2.1That the committee note the progress information contained within this report. 3. Executive Summary
3.1The purpose of this report is to summarise performance information for the Council’s Internal Audit service for the 2016/17 financial year. This includes a breakdown of audits in progress and completed to date, the number and classification of recommendations made, agreed and where applicable, implemented by management.
3.2All audit recommendations have been agreed, and to date 100% of 2016/17 audit recommendations that are due have been implemented. Where deficiencies in internal control have been identified and not corrected, Internal Audit are satisfied that they will be resolved in an appropriate manner and they will continue to monitor such cases. It should be noted that it is the responsibility of relevant Managers to implement agreed recommendations.
4. How this report links to Corporate Priorities
4.1The assurance provided by the work of Internal Audit informs the Annual Governance Statement and therefore helps to confirm effective use of financial and other resources to ensure value for money.
5. Options and Analysis
5.1There are no options to consider.
6. Implications
6.1Community Safety - (Crime and Disorder Act 1998)
None.
6.2Workforce
None.
6.3Equality and Diversity/Equality Impact Assessment
This report has been prepared in accordance with the Council's Diversity and Equality Policies.
6.4Financial Considerations
None. 6.5 Legal
None.
6.6Sustainability
None.
6.7Internal and External Consultation
None.
6.8Risk Assessment
None.
ANDREW P STOKES Executive Director (Transformation) & Chief Finance Officer
Web Links and Location Contact details Background Papers None N/A John Leak Audit Manager Tel: (01538) 395695 e-mail: [email protected] 7. Background and Detail
7.1Introduction
7.1.1 The purpose of this report is to summarise performance information for the Council’s Internal Audit service for the 2016/17 financial year. This includes a breakdown of audits in progress and completed to date, the number and classification of recommendations made, agreed and where applicable, implemented by management.
7.1.2 The work of the internal audit service is primarily based upon an annual risk assessed audit plan, which for the financial year 2016/17 was agreed by this Committee at the 26th May 2016 meeting. The Internal Audit service also carry out work outside of the audit plan for which a contingency is usually built in. This unplanned work consists mainly of internal control consultancy work and special investigations into suspected fraud and irregularity.
7.2Audits Reports Issued & Status of Agreed Recommendations
7.2.1 A summary of the Audit Reports issued during the period 1st February 2017 to 30th April 2017 is shown in the table below. Further details of these audits outlining key issues and strengths and improvements are shown in Appendix 1.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2016/17 Internal Audit Periodic Report February 2017 to April 2017.Report | 80 KB | DownloadRead as text |
PDF |
6. Appendix 1: SMDC Audit Committee SummaryAppendix | 104 KB | Download |
PDF |
6. Appendix 2: IA SMDC Progress Report to DateAppendix | 64 KB | Download |
PDF |
6. Appendix 3: IA SMDC 2015-16 Audit Recommendations ImplementationAppendix | 62 KB | Download |
Follow Audit & Accounts Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... | Approved | Open |
| 5 Jun 2026 | External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. | Decided | Open |
| 5 Jun 2026 | Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.