That the River Hamble Board approves the Harbour Works Consent for the proposal set out in Section 3 of this report and subject to the following conditions: a) That the proposal is to be built in accordance with the details, plans and method set out in paragraph 3.5. b) That all reasonable precautions are undertaken to ensure no pollutants enter the water-course. c) That all equipment and debris associated with the works should be removed from the area upon completion of the works and the area returned to its previous condition. d) That the user completes a full Risk Assessment for the new pontoon arrangement to ensure that all risks to those are reduced to a level that is as low as reasonably practicable. e) That the development must be completed within 3 years from the date of the approval granted by the Harbour Board. f) That the permissions from the Local Planning Authority, Environment Agency, Marine Management Organisation and The Crown Estate be obtained before any work begins on the project.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
1.1This report sets out an application for Harbour Works Consent (HWC) made by YMCA Fairthorne Manor, Curdridge, Southampton, SO30 2GH
1.2The proposal is to install a 12x3 metre floating pontoon to an existing quay wall at the YMCA Fairthorne Manor water sports centre, located at National Grid Reference SU518 119. The application also proposes some mitigation through the removal of existing structures from the intertidal mud.
2. Background 2.1. YMCA Fairthorne Manor is a Hampshire County Council approved outdoor activity centre which borders the River Hamble. It offers a wide variety of activity programmes to help develop life skills, stimulate learning and improve confidence. The site hosts over 12,000 young people per year across the 111 acre park and woodland site. The small water sports centre offers raft building, kayaking, open canoeing and sailing at higher states of the tide during the summer months only. This is a private site for use by supervised YMCA clients only.
3. Project Description
3.1The YMCA wish to improve the safety of access to the water for its clients by installing a 12x3 metre pontoon fixed by runners alongside an existing sheet pile quay wall. The pontoon will extend 3 metres from the quay wall and will sit on the mud at lower states of the tide. This will complement an existing pontoon (12x2.9) located 2 metres further downstream. 3.2. An old pontoon (4.5x5.5 metres) formerly located at the site, which extended 8m from the quay wall, has previously been removed. 3.3. It is proposed that 2 redundant timber piles which supported the old pontoon also be removed, to be cut off at bed level.
3.4The removal of an old boat mould, washed up on the foreshore upstream, is also proposed in order to free-up the intertidal mud area underneath.
3.5The following plans and documents have been provided by the applicant to support this application, and reference must be made to these for a full understanding of the proposal (see Appendix 1a-c): Appendix 1a o Project Description Appendix 1b o Proposed Pontoon Drawing ref SOL-3273-SC01-000. Dated 01/09/2016. Appendix 1c o Aerial photograph of location. o Location Plan (Ordinance Survey map). o Photograph showing proposed location. o Aerial photograph showing location of proposals. o Photograph of the old mould to be removed.
4. Harbour Authority’s Responsibilities
4.1Consent may be granted by the River Hamble Harbour Board permitting harbour works in the River Hamble in accordance with Section 10 of the Southampton Harbour Act 1924 and Section 48 of the Southampton Harbour Act 1949 as amended by the River Hamble Harbour Revision Orders 1969 to 1989. Within the River Hamble Harbour Board’s statutory duties lies the responsibility to ensure that all matters concerning navigational safety and responsibilities under the Habitat Regulations are addressed. This area of responsibility includes the proposed development.
4.2Navigational safety issues are addressed through the Port Marine Safety Code and the Harbour’s Safety Management System. Specific issues relevant to this particular application are covered within the Harbour Master’s comments below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.