Cabinet, Monday 19 January 2026 at 7.00pm

Procurement Strategy for Edward Woods Towers External Facade and Window Replacement Works

Noted Executive 2 papers

AI summaryCabinet approved a procurement strategy for fire safety and façade works at three 24-storey Edward Woods estate towers in W11, using the Pretium Building and Fire Safety Framework. Contract value is in a withheld appendix.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedMini-competition via Pretium Framework, Lot 8
MoneyValue in exempt Appendix 1Costs expected from HRA borrowing; recharges to leaseholders
What happens nextMini-competition to publish 23 February 2026PCSA award expected September 2026, works from September 2027
Who it affectsEdward Woods estate, Shepherds Bush Green ward. 540 homes across three towers, 79 leaseholders

What was decided

Cabinet approved a mini-competition under the Pretium Building and Fire Safety Framework (Lot 8) to source a contractor for external façade safety works at Norland House, Stebbing House and Poynter House, Edward Woods estate, W11. Report P6

Cabinet noted the procurement will be a two-stage design and build process, with a Pre-Construction Services Agreement (PCSA) with a preferred supplier, followed by a separate works contract. Report P7

Cabinet noted that Exempt Appendix 1, containing the estimated contract value, is not for publication under paragraph 3 of Schedule 12A of the Local Government Act 1972. Report P5

Why

Post-Grenfell inspections found fire safety concerns including missing cavity barriers, delaminated cladding panels and a highly combustible backing to vertical photovoltaic panel arrays on each tower. Report P3, P30, P33

The Council has landlord duties under the Landlord and Tenant Act 1985 and Housing Act 1985, and the Government is imposing a statutory duty to remediate cladding on buildings 18 metres and over by the end of 2029, with criminal penalties for non-compliance. Report P18, P22

The Pretium framework offers pre-assessed suppliers experienced in social housing fire safety works, and a mini-competition is faster than a full regulated procurement which would take 12 to 24 months. Report P45, P48, P62

What happens next

Expressions of interest from framework suppliers will be sought from 29 January 2026, with the mini-competition published on 23 February 2026 and responses closing on 20 April 2026. Report P71

The PCSA contract is scheduled to commence on 19 November 2026, with the main works contract starting in September 2027 and practical completion expected in February 2030. Report P71

A further Cabinet report will be required to approve the appointment of a contractor and set out detailed financial implications; Section 20 leaseholder consultation will be carried out. Report P15, P106, P107

The money

  • Estimated value in Exempt Appendix 1 (not disclosed) Estimated procurement contract value for façade, window, smoke control and ventilation works Report P4, P16, P42

Options considered

  • Rejected: Do nothing or decommission the requirement. Buildings must be brought up to current safety standards Report P43
  • Rejected: Call-off from the existing Council Responsive Capital contract. High value and complexity make market competition preferable for value for money Report P44
  • Rejected: Run a full regulated competitive procurement advertised to the market. Would take 12 to 24 months, conflicting with the urgency of safety works Report P44
  • Chosen: Mini-competition via the Pretium Building and Fire Safety Framework, Lot 8. Compliant with PCR 2015, suppliers are pre-assessed for social housing fire safety, and the route is faster than a full tender Report P45

Implications

  • Financial: Costs are expected to be funded from additional Housing Revenue Account borrowing, subject to Cabinet approval in the quarterly Capital Programme Monitor; leaseholders will be recharged for windows, smoke control and ventilation works after consultation. Report P15, P107
  • Legal: A new statutory duty will require landlords to complete cladding remediation on buildings 18 metres and over by the end of 2029, with criminal penalties including unlimited fines and imprisonment for non-compliance. Report P22
  • Equalities: An Equalities Impact Assessment has been completed; major refurbishment may disproportionately affect residents with protected characteristics such as age or disability, and the project team will liaise with housing management to identify vulnerable residents. Report P88, P89
  • Climate: New cladding and windows should significantly improve energy efficiency, supporting the Government target of Energy Performance Certificate C for social rented homes by 2030. Report P95
  • Staffing: The Transfer of Undertakings (Protection of Employment) Regulations 2006 (TUPE) do not apply to this contract. Report P60
  • Other: Leaseholders will be consulted under Section 20 of the Landlord and Tenant Act 1985 and the Qualifying Long-Term Agreement procedure, with Notice of Intention and Notice of Proposal stages either side of the procurement. Report P104, P105, P106

Who and where

  • Residents of Norland House, Poynter House and Stebbing House at Edward Woods estate, providing 540 homes Report P31
  • 79 leaseholders across the three blocks (25 in Norland, 27 each in Poynter and Stebbing) Report P104
  • Shepherds Bush Green ward Report P8

Timeline

  • 29 January 2026: Preliminary market engagement notice (expressions of interest) Report P71
  • 23 February 2026: Publish mini-competition Report P71
  • 20 April 2026: Closing date for procurement responses Report P71
  • 6 July 2026: Contracts Assurance Board (award) Report P71
  • 14 September 2026: PCSA contract award notice issued (post Section 20 consultation) Report P71
  • 19 November 2026: PCSA contract commencement Report P71
  • September 2027: Works contract commencement Report P71
  • February 2030: Works contract practical completion Report P71
  • August 2030: Works contract regulator sign-off Report P71

Plain English for the jargon

  • A1-rated: Fire safety classification for non-combustible building materials, the highest standard
  • PCSA: Pre-Construction Services Agreement, a contract for design work before a main works contract
  • JCT: Joint Contracts Tribunal, a standard form of building contract used in the UK
  • MEAT: Most Economically Advantageous Tender, the bid with the highest combined quality and price score
  • QLTA: Qualifying Long-Term Agreement, a long-duration contract that triggers additional leaseholder consultation duties
  • PCR 2015: Public Contracts Regulations 2015, the procurement rules in force when the framework was set up
  • CSOs: Contract Standing Orders, the Council's internal rules for procuring contracts
  • HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending
  • BSR: Building Safety Regulator, the body that must sign off higher-risk building work
  • SME / VCSE: Small and Medium-sized Enterprises / Voluntary, Community and Social Enterprises
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

To note that Appendix 1 is not for publication on the basis that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) as set out in paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended). That Cabinet approves the procurement strategy proposing a mini-competition via the Pretium Building and Fire Safety Framework (Lot 8 – External Wall Works) to source a contractor to undertake external façade safety works at Norland House, Stebbing House, Poynter House Edward Woods estate W11. That Cabinet notes that the procurement will be a two-stage design and build process with the Council entering into a pre-construction services agreement (“PCSA”) with a preferred supplier. Following completion of the design phase the Council will seek to enter into a works contract with the preferred supplier.
Word for word from the decision Hammersmith & Fulham published for this meeting. Source: democracy.lbhf.gov.uk

Follow this further

Built from Hammersmith & Fulham's papers

What the report saysPro

Report to Cabinet

Summary

London Borough of Hammersmith & Fulham (the “Council”) has commissioned a works programme at Edward Woods estate to refurbish the external facades and windows, and upgrade ventilation and smoke control systems of three 24-storey towers - Norland House, Poynter House and Stebbing House – to ensure they meet current Building Regulations. The works will protect the structure of the buildings from the elements, extending their design life, whilst further improving fire safety and thermal insulation for residents.

Between 2010 and 2013 the towers at Edward Woods underwent major works with the installation of a render cladding system on the north and south elevations, the installation of new cladding panels to the east and west (front and rear) elevations; and the installation of photovoltaic solar panels to the principal south-facing façade of each block. The electricity generated by the solar panels contributed to the powering of communal facilities such as lighting and lifts.

Following the Grenfell tragedy, the Council commissioned a proactive inspection of the original works and found areas of fire concern including the absence of cavity barriers to cladding panels, delamination of some cladding panels and absence of firestopping. The backing of the Photovoltaic (PV) panel arrays, stacked vertically from the 4th to the 24th floor, was found to be constructed from a highly combustible material.

In response to this investigation, the first part of this programme has seen the completion of works relating to the removal of PV panel arrays and internal PV equipment and the installation of hoists, mast climbers, scaffolding to facilitate the removal of existing cladding. The Council is now required to engage a contractor to undertake the remaining works which include: installation of a new A1-rated cladding system, replacement windows, and smoke control and ventilation improvement works. The A1 rating of the new components certifies that the materials used are non-combustible and achieve the highest fire safety standards. This report seeks approval to run a procurement exercise to source a contractor to undertake the required works via a mini-competition using the Pretium- Building and Fire Safety Framework, Lot 8 – External Wall Works. The estimated value of this procurement is included in Exempt Appendix 1.

Recommendations

1. To note that Appendix 1 is not for publication on the basis that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information) as set out in paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended).

2. That Cabinet approves the procurement strategy proposing a mini-competition via the Pretium Building and Fire Safety Framework (Lot 8 – External Wall Works) to source a contractor to undertake external façade safety works at Norland House, Stebbing House, Poynter House Edward Woods estate W11.

3. That Cabinet notes that the procurement will be a two-stage design and build process with the Council entering into a pre-construction services agreement (“PCSA”) with a preferred supplier. Following completion of the design phase the Council will seek to enter into a works contract with the preferred supplier.

Wards Affected: Shepherds Bush Green

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equalities Impact AssessmentAppendix 3 249 KB Download
PDF
Procurement Strategy for Edward Woods Towers External Facade and Window Replacement WorksReport 516 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
SC
Councillor Stephen CowanChair, present
AS
Councillor Alex SandersonCommittee Member, present
FC
Councillor Florian Chevoppe-VerdierCommittee Member, present
WH
Councillor Wesley HarcourtCommittee Member, present
RH
Councillor Rebecca HarveyCommittee Member, present
AJ
Councillor Andrew JonesCommittee Member, apologies
BK
Councillor Bora KwonCommittee Member, present
ZQ
Councillor Zarar QayyumCommittee Member, present
RR
Councillor Rowan ReeCommittee Member, present
FU
Councillor Frances UmehCommittee Member, present

On this subject at Hammersmith & Fulham

Search all
  1. Procurement Strategy for Edward Woods Towers External Facade and Window Replacement WorksThis decision
  2. Procurement Strategy for Community Reablement and HomecareNoted
  3. Procurement Strategy for Housing Repairs 2027Noted
  4. Procurement Strategy for the Recommissioning of H&F 0-19(25) Public Health Nursing Services and a New Maternity in the Community ServiceApproved
  5. Local Electric Vehicle Infrastructure (LEVI) Procurement StrategyNoted
  6. Public Realm Works and Consultancy Procurement StrategyApproved

More from Hammersmith & Fulham Cabinet

All decisions
MeetingDecisionOutcome
12 Oct 2026 General Fund Medium Term Financial Plan 2027/28 - 2030/31Note the revised Medium Term Financial Strategy for 2027/28 to 2030/31. To agree next steps to take forward the devel... Noted Open
12 Oct 2026 Capital Programme Monitor and Budget Variations 2026/27 (First Quarter)To note the overall forecast of £209.3m for 2026/27 capital expenditure which is a net decrease of £51.1m in comparis... Noted Open
12 Oct 2026 LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy... Approved Open
12 Oct 2026 TfL Hammersmith Road Permanent Cycleway 9 (C9)To support the implementation of Transport for London's Permanent Cycleway 9 scheme on Hammersmith Road, subject to c... Approved Open
12 Oct 2026 Approval to Consult on the School Organisation Plan and Primary Place Sufficiency OptionsThat Cabinet: Approve consultation on the draft School Organisation Plan and associated options for managing primary ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies