1) That the report be noted. 2) For the Parish Councils to be contacted to request funding towards funerary monuments and for their assistance in locating the families of the monuments.
Moorlands Partnership Board noted this item on Wednesday 27 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
1) That the report be noted. 2) For the Parish Councils to be contacted to request funding towards funerary monuments and for their assistance in locating the families of the monuments.
1.1That the report is noted.
2.1This report deals with progress to date on those projects awaiting commencement, on site or completed since the last meeting of the Moorlands Partnership Board.
2.2This report is for information but it does offer Members an opportunity to comment on progress.
3 Background and Detail
Projects Update
2011/2012 OFFERS
Bourne Fountain, Cheadle Works are now complete and the grant paid. The fountain has been cleaned, the surrounding setts and paving repointed and the cast iron bollards redecorated.
2015/16 OFFERS
Gazebo, Whitehough, Ipstones The applicant has the builders lined up to start the works but is waiting to discharge his conditions as part of his listed building consent. 2016/17 OFFERS
67 Tape Street, Cheadle Works delayed and will not commence until Oct 2019. At the last meeting the board agreed to honour an extension to the grant offer to meet this date.
9 – 11 High Street Dilhorne Officers previously expressed some concerns over the quality of the repointing and the colour choice for the doors. Much of this has been rectified and a partial grant payment of £3,000 has now been made. £1,000 is being retained until all works are complete (brickwork cleaning) and scaffolding removed.
Endon and Stanley Interpretation panels Repairs complete but awaiting payment.
The Trough – Biddulph Awaiting commencement.
2017/2018 OFFERS
Leekbrook to Leek (Cornhill) heritage rail link Planning permission has now been granted for the reinstatement of the rail link. Draft Heads of Terms are being discussed between the Council and the Churnet Valley Railway (CVR). The full cost for construction of the line is circa £810,000. There is an 18-month construction period that would only commence once funding is confirmed. CVR will be responsible for raising the funding to cover the construction costs. Officers have supported CVR to submit an expression of interest application for £494,750 under the European Agricultural Fund for Rural Development (EAFRD). If successful, a full application will need to be made by September 2018.
Leekbrook Station Works have started on site to restore Leekbrook Station waiting room. The building will be an exact replica of the original and will be finished in the same colour scheme as the adjacent listed signal box. The shell of the building is now erect and the doors and windows are in the process of being fitted. After this, scaffolding will be erected to fit the slated roof and rainwater goods. The building is due for completion in August with an official opening in October.
Cheddleton Station The architect has now completed a set of plans and proposals for the repair and refurbishment of the building. Once the scope of works is agreed the architect will produce a form of tender to issue to potential building contractors. Funerary Monuments The condition survey of all the listed funerary monuments identified as being at risk has been completed and a list of the 4 in the worst condition has been agreed. These are:-
Chest Tombs at Church of All Saints, Dilhorne; Chest Tombs at Church of All Saints, Dilhorne; Prince Memorial Church of St Leonard, Ipstones; and Yates Memorial, Endon.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Current Status of ProjectsReport | 71 KB | DownloadRead as text |
Follow Moorlands Partnership Board at High Peak and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Mar 2026 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. | Approved | Open |
| 16 Mar 2026 | Summary of ProjectsThat the report be received. | Decided | Open |
| 16 Mar 2026 | Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... | Noted | Open |
| 16 Mar 2026 | Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. | Decided | Open |
| 17 Nov 2025 | To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.