To implement the pedestrian crossing phases at the Wandsworth Bridge Road/Carnwath Road/Townmead Road junction as described in Section 5 below. 2. To monitor the effects of the scheme when it is in place and work with TfL and the London Borough of Wandsworth to introduce measures which would mitigate any adverse effects. 3. To note that funding for the implementation of the proposal, at an estimated cost £140,000, is available from Section 106 money provided by Thames Tideway.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
1.1The Council has pursued the introduction of pedestrian crossing phases at the Carnwath Road/Wandsworth Bridge Road/Townmead Road junction for many years. Transport for London, who control all traffic signals in London, have previously refused to do so because of the additional delays this would cause to motor traffic
1.2However, with the advent of the Thames Tideway Tunnel construction site on Carnwath Road, there would be a significant increase in the number of HGV movements in the area and Tideway agreed to fund further studies and the provision of a crossing should a design be produced which is acceptable to TfL.
1.3The Council undertook consultation on a scheme which was acceptable to TfL in October-November 2017 and 92% of respondents were in favour of the proposal. 2. RECOMMENDATIONS
2.1To implement the pedestrian crossing phases at the Wandsworth Bridge Road/Carnwath Road/Townmead Road junction as described in Section 5 below.
2.2To monitor the effects of the scheme when it is in place and work with TfL and the London Borough of Wandsworth to introduce measures which would mitigate any adverse effects
2.3To note that funding for the implementation of the proposal, at an estimated cost £140,000, is available from Section 106 money provided by Thames Tideway.
Reasons for decision
3.2Transport for London (TfL) have in the past refused permission for the provision of such crossings because of predicted additional delays to motor traffic. Because of the additional movement of Heavy Goods Vehicle traffic in the area associated with the Thames Tideway construction site on Carnwath Road, TfL have now agreed a design for the crossings. We have undertaken consultation with local residents and stakeholders and received 240 responses, 92% of which were in favour of the scheme. However, some concerns were expressed about the effect on traffic flow and these issues will need to be addressed.
4. INTRODUCTION AND BACKGROUND
4.1The lack of pedestrian crossings at the Wandsworth Bridge Road/Carnwath Road/Townmead Road junction has been a cause of community severance for many years, with some pedestrians crossing the road at risk as motor traffic always has a green light from at least one direction. The council has approached TfL at various times with a view to providing such crossings, e.g. as part of the London Cycle Network, but Wandsworth Bridge is a very important strategic road and one of a limited number of river crossings in south west London. Modelling showed that pedestrian phases would cause substantial additional congestion and traffic queuing, and therefore TfL declined such provision.
4.2In September 2014, Thames Tideway was granted consent by order of parliament to use a construction site in Carnwath Road. This would generate a significant number of Heavy Goods Vehicle movements through the junction, adding to the danger to pedestrians there. The Council has received some £750,000 in Section 106 money to mitigate these effects
5. PROPOSALS AND ISSUES
5.1The Council therefore commissioned further modelling on pedestrian phases early in 2016 and a scheme has been proposed which TfL have now accepted. The adverse traffic effects are still predicted, but the need to mitigate the effects of Tideway on the community has taken precedence.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.