Capital Programme Monitor and Budget Variations 2025/26 (Quarter 3)
NotedExecutive1 paper
AI summaryHammersmith & Fulham Cabinet notes £220.8m 2025/26 capital spend forecast, £45m below Q2 budget, and approves £3.7m extra investment across the four-year programme, now totalling £657.776m.
Written from the decision and the officer reportPDF Pro
OutcomeNotedQ3 2025/26 monitor and £3.7m additions approved
Money£657.776mTotal four-year capital programme 2025-2029
What happens nextMonitor through Q4 and next cycleRisks include sales, Right to Buy, Civic Campus
Who it affectsAll wards in the boroughHousing, Town Hall, Fire Safety, Highways
What was decided
Cabinet noted the 2025/26 capital spend forecast of £220.8m, a £45m net reduction from the Q2 revised budget of £265.3m. Report P7
Cabinet approved an additional £3.7m of investment across the revised four-year programme, including new borrowing, with details in Appendix 1. Report P8
Cabinet approved the updated four-year capital programme for 2025-2029 totalling £657.776m, a £3.7m net increase on the Q2 forecast of £654.026m. Report P9
Why
The report sets the council's overall financial strategy of significant capital investment in the borough's infrastructure, supporting priorities including housing, regeneration, children and a safer borough. Report P2, P3, P11
Variances include slippages and accelerations between financial years to match forecast timing of project delivery, with no change to the overall budget envelope. Report P26
The council aims to confirm spend fits its priorities, challenge how much needs to be spent, and achieve results within agreed budgets. Report P13
What happens next
The detailed plans and strategy for managing the council's Capital Financing Requirement are discussed in the Treasury Management Strategy and Medium-Term Financial Strategy. Report P41
Finance officers are working with departments to manage VAT partial exemption risk on capital projects, where a breach could cost over £3m per year. Report P68
The Client Management Team continues to monitor Civic Campus works, with the Health & Safety Executive report on the site incident still awaited. Report P54
The money
£220.8m Forecast 2025/26 capital expenditure Report P7
Chosen: Note 2025/26 capital forecast of £220.8m. Reflects latest expected spend, £45m below Q2 revised budget. Report P7
Chosen: Approve £3.7m additional investment in the four-year programme. Includes new borrowing, details in Appendix 1. Report P8
Chosen: Approve updated 2025-2029 capital programme of £657.776m. Net £3.7m increase on Q2 forecast of £654.026m. Report P9
Implications
Financial: Borrowing to fund additions will increase the Capital Financing Requirement and must be considered alongside the revenue budget and medium-term financial strategy. Report P16
Risk: Housing development sales risk: slower frequency or lower receipts than originally forecast could affect funding of the wider capital programme. Report P52
Risk: Right to Buy funding risk: reduced discounts are expected to lead to lower Right to Buy sales in coming years, affecting HRA capital receipts. Report P53
Risk: Cost inflation and interest rates remaining higher than previous medium-term forecasts pose ongoing risks to capital programme costs and debt. Report P55, P56
Financial: VAT partial exemption breach could cost the council over £3m per year whilst in breach; finance officers are working with departments on this. Report P68
Legal: No direct legal implications; legal advice will be sought for each procurement and additional advice on individual projects where needed. Report P18
Equalities: No direct equalities implications; recommendations do not directly impact groups with protected characteristics under the Equality Act 2010. Report P57
Who and where
All wards across the London Borough of Hammersmith & Fulham Report P10
Disabled residents, through implementation of the Disabled People's Housing Strategy Report P13
Construction contractors and developers working with the council Report P58
Future home seekers and affordable housing applicants Report P52
Timeline
23 February 2026: Report signed off by Director of Finance, Assistant Director of Legal Services, Director of Audit, Fraud, Risk and Insurance, and Principal Accountant (Taxation). Report P17, P18, P66, P69
2025/26: Capital programme forecast spend of £220.8m, with £70.2m on housing and regeneration, £24.3m on Town Hall refurbishment, and £13.4m on fire safety. Report P5, P7
2028/29: Forecast total Capital Financing Requirement of £1.001bn across General Fund and HRA. Report P51
Plain English for the jargon
CFR: Capital Financing Requirement, the council's outstanding debt for borrowing used to fund capital programmes.
MRP: Minimum Revenue Provision, a required annual payment from revenue resources towards outstanding debt.
HRA: Housing Revenue Account, the ring-fenced account for council housing income and spending.
GF: General Fund, the council's main revenue account covering services other than council housing.
CIL: Community Infrastructure Levy, a charge on development to fund infrastructure.
Section 106: Planning obligations under Section 106 of the Town and Country Planning Act used to fund infrastructure.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
To note the overall forecast of £220.8m for 2025/26 capital expenditure which is a net decrease of £45m in comparison to the revised budget of £265.3m at Q2 2025/26. To approve a total additional investment of £3.7m across the revised four-year programme, including new additional borrowing, the details of this investment are set out in Appendix 1. To approve the updated four-year capital programme for 2025-2029 of £657.776m, as detailed in the report. This is a net increase of £3.7m in comparison to the forecast four-year programme as at Q2 2025/26 (£654.026m).
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
The Council’s Corporate Plan for 2023-26 sets out the Council’s strategy for delivering on the ambitions and vision to transform its services and spend and invest money to help protect high quality essential services for its residents.
A key value is Building Shared Prosperity, and the Council’s overall financial strategy includes significant capital investment in the infrastructure of the Borough and this in turn supports the delivery of the Council’s key priorities and strategies. These are:
• build a better future for children and young people • foster inclusive, sustainable economic growth for everyone • build more affordable, accessible, safe and sustainable housing • deliver high quality housing services • Ensuring our borough is a safer, stronger, kinder borough to live in, work and visit through expansion of our CCTV infrastructure to prevent and deter crime.
All capital programmes are complex and involve considerable local community engagement, procurement, and planning considerations. The 2025/26 capital programme is forecast to spend £220.8m as at quarter three. Some major areas of spend major areas of spend with the 2025/26 budget is:
• £70.2m completing Housing and Regeneration Projects • £24.3m on refurbishing the Hammersmith Town Hall; • £13.4m on Fire Safety programmes • £4.3m on Planned Maintenance schemes; • £10.2m on bringing void housing units back into service. • £8.9m on the Acquisition of Affordable Housing units;
Work is also continuing to complete the Civic Campus development that will re-open the iconic town hall to the public, which will rejuvenate and regenerate an important part of the Borough, providing a vibrant entertainment, arts, business, education, and social destination featuring world-class architecture. The details of the forecast capital programme for the financial year 2025/26 (including the financing of the programme for the year) and the future years are set out in the report.
Recommendations
1. To note the overall forecast of £220.8m for 2025/26 capital expenditure which is a net decrease of £45m in comparison to the revised budget of £265.3m at Q2 2025/26.
2. To approve a total additional investment of £3.7m across the revised four-year programme, including new additional borrowing, the details of this investment are set out in Appendix 1.
3. To approve the updated four-year capital programme for 2025-2029 of £657.776m, as detailed in the report. This is a net increase of £3.7m in comparison to the forecast four-year programme as at Q2 2025/26 (£654.026m).
Wards Affected: All
The capital programme contains schemes and projects which are directly linked to the Council’s priorities.
Our Values Summary of how this report aligns to the H&F Values Being ruthlessly financially All capital investment decisions are required to efficient be underpinned by a robust business case that sets out the full costs, funding and risks and any expected financial return alongside the broader outcomes including economic and social benefits.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.