently in Riverview House, and the associated removal and infrastructure costs relating to their move to the Town Hall Extension.
That settlement of the dilapidations claim relating to the termination of the Riverview House lease is delegated to the Director of Environment and Director of Finance & Corporate Services.
That a report is presented to Cabinet in March 2010 summarising the outcomes achieved and with a further business case and plan for the remaining roll out to the rest of the council (Stage C). 1. EXECUTIVE SUMMARY
1.1This report is an update on the progress of the SmartWorking programme, and identifies the need to draw down funding of £1,182,332, as follows:
• £223,085 to SmartWork teams in Environment in order to make space to accommodate the emptying of Riverview House prior to its disposal in February 2010, • £81,000 to develop the approach and tools for further roll out of SmartWorking • £262,687 to pay for new IT and telephony required for this stage, • £106,560 to pay for annual support for new IT already developed and implemented to enable SmartWorking, • £290,000 to fund the various associated office moves needed in order to enable the decant and disposal of Riverview House, • £60,000 to finance the relocation of the IT Training unit to Macbeth Street which will also allow Adult Education access. • £60,000 to SmartWork teams in H&F Homes in Riverview House to ensure they will occupy a smaller office footprint before they move to the Town Hall Extension, • £99,000 for the associated removal and infrastructure costs relating to the H&F Homes move from Riverview House.
The report recommends that settlement of the dilapidations claim relating to the termination of the Riverview House lease is delegated to the Director of Environment and Director of Finance & Corporate Services. King Sturge have been appointed to undertake negotiations on behalf of the Council and funding for the dilapidations claim is contained within a central provision.
1.2Cabinet agreed funding of £1.529m for Stage 1 of the SmartWorking programme in July 2008, and the programme commenced in September 2008 and was expected to be of 12 – 18 months duration. This phase (which is seen as a foundation or enabling phase), is therefore still in progress and will complete in March 2010.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.