That the River Hamble Harbour Board approves the Harbour Works Consent for the proposal set out in paragraph 4 of this report and subject to the following conditions: i. The proposal is to be built in accordance with the details, plans and method set out in paragraph 5. ii. The applicant should ensure that only coatings and treatments that are suitable for use in the marine environment are used in accordance with best environmental practice. All reasonable precautions will be undertaken to ensure no pollutants enter the waterbody. iii. The applicant should ensure that all equipment, temporary structures, waste and/or debris associated with the licensed activities is removed upon completion of the licensed activities. iv. The development must be completed within 3 years from the date of the approval granted by the Harbour Board.
Word for word from the decision Hampshire published for this meeting.Source: democracy.hants.gov.uk
2. That the River Hamble Harbour Board approve Harbour Works Consent for the proposal set out in paragraph 4 of this report and subject to the following conditions: a. The proposal is to be built in accordance with the details, plans and method set out in paragraph 5. b. The applicant should ensure that only coatings and treatments that are suitable for use in the marine environment are used in accordance with best environmental practice. All reasonable precautions will be undertaken to ensure no pollutants enter the waterbody. c. The applicant should ensure that all equipment, temporary structures, waste and/or debris associated with the licensed activities is removed upon completion of the licensed activities. d. The development must be completed within 3 years from the date of the approval granted by the Harbour Board. Executive Summary
3. This report seeks to: set out an application for Harbour Works Consent made by John Willment Marine Limited (via its agent Lymington Technical Services) for the installation of a hoist dock pontoon at Universal Marina, Crableck Lane, Sarisbury Green, SO31 7ZN. Consider the impacts of the proposal on safety and ease of navigation and on the environment of the Hamble Estuary, both during construction and once operational.
Project Description
4. The proposal is for the installation of a landing pontoon to improve vessel launching efficiency from the hoist dock.
5. The following documents have been provided by the applicant to support this application, and reference must be made to these for a full understanding of the proposal (see Appendix 1a & 1b): Drawing No. 10584/44B dated Feb 2019. Supporting Statement
Harbour Authority’s Responsibilities
6. Consent may be granted by the River Hamble Harbour Board permitting harbour works in the River Hamble in accordance with Section 10 of the Southampton Harbour Act 1924 and Section 48 of the Southampton Harbour Act 1949 as amended by the River Hamble Harbour Revision Orders 1969 to 1989. Within the River Hamble Harbour Board’s statutory duties lies the responsibility to ensure that all matters concerning navigational safety and responsibilities under the Habitat Regulations are addressed. This area of responsibility includes the proposed development.
7. Navigational safety issues are addressed through the Port Marine Safety Code and the Harbour’s Safety Management System. Specific issues relevant to this particular application are covered within the Harbour Master’s comments below.
8. The River Hamble is part of the Solent European Marine Site and is afforded protection due to its international nature conservation value. The RHHA is a Relevant Authority under the Conservation of Habitats and Species Regulations 2010 as amended, commonly known as the Habitats Regulations. As a Relevant Authority the Harbour Authority has a duty to comply with the requirements of the Habitats Regulations. This means that the RHHA must ensure that, in the exercise of any of its powers or functions, it must have regard to both direct and indirect effects on interest features of the European Marine Site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.