FABRIC MAINTENANCE PLAN ANNUAL REPORT

Noted Committee 3 papers

Alexandra Park and Palace Board noted this item on Thursday 29 September 2022. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

RESOLVED To note progress made in 2021/22 despite the challenges of the limited budget, increasing number of severe weather events placing additional pressure on the assets; and To approve adjustments to priorities as listed in the report .
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Alexandra Park and Palace Board, 10 pages

Alexandra Park and Palace Charitable Trust

Forward Maintenance Plan Annual Update and Recommendation 2021/22

August 2022– Charts and Year 8 Priority A Packages Progress to date against 10 year Fabric Maintenance Plan Actual @ end Year 7 Target @ end Year 7 Priority items for Year 8 Total @ end Year 10 £800,000 100% Summary of building fabric

£700,000 83.5% 100% £600,000 £500,000 repairs

£400,000 111.4% 100% £300,000 84.0% 100% 35.4% £200,000 20.0% 17.96% £100,000 158.8% 15.8% 6.8% 0.8% 3.5% 0.0% £- West Entrance, Palm Court & Adjoining WestRooms Hall, West Corridor & AdjoiningService RoomsYard, Stores & North West Tower South West Tower

Condition (2014) Fair Condition (2014) Fair Condition (2014) Poor Condition (2014) Fair Condition (2021) Fair Condition (2021) Fair Condition (2021) Fair Condition (2021) Fair/Poor

Sector 1 Sector 2 Sector 3 Sector 4 FMP Packages – Year 8 2021/22 o Sector 1 – West Entrance, Palm Court and Adjoining Spaces • Priority A Glazing works plus access £14,510 and £104,094 • Priority A Crittall lantern re-glazing £4,000 • Priority A Crittall lantern refurbishment £11,000 • Priority A Various roof leaks £13,436 to Sector 1 and other sectors • Priority A/B SW Pavilion roof repair and decoration DEFERRED • Priority A/B Redecoration DEFERRED

o Sector 2 – West Hall, West Corridor and Adjoining Rooms • Priority A £4,640 • Priority A/B Redecoration £1,200 DEFERRED

o Sector 3 – Service Yard, Stores and North West Tower • Priority A Box Office roof repairs £1,926 • Priority A/B Box Office refurbishment £8,594 • Priority B North West Service Hall roof access install DEFERRED

o Sector 4 – South West Tower o Priority B SW Tower renew roof, windows and internal scaffold DEFERRED Progress to date against 10 year Fabric Maintenance Plan £1,400,000 Actual @ end Year 7 Target @ end Year 7 Priority items for Year 8 Total @ end Year 10 Summary of building fabric repairs

123.0% 100% £1,200,000

84.4% £1,000,000

£800,000

100% £600,000 100% 81.5% 92.8% 100% £400,000 54.6%

59.3% £200,000 34.8% 16.2% 1.9% 0.8% 1.9% 0.6% £- Panorama Room and The Great Hall Ice Rink and Adjoining Theatre, North East Tower South West Colonnade Spaces and Adjoining Spaces

Condition (2014) Fair Condition (2014) Fair Condition (2014) Fair Condition Condition (2014) Poor Condition Condition (2021) Fair/Poor Condition (2021) Fair/Poor (2021) Fair (2021) Good/Fair

Sector 5 Sector 6 Sector 7 Sector 8 FMP Packages – Year 8 o Sector 5 – Panorama Room and South West Colonnade • Priority A Emergency repairs to PR link roof £500 • Priority A/B - SW Colonnade floor slab renewal ( 2 bays) £39,000 DEFERRED • Priority B SW Colonnade & West Light well roof access install £3,400 DEFERRED

o Sector 6 – The Great Hall • Priority A Great Hall/North Service Yard Bridge & Stairs structural repairs DEFERRED • Priority A Great Hall Spaceframes -External Redecoration £73140 • Priority A Great Hall Glazing Servicing & Replacements £21680 • Priority A Great Hall Glazing Servicing & Replacements £12490 PART DEFERRED • Priority B Carry out feasibility for resurfacing the entire floor to Great Hall DEFERRED

o Sector 7 – Ice Rink and Adjoining Spaces • Priority A Smoke Vents Replacement £7080 • Priority A Roof repairs (south) £2889

o Sector 8 – Theatre, North East Tower and Adjoining Spaces • Priority A Spider access for bi-annual inspections of ceiling, walls & proscenium arch July 21 £3282 plus £650 • Priority A Theatre Bi-annual ceiling, proscenium arch and walls inspections January 22 • Priority A Auditorium ceiling and walls preventative works £3475 Progress to date against 10 year Fabric Maintenance Plan £2,500,000 Actual @ end Year 7 Target @ end Year 7 Priority items for Year 8 Total @ end Year 10 100% Summary of building fabric repairs

87.2% £2,000,000

£1,500,000 100%

100% 93.4% £1,000,000 65.37%

52.2% £500,000

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
9b. FMP Annual Update and Recommendation Draft WIP Aug 2022Minutes 10 pages DownloadRead as text
PDF
9c. FMP Annual Update and Recommendation (graph 10 year actual against target: Priority A only)Minutes 2 pages Download
PDF
FABRIC MAINTENANCE PLAN ANNUAL REPORTMinutes 7 pages Download

At this meeting

Whole meeting

On this subject at Haringey

Search all
  1. FABRIC MAINTENANCE PLAN ANNUAL REPORTThis decision
  2. Fabric maintenance planNoted
  3. Fabric maintenance plan reportNoted
  4. Fabric maintenance planApproved
  5. Fabric maintenance plan (fmp)Noted
  6. Annual report on fabric maintenance planApproved

More from Haringey Alexandra Park and Palace Board

All decisions
MeetingDecisionOutcome
29 Oct 2026 Charitable Trust Progress ReportThe Committee noted the report. Noted Open
29 Oct 2026 FRRAC Chair's Report (Verbal update)The Committee noted the report. Noted Open
29 Oct 2026 Finance ReportThe Committee noted the 2026/27 forecast against revised budget. Noted Open
29 Oct 2026 Panorama Room ReportThe Committee noted the report. Noted Open
29 Oct 2026 Environmental Sustainability UpdateThe Committee noted the contents of this report and approve the Carbon Reduction Plan at Appendix 1. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies