That Cabinet: 1 Resolves that the areas of land at the Civic Campus referred to in this report and shown edged red on the plans at Appendix 1 are no longer required for the mixed commercial and civic purposes for which they are currently held. 2 Approves the appropriation of the areas of land edged red on the plans at Appendix 1 pursuant to section 122 of the Local Government Act 1972 for the planning purposes of facilitating redevelopment for residential and other uses pursuant to section 226 of the Town and Country Planning Act 1990 3 Approves the use of powers to override easements and other rights in respect of the land pursuant to section 203 of the Housing and Planning Act 2016.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
In order for the redevelopment of the Civic Campus to proceed it is necessary to appropriate the site for Planning purposes. This will allow the Council to utilise powers to override third party rights that may prevent the implementation of the proposed development.
The civic campus programme will bring significant benefits to the local economy, including 204 new homes, of which half will be affordable, new offices for the Council and a cinema, retail, restaurant and affordable workspace.
Recommendations
It is recommended that Cabinet:
1 Resolves that the areas of land at the Civic Campus referred to in this report and shown edged red on the plans at Appendix 1 are no longer required for the mixed commercial and civic purposes for which they are currently held.
2 Approves the appropriation of the areas of land edged red on the plans at Appendix 1 pursuant to section 122 of the Local Government Act 1972 for the planning purposes of facilitating redevelopment for residential and other uses pursuant to section 226 of the Town and Country Planning Act 1990
3 Approves the use of powers to override easements and other rights in respect of the land pursuant to section 203 of the Housing and Planning Act 2016.
Our Priorities Summary of how this report aligns to the H&F Priorities Building shared prosperity The programme represents a significant opportunity for the Council to improve the use of its public assets, drive efficiency of operation and enhancement to public services whilst simultaneously creating social and economic value through development of a new cinema and much needed affordable housing. Creating a compassionate The programme will further the Council’s council ability to provide compassionate, high- quality services that residents can rely on. Doing things with local Through the bottom up approach taken at residents, not to them numerous public consultations and feedback sessions, as well as, the co-production of design with the Disabled People’s Commission. Being ruthlessly financially The investment in the programme will efficient generate a significant return, both financially and socially for local residents.
Financial Impact
The Financial Impact of the wider Civic Campus scheme have been set out in various decision reports, this report focuses on the need to appropriate the land to enable the scheme to progress and the Financial Impact is limited to the recommendations in this report.
The appropriation of land for planning purposes does not involve any significant external cost, with costs relating to officer time relating to the decision.
As set out in the report, beneficiaries of right to light that are interfered with as a result of the carrying out of the development will be entitled to compensation which will be calculated on the basis of the diminution in value of their land. The conditional agreement for lease includes an indemnity in respect of these costs and to ensure that any costs arising are picked up by the developer rather than the council.
Legal implications
The legal powers available to the Council to appropriate land and override third party rights are identified and explained in this report. Cabinet approved a report in March 2018 which set out the six considerations for using these legal powers. These considerations have been complied with as set out elsewhere in this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.