London Borough of Hammersmith & Fulham
Cabinet, Monday 5 February 2018 at 7.00pm

Approval To Procure A Major Works Contractor To Develop Sands End Arts & Community Centre

Approved Executive 2 papers

Cabinet approved this item on Monday 5 February 2018. Below is the council's own wording, with the papers it was decided on.

Item125

Resolved

To approve the designs for the new Sands End Arts and Community Centre. 2. Authority to implement the Procurement Strategy (Appendix 1) for Phase 2 relating to the ‘Major Works Contractor’ which has an estimated value of £2.5m. 3. Delegate authority to the Lead Director for Regeneration, Planning & Housing Services in consultation with Cabinet Member for Economic Development and Regeneration to appoint the successful contractor.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1This report updates on the Council’s progress in implementing February 2017 Leader’s decision to procure a Design Team to develop plans at the former Sands End Community Centre.

1.2A Cabinet Member Decision Report (9th November 2017) was approved to progress the procurement of an Enabling Works Contractor to start on site in early 2018.

1.3Cabinet approved the creation of a ‘Community Trust’ to oversee the operations of the Sands End Arts and Community Centre (SEA & CC) on 4th December 2017.

1.4A planning application for the SEA & CC was approved by the Planning and Development Control Committee (PADCC) on 5th December 2017. 1.5. Officers now seek Cabinet approval to next stage of the programme which includes:  Approval to proceed with the proposed designs for the SEA & CC.  Procurement of a Main Works Contractor to develop the site.

Recommendations

2.1To approve the designs for the new Sands End Arts and Community Centre.

2.2Authority to implement the Procurement Strategy (Appendix 1) for Phase 2 relating to the ‘Major Works Contractor’ which has an estimated value of £2.5m.

2.3Delegate authority to the Lead Director for Regeneration, Planning & Housing Services in consultation with Cabinet Member for Economic Development and Regeneration to appoint the successful contractor.

Reasons for decision

3.1The Council has committed to redeveloping the Sands End Community Centre on the site of the existing Clancarty Lodge Depot in South Park, Fulham. The key aim is to deliver a sustainable community asset for local residents.

4. PROPOSAL AND ISSUES

4.1The new centre will provide a range of flexible new spaces for community use, changing rooms and WC’s, a café, and a nursery within a new single storey structure totalling 760sqm. The existing Clancarty Lodge will be refurbished and extended to provide community space for residents to use.

4.2Detailed planning permission has now been achieved for the scheme to redevelop the existing Clancarty Lodge and depot site.

4.3An Enabling Works Contractor will start on site early February 2018 to carry out all preparatory works by April 2018. There will be some selective demolition of existing structures, though Clancarty Lodge itself is to be retained and re-modelled as part of the new Centre.

4.4The procurement exercise can be run directly by Officers with support from Procurement Services using the CapitalESourcing procurement portal to manage the process.

4.5The tender returns will be a fixed sum and JCT Intermediate Building Contract with Contractor’s Design 2016 (ICD2016) contract will be entered in to.

4.6It is anticipated that the procurement process will require a 6 – 8-week tender period, which includes a Selection Questionnaire (SQ) process, followed by an Invitation to Tender (ITT). 5. OPTIONS AND ANALYSIS OF OPTIONS

5.1Option 1: Do nothing.

5.2Option 2: Run an open public procurement process and select a major works contractor.

5.3Option 3: Access existing Frameworks such as the London Construction Programme Framework or Southern Construction Framework and carry out mini-competitions.

5.4Officers recommend progressing Option 2 and further details of the options and recommendations are set out in Appendix 1 – Procurement Strategy.

Consultation

6.1Further details are set out in Appendix 1 – Procurement Strategy.

Equality implications

7.1There are no specific equalities implications concerning this report or the open procurement process recommended for approval in this report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement StrategyAppendix 1 464 KB Download
PDF
Approval To Procure A Major Works Contractor To Develop Sands End Arts & Community CentreReport 330 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 11 attended
AB
Councillor Andrew BrownOther Attendee, present
JC
Councillor Joe CarlebachOther Attendee, present
BC
Councillor Ben ColemanCommittee Member, present
SC
Councillor Stephen CowanChair, present
SF
Councillor Sue FennimoreCommittee Member, present
SH
Councillor Steve HamiltonOther Attendee, present
WH
Councillor Wesley HarcourtCommittee Member, present
LH
Councillor Lisa HomanCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, present
SM
Councillor Sue MacmillanCommittee Member, present
MS
Councillor Max SchmidCommittee Member, present

On this subject at Hammersmith & Fulham

Search all
  1. Approval To Procure A Major Works Contractor To Develop Sands End Arts & Community CentreThis decision
  2. Approval to procure a borough-wide Responsive Repairs contractor and terminate existing term-service contract for LOT 1 and LOT 2Noted
  3. Adoption Of A Free-Floating Car Sharing Service And Approval To Tender And Procure Provider(s) in LBHFAgreed
  4. Business Case & Procurement Strategy - Approval To Procure Contractor For Drainage And Landscape Work At Shepherds Bush GreenApproved

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies