Future Resident Facing Energy Proposals

Approved Executive 5 papers

AI summaryH&F Cabinet approves 'Healthy Homes' retrofit service for residents, with two neighbourhood pilots in social housing at Wormholt and private homes at Wendell Park, expected to cost the council nothing.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedNew retrofit support with two neighbourhood decarbonisation pilots
MoneyNo cost to Council expectedFunded from Carbon Offset Fund and recharges to users
What happens nextThree procurements to followTechnical, engagement and communications partners to be tendered
Who it affectsAll H&F wards and residentsPilots in Wormholt, College Park and Old Oak, and Wendell Park

What was decided

Approved a new H&F 'Healthy Homes' service to help residents design and install insulation, solar PV, heat pumps and energy storage, linked to a proposed small grant scheme administered by H&F for less well-off residents. Report P5

Approved the selection of H&F social housing in parts of Wormholt and College Park and Old Oak wards as a social housing place-based decarbonisation scheme, including solar energy, batteries, heat pumps, insulation and innovative energy tariffs. Report P6

Approved Wendell Park as a private housing place-based decarbonisation scheme, with intensive engagement, thermal drone scans and possible work with an engagement partner under the European Horizon 2020 programme. Report P7

Why

Buildings account for over 80% of H&F's carbon emissions and council social housing is only 11% of borough emissions, so the council must work with private residents to reach its 2030 net zero target. Report P3, P14, P19, P30

Residents face financial, technical and social barriers to retrofit, including upfront cost, difficulty finding trusted installers, confusing funding options, and low awareness of technologies such as heat pumps. Report P41, P42, P43

A place-based approach allows tailored engagement where housing types are similar, supports neighbour to neighbour modelling, and lets the council test the impact of hyper-localised engagement strategies. Report P59, P60, P61

What happens next

Three procurement exercises will be run: a technical partner for energy surveys, an engagement partner, and a communications partner, with tender notices published on the Find a Tender Service under the Procurement Act 2023. Report P17, P23

Rollout and promotion of the retrofit advice service, SHF funded clean energy measures in Wormholt and College Park and Old Oak, hyper-localised engagement in Wendell Park, an H&F microsite, and a grant scheme for residents installing clean energy measures. Report P75

Continue work on clean heat network feasibility studies around Bayonne, Margravine and White City estates, social housing retrofit, energy flex tariffs, and supporting HFCE to install solar PV on council rooftops. Report P76, P77

Options considered

  • Rejected: Do nothing. Ignores the vital role the council can play in encouraging and supporting clean energy and energy efficiency in private housing Report P66
  • Rejected: H&F advice, comms and signposting to existing London and national handholding services. Does not assess provider quality and is likely to lead to confusion and choice paralysis for residents Report P67
  • Chosen: Partner with an expert retrofit support service provider, cobranded or white-labelled for H&F residents. Provides the simplest and most accessible service for residents, with a single trusted provider offering end to end support under PAS 2035 Report P68, P79

Implications

  • Climate: Strategy is a cornerstone of the council's delivery on its 2030 net zero target and supports the Climate and Ecology Strategy objective on comfortably and affordably heated, zero carbon homes. Report P14, P26
  • Financial: Engagement and communications contracts to be funded from the Carbon Offset Fund, and technical partner costs recharged to service users, with a possible small council contribution also from the Carbon Offset Fund. Report P17
  • Legal: Procurement must comply with the Procurement Act 2023 and the council's Contract Standing Orders, with tender notices on the Find a Tender Service via CapitalESourcing. Report P20, P23
  • Risk: Risks in branding a retrofit service and standing behind a network of installers to be mitigated through a competitive procurement process. Report P20
  • Equalities: Reducing fuel poverty and energy bills, and improving insulation, is expected to have positive impacts in particular on older people, very young children, and disabled people. Report P11
  • Staffing: Service aims to encourage new entrants to the retrofit workforce and incentivise the existing workforce to retrain, supporting the borough's industrial strategy and skills pipeline. Report P10, P49

Who and where

  • All H&F wards and residents across the borough Report P9
  • Tenants in H&F social housing in parts of Wormholt and College Park and Old Oak wards Report P6, P32
  • Around 300 mostly owner-occupied homes in Wendell Park Report P32
  • Less well-off residents who may receive a small council funded grant for clean energy measures Report P5, P35
  • Households in fuel poverty who will continue to be supported through existing services Report P2, P8

Timeline

  • 2019: H&F declared a climate emergency and set a 2030 net zero ambition Report P30
  • 2021: Council published its Climate and Ecology Strategy Report P31
  • 2023: Council approved its Fuel Poverty Strategy Report P31
  • 2025: Council approved its Council Housing Retrofit Strategy Report P31
  • 2030: Council's target for net zero carbon emissions Report P14
  • 2050: UK legal target for net zero under the Climate Change Act 2008 Report P19
  • 2026-01-19: Cabinet decision to approve the Healthy Homes service and two pilot areas

Plain English for the jargon

  • H&F: Hammersmith and Fulham, the London Borough council taking the decision
  • Healthy Homes: Proposed H&F umbrella programme covering fuel poverty, able to pay retrofit and council housing retrofit support
  • Retrofit: Upgrading existing homes with energy efficiency or clean energy measures such as insulation, solar PV, heat pumps and batteries
  • Solar PV: Solar photovoltaic panels that generate electricity from sunlight
  • Heat pump: Low carbon heating system that transfers heat from outside a building to inside
  • Net zero: No net greenhouse gas emissions, achieved by reducing emissions and balancing any remaining emissions through removals
  • Place-based decarbonisation: Approach to cutting carbon emissions that targets a defined neighbourhood rather than the whole borough at once
  • HFCE: Hammersmith and Fulham Community Energy, a local green energy co-op
  • PAS 2035: British Standard covering the management of energy retrofit of domestic buildings, required for the recommended partner service
  • Carbon Offset Fund: Developer funding used by H&F to offset carbon impacts, expected to fund the engagement, communications and any small grant elements
  • Warm Homes Social Housing Fund: Government funding stream being used to retrofit 516 H&F street properties
  • Heat network: System that distributes heat from a central source to multiple buildings through underground pipes
  • Heat Network Zoning: Proposed UK legislation framework for designating areas that must connect to a heat network
  • GLA: Greater London Authority, the regional body launching the related Warmer Homes London scheme
  • DESNZ: Department for Energy Security and Net Zero, a UK government department
  • Horizon 2020: European Union research and innovation programme that has expressed interest in H&F's hyper-localised engagement approach
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

To approve a new H&F service, as part of the H&F ‘Healthy Homes’ programme, to help residents design and install measures including insulation, solar PV, heat pumps and energy storage to their homes. A proposed small grant scheme, administered by H&F, is linked to this to help less well-off residents to pay for measures. To approve the selection of the portion of Wormholt and College Park & Old Oak wards that is H&F social housing as a social housing place-based decarbonisation scheme, including solar energy, batteries, heat pumps, insulation and innovative money saving energy tariffs. To approve the selection of Wendell Park as a private housing place-based decarbonisation scheme, using intensive, targeted communications and engagement, alongside innovative measures such as thermal drone scans, to drive clean energy measures in the neighbourhood. The European Horizon 2020 programme, which covers leading innovative climate initiatives, has shown an interest in this. H&F proposes to work with an engagement partner who will support on research, development, implementation and measurement of this hyper-localised approach to engagement. To note the other schemes already underway and expanding, including the HFCE green energy co-op, feasibility studies for large scale clean energy networks, support for residents in fuel poverty, and social housing retrofit projects in the West Kensington and White City estates among others.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

This report covers a package of programmes aimed at streamlining access to clean energy opportunities and technologies for H&F residents. At the heart of these is a proposed new ‘Healthy Homes’ service to guide residents through the design, funding and implementation of housing retrofit projects. While this service will be borough wide, two proposed Healthy Homes pilot areas will receive intensive hyper- localised community engagement to further drive and scale clean energy and sustainability measures. One of these is based around social housing and one around private housing. These proposals build on work underway in H&F to:

 work with the HFCE green energy co-op to install solar PV on selected H&F schools, enabling residents to invest in solar energy in the borough  trial innovative green energy flex tariffs in social housing units  support fuel poor residents to save energy and access government grants  design clean heat networks for larger H&F Housing estates  commission the innovative new clean energy network on the Civic Campus.

They form a vital part of the trajectory towards net zero with buildings accounting for over 80% of the carbon emissions in H&F, and will help residents affordably heat their homes, bring investment into the borough and improve air quality.

This strategy is a key component of the council’s Climate and Ecology Strategy, supports the council’s Industrial Strategy, and integrates with proposed new powers for local governments to procure and build clean energy infrastructure via Heat Network Zoning legislation. It also links to the H&F Council Housing Retrofit Strategy and the H&F Fuel Poverty Strategy.

Recommendations

1. To approve a new H&F service, as part of the H&F ‘Healthy Homes’ programme, to help residents design and install measures including insulation, solar PV, heat pumps and energy storage to their homes. A proposed small grant scheme, administered by H&F, is linked to this to help less well-off residents to pay for measures.

2. To approve the selection of the portion of Wormholt and College Park & Old Oak wards that is H&F social housing as a social housing place-based decarbonisation scheme, including solar energy, batteries, heat pumps, insulation and innovative money saving energy tariffs.

3. To approve the selection of Wendell Park as a private housing place-based decarbonisation scheme, using intensive, targeted communications and engagement, alongside innovative measures such as thermal drone scans, to drive clean energy measures in the neighbourhood. The European Horizon 2020 programme, which covers leading innovative climate initiatives, has shown an interest in this. H&F proposes to work with an engagement partner who will support on research, development, implementation and measurement of this hyper-localised approach to engagement.

4. To note the other schemes already underway and expanding, including the HFCE green energy co-op, feasibility studies for large scale clean energy networks, support for residents in fuel poverty, and social housing retrofit projects in the West Kensington and White City estates among others.

Wards Affected: All

Our Values Summary of how this report aligns to the H&F Values Building shared Retrofit is a green industrial sector which has been limited by prosperity stop-start subsidies in the past. Supporting residents will help build a pipeline of projects to support suppliers to invest in skills. Heat networks, low-carbon and renewable sectors are high- growth areas worked on by the borough’s anchor institutions and start-ups, and the retrofit strategy supports our industrial strategy by advancing collaborations with these organisations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract and KPIs for H&F fuel poverty serviceAppendix 1 493 KB Download
PDF
Draft scope of work for retrofit support serviceAppendix 2 412 KB Download
PDF
H&F Council Housing Retrofit StrategyAppendix 3 1.7 MB Download
PDF
Summary presentation of proposalsAppendix 4 2 MB Download
PDF
Future Resident Facing Energy ProposalsReport 273 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
SC
Councillor Stephen CowanChair, present
AS
Councillor Alex SandersonCommittee Member, present
FC
Councillor Florian Chevoppe-VerdierCommittee Member, present
WH
Councillor Wesley HarcourtCommittee Member, present
RH
Councillor Rebecca HarveyCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, apologies
BK
Councillor Bora KwonCommittee Member, present
ZQ
Councillor Zarar QayyumCommittee Member, present
RR
Councillor Rowan ReeCommittee Member, present
FU
Councillor Frances UmehCommittee Member, present

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies