APPROVED as set out in the report, subject to: a. The completion of a legal agreement to secure the contributions towards off site public open space improvements as set out within the report; b. The conditions as set out in the report; c. The additional conditions as set out in the update sheet; d. An additional condition for construction management. 2. That in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions / informatives / planning obligations or reasons for approval / refusal) prior to the decision being issued, the Operations Manager – Development Services be delegated authority to do so in consultation with the Chair of the Committee, provided that the changes do not exceed he substantive nature of the committee’s decision.
Word for word from the decision High Peak published for this meeting.Source: democracy.highpeak.gov.uk
HIGH PEAK BOROUGH COUNCIL DEVELOPMENT CONTROL COMMITTEE
Date 27th November 2017
Application HPK/2017/0366 No: Location Land off Ellison Street, Glossop Proposal Proposed residential development of 22 no. dwellings together with various infrastructure and landscaping works, following demolition of existing buildings and subsequent site clearance Applicant Pembroke East Ltd Agent PWA Planning Parish/ward Howard Town Ward Date registered 3rd July 2017 If you have a question about this report please contact: Mark Ollerenshaw, Tel. 01538 395400 extension 4921, [email protected]
REFERRAL
The application is referred to committee as it is a major development.
1. SUMMARY OF RECOMMENDATION
APPROVE, subject to completion of a Section 106 Agreement and Conditions
2. DESCRIPTION OF THE SITE AND ITS SURROUNDINGS
2.1The application site is located to the east of Ellison Street and is currently vacant having been previously occupied by Fabricare, an industrial sized laundrette business. There are various vacant buildings and areas of hardstanding and the site therefore constitutes previously developed land. Existing residential properties border the site to north and east (King Edward Avenue and Drovers Walk), whilst Glossop Police Station adjoins the southern boundary of the site. The site takes access off Ellison Street to the west which is to be utilised with relevant improvement works as part of the proposals.
2.2A number of trees on the site were felled before submission of the application, however, none of the trees on the site are protected by a TPO.
2.3The site is within the built-up area boundary of Glossop within relatively close proximity to the Town Centre. The site is not within a conservation area but the boundary of the Norfolk Square Conservation Area is within close proximity to the west of the site. 3. DESCRIPTION OF THE PROPOSAL
3.1This application seeks full planning permission for the erection of 22 no. dwellings following demolition of existing buildings on the site. The proposals include complete site clearance and the construction of 17 no. houses and 5 no. apartments comprising a mix of two, three and four bedroom units, ranging from two to two and half storeys in height, and comprising both linked and semi-detached properties.
3.2The existing access off Ellison Street is to be retained with improvement works proposed and formation of an internal access road to serve the development.
3.3Revised plans were submitted during the course of the application following discussions between officers and the applicant.
3.4The application is accompanied by the following supporting documents: Planning Statement Affordable Housing Statement Design and Access Statement Draft Heads of Terms Drainage Strategy Heritage Statement Land Contamination Assessment Landscape Layout Noise Impact Assessment Phase 1 Habitat Assessment and Bat Survey Report Transport Statement Tree Survey and Report Sustainability Statement Waste and Refuse Statement
3.5Full details of the application can be viewed at:
5. PLANNING POLICIES, GUIDANCE AND OTHER MATERIAL CONSIDERATIONS RELEVANT TO THE DECISION
High Peak local Plan 2016
S1 – Sustainable Development Principles S1a – Presumption in Favour of Sustainable Development S3 – Strategic Housing Development S5 – Glossopdale Sub-area Strategy EQ1 – Climate Change EQ5 - Biodiversity EQ6 – Design and Place Making EQ7 – Built and Historic Environment EQ9 - Trees, woodlands and hedgerows EQ10 – Pollution Control and Unstable Land EQ11 – Flood Risk Management E4 – Change of Use of Existing Business Land and Premises H1 – Location of Housing Development H2 – Housing Allocations H3 – New Housing Development H4 – Affordable Housing CF4 – Open Space, Sports and Recreation Facilities CF6 – Accessibility and Transport CF7 – Planning Obligations and Community Infrastructure Levy
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.