To approve the four-year General Fund Capital Programme budget at £123.6m for the period 2023/24-2026/27 (presented in Table 2 and Appendix 1). 2. To approve the continuation of rolling programmes for 2023/24 funded from the Council’s mainstream resources. For financial modelling purposes, these programmes are assumed to continue at the same level until 2026/27: £m Corporate Planned Maintenance 2.400 Footways and Carriageways 2.030 Column Replacement 0.346 Total 4.776 3. To delegate approval of the detailed programmes for use of the rolling programmes, in recommendation 2, to the relevant SLT Director in consultation with the Director of Finance and relevant Lead Cabinet Member. 4. To approve the four-year Housing (HRA) Capital Programme at £383.2m for the period 2023/24-2026/27 as set out in Table 5 and Appendix 1. 5. To delegate authority to the Director of Finance in consultation with the Cabinet Member for Finance and Commercial Services to approve the potential use of up to £4.3m of capital receipts under the Government’s Flexible Use of Capital Receipts provisions for funding of Invest to Save schemes in 2023/24 and 2024/25 (as identified in Appendix 4) and potential match-funding opportunities. 6. To approve the Capital Strategy 2023/24, as set out in Appendix 3. 7. To approve the annual Minimum Revenue Provision policy statement for 2023/24, as set out in Appendix 5. 8. To note the existing mainstream funded schemes previously approved, but now reprofiled to 2023/24 and future years as detailed in Table 3.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
This report presents the Council’s four-year Capital Programme for the period 2023 to 2027.
The council is investing £506.8m over the next four financial years to develop and enhance its assets (including council housing), to meet its strategic objectives and provide better outcomes for its residents, businesses, and visitors. Key schemes within the programme include:
Significant investment in the major repairs and health and safety compliance of the council’s 12,000 dwellings Investment in housing development schemes to provide additional affordable accommodation across the borough Public CCTV equipment purchases and installation Financing facility towards Education City development School maintenance programme Investment in energy efficient lighting and decarbonisation schemes. Hammersmith Bridge pre-restoration works Civic Campus programme/ refurbishment of Hammersmith Town Hall Investment in the council’s public realm including column replacement, footways, and carriageways
The council is required by the CIPFA Prudential Code for Capital Finance (2017) and statutory guidance to prepare certain capital related strategies and policies. The Capital Strategy and Minimum Revenue Provision (MRP) Policy are included as appendices to this report. The Treasury Management Strategy Statement 2023/24 will also be presented to Cabinet in February 2023 under a separate agenda item.
In accordance with the requirements of the Prudential Code for Capital Finance, local authorities are required to maintain a number of prudential indicators. These are set out in the Treasury Management Strategy Statement 2023/24. The indicator used to reflect the underlying need of an authority to borrow for a capital purpose is the Capital Financing Requirement (CFR) which is set out within this report.
Page 1 RECOMMENDATIONS
1. To approve the four-year General Fund Capital Programme budget at £123.6m for the period 2023/24-2026/27 (presented in Table 2 and Appendix 1).
2. To approve the continuation of rolling programmes for 2023/24 funded from the Council’s mainstream resources. For financial modelling purposes, these programmes are assumed to continue at the same level until 2026/27:
£m Corporate Planned Maintenance 2.400 Footways and Carriageways 2.030 Column Replacement 0.346 Total 4.776
3. To delegate approval of the detailed programmes for use of the rolling programmes, in recommendation 2, to the relevant SLT Director in consultation with the Director of Finance and relevant Lead Cabinet Member.
4. To approve the four-year Housing (HRA) Capital Programme at £383.2m for the period 2023/24-2026/27 as set out in Table 5 and Appendix 1.
5. To delegate authority to the Director of Finance in consultation with the Cabinet Member for Finance and Commercial Services to approve the potential use of up to £4.3m of capital receipts under the Government’s Flexible Use of Capital Receipts provisions for funding of Invest to Save schemes in 2023/24 and 2024/25 (as identified in Appendix 4) and potential match-funding opportunities.
6. To approve the Capital Strategy 2023/24, as set out in Appendix 3.
7. To approve the annual Minimum Revenue Provision policy statement for 2023/24, as set out in Appendix 5.
8. To note the existing mainstream funded schemes previously approved, but now reprofiled to 2023/24 and future years as detailed in Table 3.
Wards Affected: All
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.