Approval of Projects

Agreed Committee 1 paper

Moorlands Partnership Board agreed this item on Wednesday 27 June 2018. Below is the council's own wording, with the papers it was decided on.

Item25

Resolved

a) That a grant of £4,000 ( inc of VAT) be offered towards the external repair of Foxlowe Arts Centre subject to the standard grant scheme conditions and the following technical conditions: · That the relevant listed building consents (if necessary) are obtained prior to executing works on site; and · Given the listed status of the building, a detailed specification for the repair of the building is agreed with the Council prior to obtaining estimates to ensure that the project employs best conservation practices. b) That Members approve a grant of up to £20,000 ( inc VAT) towards the temporary roof covering to Big Mill subject to the standard grant scheme conditions and the following technical condition: · The grant is recovered if the works are not started by 1 August 2018. This will allow the reallocation of the grant before the end of the financial year. c) That members note the completion of a condition survey at Victoria Buildings (Odeon Antiques) and considered an in-principle grant allocation of up to £20,000 towards the repair of the building subject to:- · The submission of a detailed grant application for consideration by the MPB at its November meeting, prior to making a formal grant offer.
Word for word from the decision High Peak published for this meeting. Source: democracy.highpeak.gov.uk

Follow this further

Built from High Peak's papers

What the report saysPro

Report to Moorlands Partnership Board

Recommendations

2.1That Members approve a grant of £4,000 for Foxlowe Arts Centre, Market Place, Leek towards the cost of repairing the external envelope of the building, at an estimated budget of £117,481. The work will be subject to the standard grant scheme conditions and the following technical conditions:-

• That the relevant listed building consents (if necessary) are obtained prior to executing works on site; and • Given the listed status of the building, a detailed specification for the repair of the building is agreed with the Council prior to obtaining estimates to ensure that the project employs best conservation practices.

2.2That Members approve a grant of £20,000 towards a temporary roof covering at Big Mill, Leek. The work will be subject to the standard grant scheme conditions and the following technical conditions:-  The grant is recovered if the works are not started by 1 August 2018. This will allow the reallocation of the grant before the end of the financial year.

2.3Note the completion of a condition survey at Victoria Buildings (Odeon Antiques) and consider an in-principle grant allocation of £26,000 towards the repair of the building subject to:-

 The submission of a detailed grant application for consideration by the MPB at its November meeting, prior to making a formal grant offer.

Summary

3.1This report allows members to consider applications for Environmental Enhancement Grants for funding toward projects within the district.

4. Report

Foxlowe Arts Centre, Leek 4.1 A grant application has been received from the trustees of the Foxlowe Arts Centre in Leek. The property is both listed (Grade II) and falls within the Leek Conservation Area. It commands a prominent location, being located at the head of the Market Place in Leek. Whilst structurally sound, the building’s condition is dilapidating and decaying. In the long term, there are plans to improve the first floor access and increase the size and technical resources of performance spaces. However, they cannot proceed with this until the exterior is repaired and secured. Following on from a very detailed condition survey, the following works are urgently required:-

 Eliminating rot in the roof;  Replacing damaged brickwork, coping and rainwater goods;  Repair/replace rotten window frames; and  Removal of failed cement render and replacement with a suitable lime render.

The overall project budget for the above works is £117,481 (this includes architects and professional fees, VAT and a 10% contingency). The trustees have made a bid of £100,000 to the HLF. The outcome of the bid will be known on 6 July 2018. In order to cover the shortfall the trustees have requested a grant of £4,000 with additional funds being raised from other sources.

The Foxlowe Arts Centre provides a community-led venue for music, theatre and poetry. It provides a gallery for regional arts and craftspeople, heritage exhibitions, a cinema, a self-help garden, a lively café with start-up studios for creative enterprises and a public platform for dozens of existing community groups. It is a well-used and cherished community facility. Recommendation

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval of ProjectsReport 77 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 26 attended
HS
Councillor Hilda Sheldon MBEChair, present
AF
Councillor Arthur ForresterVice-Chair, apologies
RA
Councillor Richard AlcockCommittee Member, absent
AB
Councillor Alan BanksCommittee Member, absent
JD
Councillor Jim DaviesCommittee Member, absent
EF
Councillor Elsie FallowsCommittee Member, present
AH
Councillor Andrew HartCommittee Member, apologies
IS
Councillor Ian S LawsonCommittee Member, present
CP
Councillor Colin PearceCommittee Member, apologies
TR
Councillor Teresa RileyCommittee Member, present
DS
Councillor David ShawCommittee Member, present
EW
Councillor Edwin WainCommittee Member, absent

All 26 on the meeting page

On this subject at High Peak

Search all
  1. Approval of ProjectsThis decision
  2. Approval of Projects.Approved
  3. Approval of Projects.Approved
  4. Approval of Projects.Approved
  5. Approval of Projects.Deferred
  6. Government consultations relating to permitted development rights for shale gas exploration and approvals under the National Significant Infrastructure Projects regimeNoted

More from High Peak Moorlands Partnership Board

All decisions
MeetingDecisionOutcome
16 Mar 2026 To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 17 th November 2025, be approved as correct record. Approved Open
16 Mar 2026 Summary of ProjectsThat the report be received. Decided Open
16 Mar 2026 Financial Summary and Proposed Grant Awards1) The Board noted the financial summary in 3.2 of the report; 2) Members of the Board are APPROVED a maximum grant o... Noted Open
16 Mar 2026 Any Other Business.That some alternative design options and cost for the plaque be presented at the next meeting. Decided Open
17 Nov 2025 To Approve the Minutes from the Previous Meeting.That the minutes of the previous meeting held on 15 July 2025 be approved. Approved Open