AI summaryCabinet notes 2025/26 capital programme outturn of £189.9m, around £31m under the Q3 forecast, with most slippage on housing refurbishment and property acquisition.
Written from the decision and the officer reportPDF Pro
OutcomeNotedFive recommendations to note spending and financing
Money£189.9m capital outturnAround £31m under Q3 forecast
What happens nextNo new decisionsReport is wholly of a financial nature
Who it affectsAll wardsBorough-wide capital programme
What was decided
Cabinet noted an aggregate capital outturn of £190m for 2025/26. Report P6
Cabinet noted the General Fund outturn of £64m against a Q3 budget of £72m, with a Capital Financial Requirement of £338m. Report P6
Cabinet noted the Housing Revenue Account outturn of £126m against a Q3 budget of £148m, with a Capital Financial Requirement of £559m. Report P6
Why
The report provides detailed analysis of the council's capital programme financial position and highlights potential risks and their impact on the council's resources. Report P9
All capital investment decisions are required to be underpinned by a robust business case that sets out the full costs, funding and risks alongside broader outcomes including economic and social benefits. Report P8
What happens next
Slipped spending, including £8.6m on Major Refurbishment Works, £8.4m on Property Acquisition for Affordable Housing and £2.8m on the Town Hall refurbishment, is now expected in 2026/27. Report P69, P79, P84, P89
Officers will continue to manage VAT partial exemption risk on capital projects, where a breach could cost the council around £3m per year. Report P63
The money
£189.9m Total capital expenditure for 2025/26 Report P3, P22
£63.567m General Fund capital expenditure for 2025/26 Report P25, P28
£126.265m Housing Revenue Account capital expenditure for 2025/26 Report P25, P39
£30.998m Total underspend against Q3 revised budget Report P25, P88
£337.688m Closing General Fund Capital Financing Requirement 2025/26 Report P34
£559.187m Closing HRA Capital Financing Requirement 2025/26 Report P46, P48
£23.506m Civic Campus spend, including Town Hall refurbishment Report P29, P78
£69.462m HRA spend on existing housing stock Report P43, P87
Options considered
Chosen: Note the capital outturn figures and Capital Financial Requirements as presented. Recommendations in the officer report, recorded by Cabinet as decisions Report P6
Implications
Financial: A VAT partial exemption breach could cost the council around £3m per year whilst in breach, with capital projects representing the bulk of this risk. Report P63
Risk: Construction firms face financial instability following geo-political events and cost inflation, which could lead to costly supplier changes, direct financial loss or unresolved defects. Report P53
Legal: Works must comply with the Fire Safety Act 2021, the Construction (Design and Management) Regulations and the Grenfell Tower Inquiry Phase 2 recommendations published on 4 September 2024. Report P56, P58, P59
Equalities: No direct equalities implications identified, as the report concerns only financial management issues, though it will implement the Disabled People's Housing Strategy in co-production with disabled residents. Report P9, P52
Climate: The programme supports the council's target of net zero greenhouse gas emissions in the borough by 2030, set out in the Climate and Ecology Strategy and action plan. Report P9
Who and where
All ward residents (the programme is borough-wide) Report P7
Council tenants, through £69.462m of housing stock maintenance and compliance work Report P4, P43, P44
Disabled residents, through the Disabled People's Housing Strategy and adaptation works Report P9, P52
Future users of the Civic Campus, including arts, business, education and community users Report P5
Timeline
2025/26: Capital programme outturn year covered by the report Report P3
2026/27: Around £31m of slipped spending is now expected, including the completion of Quayside Lodge and Town Hall refurbishment delays Report P69, P79, P84
2029/30: General Fund Headline CFR forecast to reach £309.83m and HRA CFR forecast to be £534.867m Report P35, P46
2030: Council's net zero greenhouse gas emissions target for the borough Report P9
Plain English for the jargon
CFR (Capital Financing Requirement): The council's underlying need to borrow to support its capital programme, including mainstream and self-financing schemes.
HRA (Housing Revenue Account): A ring-fenced account that records the income and spending relating to council housing.
MRP (Minimum Revenue Provision): The minimum amount a council must charge each year to its revenue budget to repay external borrowing, as set out in statutory guidance.
PWLB (Public Works Loans Board): A government body that lends money to local authorities for capital projects, currently at long-term rates of 5.17% to 6.66%.
CIL (Community Infrastructure Levy): A planning charge on new development used to fund infrastructure.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
RESOLVED To note an aggregate capital outturn of £190m for 2025/26 To note the capital outturn for the General Fund for 2025/26 of £64m against a Q3 budget for GF of £72m To note the Capital Financial Requirement of £338m for the General Fund for 2025/26 and the sources of financing. To note the capital outturn for the HRA for 2025/26 of £126m against a Q3 budget for HRA of £148m To note the Capital Financial Requirement of £559m for the HRA for 2025/26 and the sources of financing.
Word for word from the decision Hammersmith & Fulham published for this meeting.Source: democracy.lbhf.gov.uk
The Council’s Corporate Plan for 2023-26 sets out the Council’s strategy for delivering on the ambitions and vision to transform its services and spend and invest money to help protect high quality essential services for its residents. A key value is Building Shared Prosperity, and the Council’s overall financial strategy includes significant capital investment in the infrastructure of the Borough and this in turn supports the delivery of the Council’s key priorities and strategies. These are:
• build a better future for children and young people • foster inclusive, sustainable economic growth for everyone • build more affordable, accessible, safe and sustainable housing • deliver high quality housing services
All capital programmes are complex and involve considerable local community engagement, procurement, and planning considerations. The total capital outturn for 2025/26 was £189.9m and this included:
• £69m was invested in the existing council homes to ensure compliance and building affordable new homes for residents • £3m maintaining the UK’s most comprehensive CCTV network, with more cameras per resident than anywhere else in the country • £58m investment in acquiring and building new affordable housing and supported accommodation in the Borough
Work is also continuing to complete the Civic Campus development that will re-open the iconic town hall to the public, which will rejuvenate and regenerate an important part of the Borough, providing a vibrant entertainment, arts, business, education, and social destination featuring world-class architecture.
The details of the capital programme outturn for the financial year 2025/26 (including the financing of the programme for the year. RECOMMENDATIONS 1. To note an aggregate capital outturn of £190m for 2025/26 2. To note the capital outturn for the General Fund for 2025/26 of £64m against a Q3 budget for GF of £72m 3. To note the Capital Financial Requirement of £338m for the General Fund for 2025/26 and the sources of financing. 4. To note the capital outturn for the HRA for 2025/26 of £126m against a Q3 budget for HRA of £148m 5. To note the Capital Financial Requirement of £559m for the HRA for 2025/26 and the sources of financing.
Wards Affected: All
Our Values Summary of how this report aligns to the H&F Values Being ruthlessly financially All capital investment decisions are required to be efficient underpinned by a robust business case that sets out the full costs, funding and risks and any expected financial return alongside the broader outcomes including economic and social benefits.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
LBHF Digital Strategy 2026 to 2030That Cabinet approve the LBHF Digital and Information Strategy 2026 to 2030 including the publication of the strategy...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.