Resolved
RESOLVED To note progress made in 2021/22 despite the challenges of the limited budget, increasing number of severe weather events placing additional pressure on the assets; and To approve adjustments to priorities as listed in the report .
Alexandra Park and Palace Board noted this item on Thursday 29 September 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED To note progress made in 2021/22 despite the challenges of the limited budget, increasing number of severe weather events placing additional pressure on the assets; and To approve adjustments to priorities as listed in the report .
Alexandra Park and Palace Charitable Trust
Forward Maintenance Plan Annual Update and Recommendation 2021/22
August 2022– Charts and Year 8 Priority A Packages Progress to date against 10 year Fabric Maintenance Plan Actual @ end Year 7 Target @ end Year 7 Priority items for Year 8 Total @ end Year 10 £800,000 100% Summary of building fabric
£700,000 83.5% 100% £600,000 £500,000 repairs
£400,000 111.4% 100% £300,000 84.0% 100% 35.4% £200,000 20.0% 17.96% £100,000 158.8% 15.8% 6.8% 0.8% 3.5% 0.0% £- West Entrance, Palm Court & Adjoining WestRooms Hall, West Corridor & AdjoiningService RoomsYard, Stores & North West Tower South West Tower
Condition (2014) Fair Condition (2014) Fair Condition (2014) Poor Condition (2014) Fair Condition (2021) Fair Condition (2021) Fair Condition (2021) Fair Condition (2021) Fair/Poor
Sector 1 Sector 2 Sector 3 Sector 4 FMP Packages – Year 8 2021/22 o Sector 1 – West Entrance, Palm Court and Adjoining Spaces • Priority A Glazing works plus access £14,510 and £104,094 • Priority A Crittall lantern re-glazing £4,000 • Priority A Crittall lantern refurbishment £11,000 • Priority A Various roof leaks £13,436 to Sector 1 and other sectors • Priority A/B SW Pavilion roof repair and decoration DEFERRED • Priority A/B Redecoration DEFERRED
o Sector 2 – West Hall, West Corridor and Adjoining Rooms • Priority A £4,640 • Priority A/B Redecoration £1,200 DEFERRED
o Sector 3 – Service Yard, Stores and North West Tower • Priority A Box Office roof repairs £1,926 • Priority A/B Box Office refurbishment £8,594 • Priority B North West Service Hall roof access install DEFERRED
o Sector 4 – South West Tower o Priority B SW Tower renew roof, windows and internal scaffold DEFERRED Progress to date against 10 year Fabric Maintenance Plan £1,400,000 Actual @ end Year 7 Target @ end Year 7 Priority items for Year 8 Total @ end Year 10 Summary of building fabric repairs
123.0% 100% £1,200,000
84.4% £1,000,000
£800,000
100% £600,000 100% 81.5% 92.8% 100% £400,000 54.6%
59.3% £200,000 34.8% 16.2% 1.9% 0.8% 1.9% 0.6% £- Panorama Room and The Great Hall Ice Rink and Adjoining Theatre, North East Tower South West Colonnade Spaces and Adjoining Spaces
Condition (2014) Fair Condition (2014) Fair Condition (2014) Fair Condition Condition (2014) Poor Condition Condition (2021) Fair/Poor Condition (2021) Fair/Poor (2021) Fair (2021) Good/Fair
Sector 5 Sector 6 Sector 7 Sector 8 FMP Packages – Year 8 o Sector 5 – Panorama Room and South West Colonnade • Priority A Emergency repairs to PR link roof £500 • Priority A/B - SW Colonnade floor slab renewal ( 2 bays) £39,000 DEFERRED • Priority B SW Colonnade & West Light well roof access install £3,400 DEFERRED
o Sector 6 – The Great Hall • Priority A Great Hall/North Service Yard Bridge & Stairs structural repairs DEFERRED • Priority A Great Hall Spaceframes -External Redecoration £73140 • Priority A Great Hall Glazing Servicing & Replacements £21680 • Priority A Great Hall Glazing Servicing & Replacements £12490 PART DEFERRED • Priority B Carry out feasibility for resurfacing the entire floor to Great Hall DEFERRED
o Sector 7 – Ice Rink and Adjoining Spaces • Priority A Smoke Vents Replacement £7080 • Priority A Roof repairs (south) £2889
o Sector 8 – Theatre, North East Tower and Adjoining Spaces • Priority A Spider access for bi-annual inspections of ceiling, walls & proscenium arch July 21 £3282 plus £650 • Priority A Theatre Bi-annual ceiling, proscenium arch and walls inspections January 22 • Priority A Auditorium ceiling and walls preventative works £3475 Progress to date against 10 year Fabric Maintenance Plan £2,500,000 Actual @ end Year 7 Target @ end Year 7 Priority items for Year 8 Total @ end Year 10 100% Summary of building fabric repairs
87.2% £2,000,000
£1,500,000 100%
100% 93.4% £1,000,000 65.37%
52.2% £500,000
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
9b. FMP Annual Update and Recommendation Draft WIP Aug 2022Minutes | 10 pages | DownloadRead as text |
PDF |
9c. FMP Annual Update and Recommendation (graph 10 year actual against target: Priority A only)Minutes | 2 pages | Download |
PDF |
FABRIC MAINTENANCE PLAN ANNUAL REPORTMinutes | 7 pages | Download |
Follow Alexandra Park and Palace Board at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Oct 2026 | Charitable Trust Progress ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | FRRAC Chair's Report (Verbal update)The Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Finance ReportThe Committee noted the 2026/27 forecast against revised budget. | Noted | Open |
| 29 Oct 2026 | Panorama Room ReportThe Committee noted the report. | Noted | Open |
| 29 Oct 2026 | Environmental Sustainability UpdateThe Committee noted the contents of this report and approve the Carbon Reduction Plan at Appendix 1. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.