AGREED UNANIMOUSLY BY CABINET: That Cabinet approves an additional budget of £526,000 for the Watermeadow Court development project to cover the unforeseen costs set out in paragraphs 11,12 and 13 of the report to be funded from capital receipts.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
The report requests approval for additional budget of £526,000 for the Watermeadow Court (WMC) development project. Additional budget is required for two reasons:
1. To cover additional security costs, contract inflation, clearance and staffing costs incurred due to the delay to start of demolition. Demolition of the buildings on the site could not happen until the Greater London Authority (GLA) had given planning approval for the scheme and this was significantly delayed.
2. In October 2019, the council’s JV partner for the development, Stanhope, advised it could not meet its contractual obligation to secure funding for the project. The council cannot now hand over the site to the JV following demolition of the buildings (which concluded on 25 November 2019) and needs to secure and manage the site against illegal occupation until the site can be brought forward for development under an alternative strategy.
Recommendations
That Cabinet approves an additional budget of £526,000 for the Watermeadow Court development project to cover the unforeseen costs set out in paragraphs 11,12 and 13 of the report to be funded from capital receipts.
Wards Affected: Sands End H&F Priorities
Please state how the outcome will contribute to our priorities
Our Priorities Summary of how this report aligns to the H&F Priorities Being ruthlessly financially This report seeks to fulfil the council efficient obligations to the contractor by closing out the final account and paying for services provided.
The costs for the site security has been benchmarked and market tested though the use of obtaining more than 1 quote. The contract is agreed to allow for a full procurement exercise to be undertaken in 4 months if a permanent JV partner or solution for the site is appointed / made.
Financial Impact
1. This project is part of the Housing Capital Programme and has an overall approved budget of £1,458,000. The final required spend in order to cover additional costs and develop an alternative delivery strategy is expected to be up to £1,983,904, based on sections 10 to 13 of the Detailed Analysis, is split as follows: Current Forecasted Additional Approved Final budget Type of Cost Supplier Budget Project Cost required Reason for additional budget required Demolition Consultancy Lambert Smith Costs already incurred relating to LSH Hampton Group Ltd 58,000 61,565 3,565 delayed start on site - para .10. Coleman & Demolition Cost Company Ltd 1,329,000 1,505,513 176,513 Legal, Procurement Legal, & Professional Professional Advice 100,000 100,000 Alternative delivery strategy - para .11. Contingency & Salary Not Applicable 71,000 125,007 54,007 Para .13 First Response Post Completion Security Provision - Security Costs Group & TBC 191,819 191,819 para .11
Total 1,458,000 1,983,904 525,904
526,000 Rounded off budget requirement
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.