West London Economic Prosperity Board noted this item on Wednesday 17 February 2021. Below is the council's own wording, with the papers it was decided on.
RESOLVED 1. The Board noted the progress in development of the business case for the WLO. 2. The Board agreed the proposed arrangements for funding the project from Strategic Investment Pot resources held by the West London Alliance. 3. The Board agreed the arrangements for governance of the project, including establishment of a Partners Oversight Group.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
17th February 2021 Title West London Orbital (Standing Item)
Report of Niall Bolger, LB Hounslow
Status Public
Urgent No
Enclosures N/A Andrew Barry-Purssell, West London Planning Policy and Officer Contact Details Infrastructure Delivery Manager, West London Alliance, E: [email protected]; T: [phone removed]
Summary This report provides the Board with an update on work with Transport for London and Network Rail to develop the business case for the West London Orbital. It seeks approval for proposed arrangements for providing funding for the project from the resources secured from the Strategic Investment Pot and for governance arrangements reflecting the fact that the project is being jointly funded and delivered.
Recommendations Leaders are asked to:
i) NOTE progress in development of the business case for the WLO; ii) AGREE the proposed arrangements for funding the project from Strategic Investment Pot resources held by the West London Alliance; and iii) AGREE the arrangements for governance of the project, including establishment of a Partners Oversight Group 1. WHY THIS REPORT IS NEEDED
1.1The WLEPB has consistently identified the West London Orbital (WLO) Overground rail line as a shared strategic priority for West London, integral to the sub-region’s sustainable development. The Board has agreed that progress and next steps relating to the WLO should be a standing item on its agenda. The West London Alliance (WLA) and West London boroughs have worked closely with Transport for London (TfL) and the Greater London Authority and Network Rail to develop and refine the business case for the project. The WLA has secured funding to contribute to the costs of the work, most recently £3.6 million from the retained business rates-based Strategic Investment Pot. TfL’s current budgetary position has made the availability of this funding essential to work on the project proceeding. This has in turn highlighted the joint nature of the project and the need for robust governance arrangements to ensure it proceeds effectively, transparently and accountably and ensures best value in the use of public resources. This report takes stock of progress to date and proposes funding and governance arrangements to enable the project to move through its next stages.
2. DEVELOPMENT OF THE WLO BUSINESS CASE
2.1It will be recalled that the Strategic Outline Business Case for the WLO, published in June 2019, recommended that work on the project should move forward. This started in the autumn of 2019.
2.2Progress has been affected by the Covid-19 pandemic and, in particular, the impacts this has had on TfL’s financial position. TfL had to adopt an emergency budget in June 2020 to deal with the immediate consequences, including funding from central Government; work on the WLO continued. At its Board Meeting on 29th July 2020, TfL adopted a revised budget for 2020-2022 which included projects which are in line with Government objectives and those of the Mayor’s Transport Strategy, including longer-term projects with strong business cases – including the WLO. Other projects have been paused or dropped. However, continued delivery is subject to discussions with Government about what will be affordable over the next decade. TfL is clear that they cannot currently afford to progress them all.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow West London Economic Prosperity Board at Hammersmith & Fulham and we tell you when its next papers are published, before the meeting rather than after it.
West London Innovation District ConceptRESOLVED 1. The Board noted the mapping work undertaken to better understand the innovation landscape across West Lon...
West London Orbital (standing item)RESOLVED 1. The Board noted progress in development of the business case for the WLO. 2. The Board noted the proposed...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.