Tfl Funded Annual Integrated Transport Investment Programme 2016/17

Approved Executive 3 papers

Cabinet approved this item on Monday 2 November 2015. Below is the council's own wording, with the papers it was decided on.

Item87

Resolved

That approval be given to carry out feasibility design and consultation on projects C1 to C3, N1 to N3 and L1 to L2 (identified in the body of the report) at a total cost of £90,000 (approximately 15% of the total capital project cost, and all charged to the capital project) as set out in paragraphs 5.3 and 5.4 (forms part of the £1,796,000). 2. That authority be delegated to the Cabinet Member for Environment, Transport and Residents Services in consultation with the Director of Transport and Highways to approve the implementation of projects C1 to C3, N1 to N3 and L1 to L2 (identified in the body of the report) totalling £510,000 (forms part of the £1,711,000), subject to favourable outcome of public engagement and consultation. 3. That approval be given to utilise £500,000 to implement a borough wide 20mph speed limit, subject to separate cabinet approval as set out in paragraph 5.2 (forms part of the £1,796,000). Should cabinet not separately approve implementation of a borough wide 20mph speed limit authority is given to delegate the reallocation of this £500,000 to Cabinet Member for Environment, Transport and Residents Services in consultation with the Director of Transport and Highways 4. That approval be given to utilise £25,000 to undertake the pedestrian crossing study and a further £25,000 to the Fulham Palace Road study as set out in paragraph 5.3 (forms part of the £1,711,000). 5. That approval be given to complete the 2015/16 integrated transport capital projects at a cost of £179,000 as set out in paragraph 5.3 (forms part of the £1,796,000). 6. That approval be given to utilise £50,000 to enhance the TfL traffic signal modernisation programme in 2016/17 and £50,000 to enhance the council’s own carriageway and footway planned maintenance programme in 2015/16 as set out in paragraph 5.5 (forms part of the £1,796,000) 7. That approval be given to deliver the Smarter Travel programme at a cost of £265,000, as detailed in paragraph 5.6 (forms part of the £1,796,000). 8. That approval be given to utilise £50,000 to develop the council’s 2017/18 annual spending submission (charged to revenue) and to utilise £75,000 to contribute match funding for the Mayor’s Air Quality Fund 2 as set out in paragraph 5.7 (forms part of the £1,796,000). 9. That authority be delegated to the Cabinet Member for Environment, Transport and Residents Services in consultation with the Director of Transport and Highways to approve the implementation of the Local Transport Fund programme of £100,000, as detailed in paragraph 5.8. 10. That approval be given to place all works orders with one of the council’s existing term or framework contractors; and in exceptional circumstances (where the council does not have the specific expertise) design work services through the London Borough of Ealing’s framework consultants contract with Project Centre Limited. Reason for decision: As set out in the report. Alternative options considered and rejected: As outlined in the report. Record of any conflict of interest: None. Note of dispensation ... view the full minutes text for item 87.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
LIP: Appendix 1Appendix 1 MB Copy on its way
PDF
LIP: Appendix 2Appendix 1 MB Copy on its way
PDF
Tfl Funded Annual Integrated Transport Investment Programme 2016/17Report 256 KB Copy on its way

At this meeting

Whole meeting

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies