APPROVED as set out in the update sheet; 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Head of Regulatory Services be delegated authority to do so in consultation with the Chair of the Development Control Committee, provided that the changes do not exceed the substantive nature of the committee’s decision
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date 12th December 2016
Application HPK/2016/0476 No: Location Land at Marsh Lane, New Mills Proposal Demolition of existing workshop and development comprising 16 homes for affordable rent; 7 for low cost home ownership and 14 homes for open market sale (37 residential homes in total) (use class C3) with associated access, parking and landscaping’ Applicant The Guinness Partnership Agent P4 Planning Parish/ward Glossop Date registered 20th September 2016 If you have a question about this report please contact: Jane Colley, Tel. 01298 28400 [email protected]
SUMMARY OF RECOMMENDATION
APPROVE
1. REASON FOR COMMITTEE DETERMINATION
1.1This application has been brought before the Development Control Committee because the original application was determined by the Committee.
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2 . 1 The site comprises 0.94 ha of brownfield land. It was originally a stone quarry and some of the features of this former use remain although, for many years, the site has been overgrown, disused and partly filled. 2 . 2 Immediately to the West of the site are a number of large houses fronting Marsh Lane. Access will be taken from Marsh Lane at the North West corner of the site as previously approved. Immediately to the North is a terrace of smaller two-storey cottages which are accessed off Low Leighton Road. 2.2 To the South of the site at a slightly lower level, is the existing Marsh Lane industrial estate that is located in the remaining part of the former quarry. 2.3 There are a number of mature trees along the eastern boundary of the site within the school playing fields and additional trees within the gardens to the West. The self-seeded immature vegetation on site itself
6.1has largely been cleared in preparation for development
3 DESCRIPTION OF THE PROPOSAL
3.1This is a full planning application for Demolition of existing workshop and development comprising 16 homes for affordable rent; 7 for low cost home ownership and 14 homes for open market sale (37 residential homes in total) (use class C3) with associated access, parking and landscaping’
3.2The 37 new homes will comprise the following mix of tenures and sizes:
• 16 affordable rent (twelve 2 bed and four 3 bed properties) • 7 shared ownership (five 2 bed and two 3 bed properties) • 14 open market (two 2 bed and twelve 3 bed properties)
62% of the new homes are therefore affordable. 3.3 Vehicular and pedestrian access will be as previously approved from Marsh Lane. A second pedestrian access will be introduced from the public footpath to the East as identified on the layout plan.
3.4As a part of the development, elements of the former quarry face will be removed and the site levelled to accommodate new homes which will benefit from wide spread views to the hills to the East. 3.5 Full details of the application can be viewed at:
http://planning.highpeak.gov.uk/portal/servlets/ApplicationSearchServle t
4 RELEVANT PLANNING HISTORY
4.1The Site has been subject to previous permissions for housing development over at least the past 20 years, the most recent of which is an extant Outline consent for 28 dwellings (reference HPK/2013/0315). None of the previous permissions have been implemented.
http://planning.highpeak.gov.uk/portal/servlets/ApplicationSearchServle t
5 PLANNING POLICIES RELEVANT TO THE DECISION
High Peak local Plan 2016 S1 – Sustainable Development Principles S1a – Presumption in Favour of Sustainable Development S2 – Settlement Hierarchy
6.2S7 – Buxton Sub-area Strategy CF6 – Accessibility and Transport EQ6 – Design and Place Making
National Planning Policy Framework Paragraph 17 Paragraph 204 Section 7 – Requiring Good Design
6 CONSULTATIONS CARRIED OUT
Site notice Expiry date for comments: 6th October 2016 Neighbour letters Expiry date for comments: 3rd December 2016
Neighbours
Objection
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.