Resolved
RESOLVED – That the Council’s annual Internal Audit Plan for 2017/18 be APPROVED .
Audit & Accounts Committee approved this item on Friday 26 May 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the Council’s annual Internal Audit Plan for 2017/18 be APPROVED .
2.1That the committee approve the Council’s annual Internal Audit Plan for 2017/18.
3.1The Public Sector Internal Audit Standards state that the Audit Plan must be based on a documented risk assessment undertaken at least annually and it needs to be flexible in response to changes in the Council’s business, risks, operations, programs, systems and controls. Furthermore, the Standard states that the Audit Manager must communicate the internal audit activity’s plans and resource requirements to senior management and the Audit Committee for review and approval. The Audit Manager must also communicate the impact of resource limitations. This report seeks to address these requirements.
3.2The annual audit plan for 2017/18 has been created and is attached as Appendix 1. This involved a review of the risk scores in accordance with the Audit Service’s established risk assessment methodology to ensure that the most recent changes affecting risk are taken into account. The Internal Audit Plan is a joint Alliance plan designed to make the best use of Alliance resources and to reflect the nature of Council services.
3.3Should any amendments to the audit plan be necessary during the year, these will be reported to Members at future Audit & Accounts Committee meetings.
4. How this report links to Corporate Priorities
4.1The assurance provided by the work of Internal Audit informs the Annual Governance Statement and therefore helps to confirm effective use of financial and other resources to ensure value for money.
5. Options and Analysis
5.1Approve the 2017/18 Audit Plan (Recommended). The Council will have an achievable risk based internal audit plan which is designed to provide assurance that the control environment is effective in achieving the Council’s objectives and is in accordance with Public Sector Internal Audit Standards, and therefore the Accounts and Audit Regulations 2015.
5.2Do not approve the 2017/18 Audit Plan (Not Recommended). The Council will not be complying with the Accounts and Audit Regulations 2015 requirement to “undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance”.
6. Implications
6.1Community Safety - (Crime and Disorder Act 1998)
No implications. 6.2 Workforce
No implications.
6.3Equality and Diversity/Equality Impact Assessment
This report has been prepared in accordance with the Council's Diversity and Equality Policies.
6.4Financial Considerations
No implications.
6.5Legal
No implications.
6.6Sustainability
No implications.
6.7Internal and External Consultation
No implications.
6.8Risk Assessment
The annual audit plan has been prepared in accordance with the Internal Audit Service’s established risk assessment methodology.
ANDREW P STOKES Executive Director (Transformation) & Chief Finance Officer
Web Links and Location Contact details Background Papers None N/A John Leak Audit Services Manager Tel: (01538) 395695 e-mail: [email protected]
7. Background and Detail
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
7. Appendix 1: Audit Plan 2017-18Appendix | 51 KB | Download |
PDF |
Internal Audit: Annual Audit PlanReport | 89 KB | DownloadRead as text |
Follow Audit & Accounts Committee at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2026 | Minutes of the previous meetingThat the minutes of the meeting of the Audit and Accounts Committee held on 13 February 2026 be approved as a correct... | Approved | Open |
| 5 Jun 2026 | External Audit Plan - Grant Thornton. (TOR: External Audit 4)That the update be received. | Decided | Open |
| 5 Jun 2026 | Audit Committee Update - Grant Thornton. (TOR: External Audit 2)That the update be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Progress Report (TOR: Internal Audit 7)That the report be received. | Decided | Open |
| 5 Jun 2026 | Internal Audit Charter (TOR: Internal Audit 1)That the Internal Audit Charter be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.