That the contract for the North Tottenham Decent Homes Works Phase NT4 contract be awarded to Lovell Partnership Ltd, as allowed under Contract Standing Order (CSO) 11.03. 2. That the total Agreed Maximum Price exclusing fees as detailed in Para 2.1 of Appendix A be noted.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Agenda item: [No.] Procurement Committee On 25th March 2008
Report Title: North Tottenham Decent Homes Works Phase NT4.
Forward Plan reference number (if applicable):
Report of: Niall Bolger, Director of Urban Environment
Wards(s) affected: Tottenham Hale Report for: Key Decision
1. Purpose 1.1 To inform Members that the Decent Homes Programme for Tilson Road, Spencer Road, Wycombe Road and Glendish Road N17. will commence on 14th April 2008.
2. Introduction by Cabinet Member (if necessary)
2.1In accordance with our commitment to achieve Decent Homes standards to our homes, h properties within this phase have been surveyed and works will include, where required on an individual basis to achieve Decent Homes Standards, replacement Double Glazed windows, Multilock ‘Secure by Design’ Front entrance doors, Renewed fascia’s, soffit’s and rainwater goods, internal rewires, kitchen and bathroom refurbishment and roof renewal and repairs.
3. Recommendations 3.1 That members agree to award the contract for the above Project to the contractor named in Appendix A1.0, as allowed under Contract Standing Order (CSO) 11.03. 3.2 That the total estimated cost excluding fees as detailed in Para 2.1 of Appendix A be noted.
Report Authorised by: Niall Bolger, Director of Urban Environment
Contact Officer: Larry Ainsworth Strategic Client Representative Homes for Harlngey, River Park House (6th Floor) 225 High Road. London N22 4HQ Tel no: 020 8489 1134, e.mail: [email removed]
4. Chief Finance Officer Comments 4.1 It should noted that on 13th Feb 2007, this committee approved framework agreements to Decent Homes contractors and 4 compliance teams, to cover 4 areas. This report details the specific works needed to the 52 properties in the NT area, priced in accordance with the framework agreement.
4.2Members will be aware that CLG has approved the funding for Decent Homes, totalling £198.5m phased over six years of which £23m has been approved for 2008-09. This scheme is included in the schedule for 2008-09, thus will be funded from this budget
5. Head of Legal Services Comments
5.1This report is seeking Procurement Committee approval to award a call-off contract for Decent Homes works at Tilson Road, Wycombe Road, Glendish Road, Spencer Road N17, which are in the North Tottenham area of the borough, to the contractor recommended in paragraph 3 of this report.
5.2Cabinet Procurement committee had on 13th February 2007 granted approval to the award of four Decent Homes Constructor Partner Framework Agreements in respect of four areas within the Borough (Wood Green, Hornsey, North Tottenham and South Tottenham) to four respective contractors, of which the recommended contractor is one.
5.3The Framework Agreements were tendered in the EU and selection of the Framework contractors was undertaken in compliance with the Public Contracts Regulations 2006, as confirmed by external legal advisers (Trowers and Hamlin) who provided legal advice on the procurement of the Framework Agreements.
5.4The contractor recommended in Paragraph 3 of this report was awarded the Framework Agreement in respect of the North Tottenham area of the borough. 5.5 As the value of the contract is above the Council’s Key Decision threshold of £500,000, the Council’s Arms Length Management Organisation, Homes for Haringey, who undertook the procurement of the contract on behalf of the Council have confirmed that in accordance with CSO 11.04, details of this contract have been included on the Forward Plan (Version 71), ,
5.6As the value of the proposed contract exceeds £250,000 the award must be agreed by the Procurement Committee in accordance with CSO 11.3.
5.7The Head of Legal Services confirms that there are no legal reasons preventing Members from approving the recommendation as to the award, as set out in paragraph 3 of this report. 6. Head of Procurement Comments
6.1The selection of the contractor for these works has been undertaken from the Decent Homes contractor framework.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Award of coroners' removals contractRESOLVED · That approval be granted for the award of contract for a Coroners’ removal service to Dignity Funeral Ltd ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.