North Tottenham Decent Homes Works Phase NT2

Agreed Executive 1 paper

Cabinet Procurement Committee agreed this item on Tuesday 25 March 2008. Below is the council's own wording, with the papers it was decided on.

Item67

Resolved

That the contract for the North Tottenham Decent Homes Works Phase NT2 contract be awarded to Lovell Partnership Ltd, as allowed under Contract Standing Order (CSO) 11.03. 2. That the total Agreed Maximum Price exclusing fees as detailed in Para 2.1 of Appendix A be noted.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Procurement Committee

REPORT TEMPLATE

Agenda item: [No.] Procurement Committee On 25th March 2008

Report Title: North Tottenham Decent Homes Works Phase NT2.

Forward Plan reference number (if applicable):

Report of: Niall Bolger, Director of Urban Environment

Wards(s) affected: White Hart Lane Report for: Key Decision

1. Purpose 1.1 To inform Members that the Decent Homes Programme for White Hart Lane and Durban Road N17. will commence on 31st March 2008.

2. Introduction by Cabinet Member (if necessary)

2.1In accordance with our commitment to achieve Decent Homes standards to our homes, h properties within this phase have been surveyed and works will include, where required on an individual basis to achieve Decent Homes Standards, replacement Double Glazed windows, Multilock ‘Secure by Design’ Front entrance doors, Renewed fascia’s, soffit’s and rainwater goods, internal rewires, kitchen and bathroom refurbishment and roof renewal and repairs.

3. Recommendations 3.1 That members agree to award the contract for the above Project to the contractor named in Appendix A1.0, as allowed under Contract Standing Order (CSO) 11.03.

3.2That the Agreed Maximum Price excluding fees as detailed in Para 2.1 of Appendix A be noted.

Report Authorised by: Niall Bolger, Director of Urban Environment

Contact Officer: Larry Ainsworth Strategic Client Representative Homes for Harlngey, River Park House (6th Floor) 225 High Road. London N22 4HQ Tel no: 020 8489 1134, e.mail: [email removed]

4. Chief Finance Officer Comments

4.1It should noted that on 13th Feb 2007, this committee approved framework agreements to Decent Homes contractors and 4 compliance teams, to cover 4 areas. This report details the specific works needed to the 13 properties in the NT area, priced in accordance with the framework agreement.

4.2Members will be aware that CLG has approved the funding for Decent Homes, totalling £198.5m phased over six years of which £23m has been approved for 2008-09. This scheme is included in the schedule for 2008-09, thus will be funded from this budget

5. Head of Legal Services Comments

5.1This report is seeking Procurement Committee approval to award a call-off contract for the Decent Homes works at White Hart Lane and Durban Road N17, which are in the North Tottenham area of the borough, to the contractor recommended in paragraph 3 of this report.

5.2Cabinet Procurement committee had on 13th February 2007 granted approval to the award of four Decent Homes Constructor Partner Framework Agreements in respect of four areas within the Borough (Wood Green, Hornsey, North Tottenham and South Tottenham) to four respective contractors, of which the recommended contractor is one.

5.3The Framework Agreements were tendered in the EU and selection of the Framework contractors was undertaken in compliance with the Public Contracts Regulations 2006, as confirmed by external legal advisers (Trowers and Hamlin) who provided legal advice on the procurement of the Framework Agreements.

5.4The contractor recommended in Paragraph 3 of this report was awarded the Framework Agreement in respect of the North Tottenham area of the borough. 5.5 As the value of the proposed contract exceeds £250,000 the award must be agreed by the Procurement Committee in accordance with CSO 11.3.

5.6The Head of Legal Services confirms that there are no legal reasons preventing Members from approving the recommendation as to the award, as set out in paragraph 3 of this report.

6. Head of Procurement Comments.

6.1The selection of the contractor for these works has been undertaken from the Decent Homes contractor framework.

6.2The Client needs ensure that a risk register is in place for the works and are monitored on a regular basis

6.3An agreed Maximum price has been agreed by the parties prior to start on site in accordance with the process allowed under the form of contract.

6.4The Head of Procurement therefore state that the recommendations in this report offer best value for the Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
North Tottenham Decent Homes Works Phase NT2Minutes 146 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 4 attended
ID
Councillor Isidoros DiakidesCommittee Member, present
GM
Councillor George MeehanCommittee Member, present
CA
Councillor Charles AdjeChair, present
LS
Councillor Liz SantryCommittee Member, present

On this subject at Haringey

Search all
  1. North Tottenham Decent Homes Works Phase NT2This decision
  2. Application for the Grant of a New Premises Licence under the Licensing Act 2003 Milcana Café Annexe, 50 Park Lane, Tottenham, London N17 0JS (NORTHUMBERLAND PARK)Noted
  3. Approve extension (and variation where it applies) of the Bounds Green, Bruce Grove, Harringay, Noel Park, Northumberland Park, Seven Sisters, St Anns, Tottenham Green, Tottenham Hale, West Green and Woodside Wards Alcohol Control PSPO'sDecided
  4. Adoption of Conservation Area Appraisal and Management Plans for North Tottenham, Scotland Green, Bruce Grove, Tottenham Green, Seven Sisters/Page Green and South TottenhamNoted
  5. Approval to enter into grant agreements with Tottenham Hotspur FC to deliver heritage and public realm improvements for north TottenhamApproved
  6. North Tottenham Townscape Heritage Initiative - Appointment of Principal Contractor for Phase 1 worksApproved

More from Haringey Cabinet Procurement Committee

All decisions
MeetingDecisionOutcome
12 Apr 2012 Financing the Leisure Service Fitness Suite EquipmentRESOLVED · That the report be noted. Noted Open
12 Apr 2012 Award of coroners' removals contractRESOLVED · That approval be granted for the award of contract for a Coroners’ removal service to Dignity Funeral Ltd ... Approved Open
12 Apr 2012 Contract for the support and maintenance of the Council's IT network, IT security and data centresRESOLVED · That approval be granted to award the replacement contract for the management of the IT network, IT securi... Approved Open
12 Apr 2012 Healthy Alliance - Primary and Secondary Community HIV Prevention Programme for Enfield and HaringeyRESOLVED · That approval be granted to a waiver of the requirements to tender as required under CSO 9.01 as allowed u... Approved Open
12 Apr 2012 Sport and physical activity coaching services suppliers frameworkRESOLVED · That approval be granted for the award of a framework agreement as set out in the report for a minimum per... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies