Item86
Resolved
This report recommends the following costs from the IT Enablers Fund: a) Implementing cloud-based collaboration tools using Office 365, at a tentative cost of £643,000 for Stages A, C and D, to be funded from the IT enablers budget; b) Delegate funding approval decision for the Phase 3 project implementation to the Cabinet Member for Finance for all Stages; and, c) Award of a contract for consultancy support by calling off from the CCS G-Cloud framework. 2. Separate papers will be brought forward for Stages B, E-H. Reason for decision: As set out in the report. Alternative options considered and rejected: As outlined in the report. Record of any conflict of interest: None. Note of dispensation in respect of any declared conflict of interest: None.
Word for word from the decision Hammersmith & Fulham published for this meeting.
Source: democracy.lbhf.gov.uk