London Borough of Hammersmith & Fulham
Cabinet, Monday 6 July 2020 at 6.30pm

Civic Campus - Award of Contract for the Refurbishment and Fit-Out of the Town Hall

Agreed Executive 1 paper

Cabinet agreed this item on Monday 6 July 2020. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

AGREED UNANIMOUSLY BY CABINET: 1. To approve that Appendix 1 be exempt from disclosure on the ground it contains information relating to the financial or business affairs of a particular person (including the authority holding that information) under paragraph 3 of Schedule 12A of the Local Government Act 1972, and in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information. 2. That Cabinet approves £860,841 additional capital budget for the fit out of the Town Hall (including the extension) which reflects an equivalent revenue saving within the approved project budget and is in line with the Council’s strategy to protect reserves. 3. That the Council enters into a contract with Ardmore Construction Limited for the refurbishment of the existing Grade 2 Listed Building plus the fit out of the Town Hall (including Cat B fit out of the glass box vertical extension) and that the contract value shall not exceed the approved capital budget. 4. To delegate authority to the Strategic Director for the Economy, in consultation with the Head of Law, Director for Finance and the Cabinet Member for the Economy to finalise and complete negotiations with Ardmore Construction Limited to give effect to the decision in 3. 5. That authority be delegated to the Strategic Director for the Economy, in consultation with the Director of Finance, the Cabinet Member for the Economy and the Cabinet Member for Finance and Commercial Services, to agree an additional 5% variation of the approved capital budget to accommodate any potential increase in contract costs or approved specification changes following approval of this report, to be funded from borrowing.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

The Civic Campus Programme is an ambitious regeneration programme to transform the Council’s civic and democratic centre. It will act as a catalyst for change in the borough, replacing the life-expired Town Hall Extension building, and uninviting and poorly utilised surrounding spaces, with a state of the art public realm space, fully refurbished and inclusively designed town hall building, and vibrant mixed use neighbourhood designed to serve the community.

Planning consent for the project has been achieved and subsequent detailed design development concluded. The delivery structure for the project includes a 50:50 Joint Venture (JV) between A2Dominion and the LBHF, which will enter into a construction contact for the wider campus improvements and delivery of the Town Hall vertical extension. The Council will also enter into a separate construction contract for the refurbishment and fit out of the Town Hall.

Both contracts have been tendered together as one package to ensure consistency and efficiency across the site is maximised and enable effective site logistics required to meet the required programme – while the separate contract ensures the Council retains more control over the delivery of the Town Hall refurbishment as part of the programme. Following a procurement exercise, a preferred contractor was selected and a Pre-Construction Services Agreement (PCSA) was signed to provide pre-construction services to progress design, cost and delivery aspects of the project. This period is nearing completion and this report seeks approval for a change in the funding strategy and the Council to enter into a Construction Contract with Ardmore Construction Limited for the refurbishment and fit out works to the Town Hall. Approval will ensure the programme is maintained for a Spring 2022 opening of the Town Hall. Recommendations

1. To approve that Appendix 1 be exempt from disclosure on the ground it contains information relating to the financial or business affairs of a particular person (including the authority holding that information) under paragraph 3 of Schedule 12A of the Local Government Act 1972, and in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information.

2. That Cabinet approves £860,841 additional capital budget for the fit out of the Town Hall (including the extension) which reflects an equivalent revenue saving within the approved project budget and is in line with the Council’s strategy to protect reserves.

3. That the Council enters into a contract with Ardmore Construction Limited for the refurbishment of the existing Grade 2 Listed Building plus the fit out of the Town Hall (including Cat B fit out of the glass box vertical extension) and that the contract value shall not exceed the approved capital budget.

4. To delegate authority to the Strategic Director for the Economy, in consultation with the Head of Law, Director for Finance and the Cabinet Member for the Economy to finalise and complete negotiations with Ardmore Construction Limited to give effect to the decision in 3.

5. That authority be delegated to the Strategic Director for the Economy, in consultation with the Director of Finance, the Cabinet Member for the Economy and the Cabinet Member for Finance and Commercial Services, to agree an additional 5% variation of the approved capital budget to accommodate any potential increase in contract costs or approved specification changes following approval of this report, to be funded from borrowing.

Wards Affected: Hammersmith Broadway

H&F Priorities

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Civic Campus: Award of Contract for the Refurbishment and Fit-Out of the Town HallReport 324 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
SC
Councillor Stephen CowanChair, present
SF
Councillor Sue FennimoreCommittee Member, present
BC
Councillor Ben ColemanCommittee Member, present
AC
Councillor Adam ConnellCommittee Member, present
LC
Councillor Larry CulhaneCommittee Member, present
WH
Councillor Wesley HarcourtCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, present
LH
Councillor Lisa HomanCommittee Member, present
SM
Councillor Sue MacmillanCommittee Member, present
MS
Councillor Max SchmidCommittee Member, present

On this subject at Hammersmith & Fulham

Search all
  1. Civic Campus - Award of Contract for the Refurbishment and Fit-Out of the Town HallThis decision
  2. Civic Campus - Strategic OptionsAgreed
  3. Civic Campus - Strategic OptionsAgreed
  4. Civic Campus Enhanced InvestmentApproved
  5. Civic Campus programme - Land AppropriationApproved
  6. Town Hall Civic Campus Programme: Approval to Purchase Commercial Units and Joint Venture UpdateApproved

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies