AGREED UNANIMOUSLY BY CABINET: That Cabinet: 1. Notes that Appendix A and B are not for publication on the basis that they contain information relating to the financial or business affairs of any particular person (including the authority holding that information) as set out in paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended). 2. Approves the termination of the WMC Land Sale Agreement and delegates authority to the Strategic Director for the Economy, in consultation with the Borough Solicitor, to agree the final form of the legal document(s) of a “Deed of Variation” required for the termination and to enter into it; 3. Approves the payment of £3,491,066 ( to be funded from a new general fund capital budget financed by an increase in the Council’s Capital Financing Requirement) to the HFS Developments 2 Ltd (being the joint venture company established pursuant to the Joint Venture Agreement) to terminate the WMC Land Sale Agreement in line with the payment structure as set out in the detailed analysis section 1 5 below ; and 4. Approves to vary the ESH Land Sale Agreement to extend the conditional period to 14 June 2021 by way of a deed of variation and enter into it.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
Watermeadow Court (“WMC”) is one of two development sites under a joint venture agreement (the “Joint Venture Agreement”) between London Borough of Hammersmith and Fulham (“the Council”) and Stanhope Plc (“Stanhope”). The site was granted planning permission, issued on 3rd October 2019 for 36 affordable homes and 182 market homes.
Following the grant of the planning permission in October 2019 Stanhope advised the Council that they were unable to meet the contractual funding condition in the land sale agreement required to deliver the WMC development scheme (“the WMC Land Sale Agreement”). It is therefore proposed to terminate the WMC Land Sale Agreement and this will enable the Council to pursue alternative development arrangements. The contractual cost of termination to the council has been negotiated down from £5.05m to £3.49m.
The other development site included within the Joint Venture Agreement, the Edith Summerskill House site (“ESH”) was also granted planning at the same time, but there has been a delay progressing this project following an application for judicial review. This required the planning permission to be quashed and a new application submitted. A new planning application is expected to be submitted in April 2020, however the Conditional Period of this project included in the land sale agreement for ESH (“the ESH Land Sale Agreement”) must be extended to allow for a new planning permission. In the event that a new planning permission is granted the site will be transferred to Peabody Housing Trust and is expected to will deliver 133 affordable homes.
This report sets out and seeks approval for: (a) termination of the WMC Land Sale Agreement, so the Council can develop WMC independently and not pursuant to the Joint Venture Agreement; (b) budget for the expenditure to be incurred by the Council in terminating the WMC Land Sale Agreement; and (c) a variation of the ESH Land Sale Agreement to extend the conditional period permitted by the ESH Land Sale Agreement and allow design and planning works to continue under the Joint Venture Agreement. Recommendations
That Cabinet:
1. Notes that Appendix A and B are not for publication on the basis that they contain information relating to the financial or business affairs of any particular person (including the authority holding that information) as set out in paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended).
2. Approves the termination of the WMC Land Sale Agreement and delegates authority to the Strategic Director for the Economy, in consultation with the Borough Solicitor, to agree the final form of the legal document(s) of a “Deed of Variation” required for the termination and to enter into it;
3. Approves the payment of £3,491,066 (to be funded from a new general fund capital budget financed by an increase in the Council’s Capital Financing Requirement) to the HFS Developments 2 Ltd (being the joint venture company established pursuant to the Joint Venture Agreement) to terminate the WMC Land Sale Agreement in line with the payment structure as set out in the detailed analysis section 15 below; and
4. Approves to vary the ESH Land Sale Agreement to extend the conditional period to 14 June 2021 by way of a deed of variation and enter into it;
Wards Affected: Sands End
H&F Priorities
Please state how the outcome will contribute to our priorities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.