Resolved
That the Minutes of the Meeting held on the 14 th March 2018 be approved as a correct record and signed by the Chair.
Moorlands Partnership Board approved this item on Wednesday 27 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Minutes of the Meeting held on the 14 th March 2018 be approved as a correct record and signed by the Chair.
STAFFORDSHIRE MOORLANDS DISTRICT COUNCIL
MOORLANDS PARTNERSHIP BOARD MEETING Minutes WEDNESDAY, 14 MARCH 2018 PRESENT: Councillor H Sheldon MBE (Chair)
Councillors E Fallows, A Forrester, A Hart, H Jebb, I Lawson, C Pearce and T Riley.
IN ATTENDANCE: J Brooks Regeneration Officer S Hampton Member and Community Services Officer J Percival Finance Business Partner R Tuffrey Principal Regeneration Officer
APOLOGIES: Councillors J Davies and D Shaw.
15 TO APPROVE THE MINUTES FROM THE PREVIOUS MEETING.
RESOLVED: That the Minutes of the Meeting held on the 8th November 2017 be approved as a correct record and signed by the Chair.
16 DISCLOSURE OF INTERESTS:
Agenda No. Member Declaring Nature of Interest Interest Other – A member of the Peak District National Park Planning Committee, a member of Biddulph Town Agenda Item 6 Council, Deputy Chair Cllr A. Hart of Peak Leadership - Projects in Programme, member of Biddulph. the Biddulph Grange Country Park Steering Group and Chair of Biddulph Burial Sub- Committee. Agenda Item 5 Other – Member of - Endon & Stanley Endon and Stanley Interpretation Parish Council and is a Panels Cllr H. Jebb Member of the North - Projects relating to Staffordshire Railway railways Company. Moorlands Partnership Board - 14 March 2018
Other – A member of Biddulph Town Council, Agenda Item 6 Biddulph Grange - Projects in Cllr H. Sheldon Country Park Steering Biddulph Group and Biddulph in Bloom. Agenda Item 5 Other – Owns shares in - Relating to Cllr T. Riley the Cheddleton Cheddleton Railway. Station. Agenda Item 6 Other – Member of - Funerary Cllr E. Fallows Kingsley Parish Monuments Council.
17 FINANCIAL REVIEW AND SUMMARY OF PROJECT ALLOCATIONS 2017/18
The Board received a report introduced by Janice Percival, Finance Business Partner, which provided a financial summary of funding available to the Partnership to allocate during the financial year and included financial tables which provided a summary of grant funding.
RESOLVED - That the report be noted.
18 CURRENT STATUS OF PROJECTS
The Board received a report and presentation on the current status of projects at:-
Bourne Fountain and Butter Cross, Cheadle – Grant £565 now allocated for cleaning
14 Market Place, Leek – Grant application withdrawn
Gazebo, Whitehough, Ipstones - Stone repairs complete, the door and leaded windows to be restored this year
High Street House, Leek – Works completed and grant paid
67 Tape Street, Cheadle - Works delayed and will not commence until 2019.
9 – 11 High Street Dilhorn - Works on going and approximately 50% completed
Endon and Stanley Interpretation - Panel boards complete, lecterns being repaired works to be completed shortly
The Trough, Biddulph - Awaiting commencement
Leekbrook to Leek (Cornhill) heritage rail link - All the survey work was now completed and the planning permission had been submitted. Discussions were being held to identify possible sources of funding to deliver the rail link. Moorlands Partnership Board - 14 March 2018
Leekbrook Station – Works had commenced and part of the grant payment had been made.
Cheddleton Station - A set of plans and proposals for the repair and refurbishment of the building had been completed.
Funerary Monuments – Works had commenced
Members of the Board queried the architect’s survey costs, how the Council had decided which funerary monuments should receive grant funding and if any other funding had been sourced. It was explained that the structures which were considered to be most at risk to the public had been selected for repair and the Council wasn’t seeking additional funding from alternative sources. Five survey quotations from Conservation Accredited Architects had been received and some were more costly than the architect which had been appointed. Some members felt that the Council should contact the Diocese for funding towards the restoration of the funerary moments.
RESOLVED: 1) That the report be noted.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
To Approve the Minutes from the Previous Meeting.Minutes | 93 KB | DownloadRead as text |
Follow Moorlands Partnership Board at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. | Approved | Open |
| 16 Mar 2026 | Summary of ProjectsThat the report be received. | Decided | Open |
| 16 Mar 2026 | Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... | Noted | Open |
| 16 Mar 2026 | Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. | Decided | Open |
| 17 Nov 2025 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.