Cabinet, Wednesday 28 January 2026 at 7.00pm

Mercury Land Holdings (MLH) Business Plan and budget update 2026/27

Approved Executive 1 paper

AI summaryCabinet approved MLH's 2026/27 business plan and reprofiled up to a maximum of £270.1 million without seeking extra envelope funding. [D][P1] It added £900,000 to working capital and delegated scheme, finance and disposal decisions. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedIndividual schemes need detailed business cases. [P13]
Money£270.1 million maximum reprofiled [D]No extra envelope funding; working capital rises £900,000. [P1][D]
What happens nextScheme decisions delegated [D]Business cases and disposal terms need approval. [D]
Who it affectsMLH and Council finances [D]MLH develops homes for private rent and sale. [P3]

What was decided

Cabinet approved the MLH Business Plan Update for 2026/27. Individual schemes remain subject to detailed business cases under delegated authority. [D][P13] Report P13

The previously allocated funding of up to a maximum of £270.1 million was reprofiled to updated projects through equity investment and Subsidy Control compliant loans. [D]

Cabinet increased the MLH Working Capital Facility by £900,000 and extended its term for a period of up 5 years, as appropriate, commencing February 2026. It delegated scheme business cases and viability approvals, debt finance agreements, relevant professional appointments, and asset disposal principles and terms. [D]

Why

Approval provides MLH with a framework to grow, meet its objectives and contribute to the Council's financial objectives. [P41] Report P41

Individual funding proposals require a satisfactory business case, further governance and legally binding funding agreements. [P2] Report P2

The Council's housing objectives include increasing supply, providing a suitable mix, supporting regeneration and earning an acceptable return. [P18] Report P18

What happens next

The Cabinet Member for Regeneration & Development, with the specified officers, will approve scheme business cases, viability assessments, funding requirements and related agreements. [D]

The Strategic Director of Resources, with the required legal and regeneration consultations, will complete finance agreements, appoint professionals and determine asset disposal principles and terms. [D]

The Council will monitor MLH's financial information during each loan and release funding only where the required viability and business case tests are met. [P37] Report P37

The money

  • £270.1 million Maximum previously allocated funding reprofiled through equity investment and Subsidy Control compliant loans.
  • £900,000 Increase to the MLH Working Capital Facility.
  • £228.4m Funding commitment sought in the July 2025/26 Cabinet report. Report 6.3
  • £20m Reactive acquisition fund included in the earlier commitment. Report 6.3
  • £2m Ceiling for an under value disposal where the cited General Housing Consents apply. Report 7.9

Options considered

  • Chosen: Approve the updated business plan and delegations. Approval provides a framework for MLH to grow and meet its objectives. Report P41
  • Rejected: Do nothing. It would not fulfil the objective of growing MLH or meeting the objectives it was established to achieve. Report 5.1

Implications

  • Financial: The updated plan seeks no additional funding from the existing envelope. It reprofiles that envelope and forms part of the Capital Programme, with financing monitored through the MTFS and annual budget setting. [P1][6.1] Report P1, 6.1
  • Legal: Funding must use binding Council and MLH agreements and comply with Subsidy Control. Loans and credit must be commercial, and equity needs independent confirmation of commercial terms before entry. [P2][P74][P77] Report P2, P74, P77
  • Legal: Disposals must meet the applicable Secretary of State consent and best consideration rules, and Council powers must be used for a proper purpose. [7.7][7.8][7.12] Report 7.7, 7.8, 7.12
  • Risk: Before lending, the Council must assess repayment, rental income, sales projections, warning levels and financing margins. [P37][P39] Report P37, P39
  • Equalities: There are no adverse equalities implications directly from the updated plan. Equality issues will be considered, as appropriate, for each scheme during design and planning. [9.4] Report 9.4
  • Climate: There are no adverse environmental and climate change implications directly from the report. Each scheme will need to address planning and building control requirements, including climate change, when brought forward. [P92][P93][P94] Report P92, P93, P94
  • Staffing: There are no HR implications for the Council arising from the recommendations. [8.1] Report 8.1
  • Other: There are no direct health and wellbeing implications from the funding. It is expected indirectly to support new housing, residents' health and local construction activity. [10.1][10.2][10.3][10.4] Report 10.1, 10.2, 10.3, 10.4

Who and where

  • Mercury Land Holdings Limited Report P3
  • Havering residents Report P18, P19
  • Private rental tenants Report 2.2, 2.3
  • Buyers of MLH homes Report 2.4
  • Council taxpayers Report P70, P74
  • Local businesses and staff Report 9.2
  • Construction sector and supply chain Report 10.4
  • People needing affordable housing Report 2.5

Timeline

  • May 2015: Cabinet resolved to establish a commercially focused housing company. [P3] Report P3
  • November 2015: MLH was incorporated. [P3] Report P3
  • Feb 2025/26: Funding was allocated in the previous MLH Business Plan. [D]
  • July 2025/26: A Cabinet report sought a £228.4m commitment, including the £20m reactive acquisition fund. [6.3] Report 6.3
  • 28th January 2026: Cabinet decided the updated 2026/27 business plan. [D][P6] Report P6
  • February 2026: The extended MLH Working Capital Facility term is to commence. [D]
  • 2026/27: Scheme business cases may be approved during the business plan period. [D][P2] Report P2
  • During each loan's lifetime: The Council will regularly monitor MLH's financial information. [P37] Report P37

Plain English for the jargon

  • MLH: Mercury Land Holdings Limited, a company wholly owned by the Council. [P3]
  • PRS: Private rented sector homes managed within MLH's portfolio. [P3]
  • MTFS: Medium Term Financial Strategy. [P6]
  • Business case: A satisfactory scheme assessment required before Council funding. [P2]
  • Subsidy Control: Rules requiring Council funding and support to comply with state subsidy requirements. [P74][P77]
  • Working Capital Facility: The facility for MLH working capital increased by this decision. [D]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item78

Resolved

Report Title: Mercury Land Holdings (MLH) Business Plan and budget update 2026/27 Presented by: Councillor Ray Morgon, Council Leader Cabinet : 1. Approved the Mercury Land Holdings Limited Business Plan Update (see Exempt Appendix 3). 2. Agreed to delegate authority to the Cabinet Member for Regeneration & Development, in consultation with the Strategic Director of Resources, the Strategic Director of Place and the Monitoring Officer, to approve the detailed business cases, related viability assessments and funding requirements for the individual schemes noted within the Business Plan as they may be presented during the business plan period, including the authority to enter into all relevant agreements to give effect to the schemes. 3. Agreed that the previously allocated funding in the Feb 2025/26 Business Plan to MLH, up to a maximum of £270.1 million, is re-profiled to projects as updated in the Exempt Agenda, through a combination of equity investment and Subsidy Control compliant loans. 4. Agreed to increase the MLH Working Capital Facility by £900,000 and to extend the term for a period of up 5 years, as appropriate, commencing February 2026, and to delegate authority to the Strategic Director of Resources, in consultation with the Strategic Director Place and the Deputy Director of Legal & Governance to enter into the relevant agreements to give effect to this decision. 5. Agreed to delegate authority to the Strategic Director of Resources to agree, after consultation with the Director of Legal and Governance, the completion of all relevant agreements and appointments of relevant professionals relating to the provision of debt finance by the Council to MLH 6. Noted that the individual schemes are subject to detailed business cases to be approved under delegated authority, as set out in Recommendation 2. 7. Agreed to delegate to the Strategic Director of Resources, in consultation with the Assistant Director of Regeneration and Place Shaping, and the Deputy Director of Legal and Governance, the authority to determine the principles and processes by which any assets shall be disposed of and the terms of disposal to MLH.
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Cabinet, 13 pages

Summary

This report seeks Cabinet approval for the updated MLH Business Plan 2026/27 and its associated financial commitments. The Business Plan includes an update to the development programme and re-profiles the existing approved funding envelope, which was previously provided by the Council, to projects set out in the Exempt Report & Appendices. The updated Business Plan does not seek any additional funding commitment from the previously agreed funding envelope.

Cabinet should note that the updated MLH Business Plan 2026/27 will, if approved, provide a funding envelope within which MLH can operate. Proposals for individual scheme funding are supported by the production of a satisfactory business case at the appropriate time, which is then subject to further examination and additional governance, before the Council can place MLH in funds. This, in turn, is regulated by legally binding funding agreements between the Council as lender and MLH as borrower. Several schemes within the Business Plan already benefit from approved Business Cases.

MLH was formed as Cabinet resolved to establish a commercially focused company that would deliver housing for private rent and sale in May 2015. Mercury Land Holdings Limited (MLH) was subsequently incorporated in November 2015. MLH is wholly owned by the Council. Since its formation, MLH has established and manages a portfolio of private rented sector (PRS) homes. It has also developed and sold properties for private sale and affordable rent.

The MLH Business Plan seeks to reaffirm MLH’s commitment to significant schemes that are critical for the long-term success of the company including sale and rental opportunities that would support the continued growth of the company.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Mercury Land Holdings (MLH) Business Plan and budget update 2026/27Report 13 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Havering

Search all
  1. Mercury Land Holdings (MLH) Business Plan and budget update 2026/27This decision
  2. Mercury land holdings governanceAgreed
  3. Mercury Land Holdings Business Plan Update 2025/26Approved
  4. Call-in of an executive decision - proposed loans to mercury land holdings limited (company no: 09878652), for development at former st bernard's day centre, peel way.Decided
  5. Mercury Land Holdings- update to Business Plan 2022/23Approved
  6. Mercury Land Holdings (MLH) in-year Business Plan UpdateApproved

More from Havering Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 AnnouncementsThe Chair outlined the procedures to be followed in the event of a fire alarm or any other emergency requiring the ev... Decided Open
16 Sep 2026 Apologies for absenceAll Cabinet members were in attendance. Decided Open
16 Sep 2026 Disclosures of InterestThere were no disclosures of interest. Decided Open
16 Sep 2026 MinutesThe minutes of the meetings held on 12 th August 2026 , were agreed as a correct record and the Chair signed them. Agreed Open
16 Sep 2026 Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary SchoolReport Title: Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary School ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies